Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/03/2014 | SPOWELL1 | START | PLANS SUBMITTED | Completed | |
09/04/2014 | HEATHER THRALL | SIGNS | SIGN CODE REVIEW | Approved | See comments from last review. |
09/10/2014 | JASON GREEN | ENGINEERING | REVIEW | Approved | DATE: September 11, 2014 DUE DATE: October 01, 2014 SUBJECT: QuikTrip #1464 Development Plan Package- 3rd Engineering Review TO: Metro TED; Attn: Lisa Bowers LOCATION: 3200 N Oracle; T13S R13E Sec25 REVIEWERS: Jason Green, CFM ACTIVITY: DP13-0226 SUMMARY: Engineering Division of Planning & Development Services Department has received and reviewed the proposed Development Plan Package, Drainage Report (The WLB Group, 15OCT13, revised 28APR14), Geotechnical Investigation (Speedie and Associates, 17DEC13), Declaration of Establishments of Covenant and Reservations and Title Report. Engineering Division recommends approval of the Development Plan Package at this time. The following items need to be addressed prior to the Final Building Permit approval: SITE PLAN: 1) Restated: AM Sec.2-06.4.9.L: It is acknowledged that a Declaration of Establishments of Covenant and Reservations for the property was submitted and will be signed, notarized and recorded by QuikTrip after approval of the development plan package per their leasing/owner agreements. A hold will be placed on the building plan approval until the SEQ # for this document is submitted to PDSD. 2) AM Sec.2-06.4.9.L: It is acknowledged that a pedestrian easement for the public sidewalk within the ADOT right-of-way will be recorded by QuikTrip after approval of the development plan package per their leasing/owner agreements. A hold will be placed on the building plan approval until the SEQ # for this easement is submitted to PDSD. GENERAL COMMENTS: For any questions or to schedule meetings call me at 837-4929. Jason Green, CFM Senior Engineer Associate Engineering Division Planning & Development Services Department |
09/19/2014 | MICHAEL ST. PAUL | ZONING | REVIEW | Approv-Cond | Recordation an final approval of lot split 14-045 and the recordation of the CC&Rs cross access and cross parking agreement. |
09/25/2014 | RONALD BROWN | ZONING HC | REVIEW | Approved | |
09/30/2014 | JOE LINVILLE | LANDSCAPE | REVIEW | Approved | |
10/01/2014 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Approv-Cond | Once zoning conditions have been met, the plans will be signed and approved. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/14/2015 | KROBLES1 | OUT TO CUSTOMER | Completed |