Review Date Reviewer's Name Type of Review Description Status Comments
10/17/2012 PGEHLEN1 START PLANS SUBMITTED Completed
10/19/2012 PGEHLEN1 ENV SVCS REVIEW Approved ES Solid Waste and Recycling comments from review 1 have been addressed in Revision 2. This project is approved for Solid waste and Recycle.




Jeff Drumm, P.E.
Environmental Manager
City of Tucson Environmental Services
520-837-3713
10/22/2012 STEVE SHIELDS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Planning and Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Park Avenue Housing
Development Package (2nd Review)
DP12-0132

TRANSMITTAL DATE: October 25, 2012

DEVELOPMENT PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

The following comments are based on Development Standard 2-01.0:

1. This comment has not been addressed. D.S. 2-01.3.8.B There is a "5' COMMUNICAITON EASEMENT PER DKT 2716, PG 159 TO BE ABANDONED" shown on sheet 8. This easement will need to abandoned prior to approval of this development package.

2. This comment was not addressed. D.S. 2-01.3.9.A As this proposed project is located on three (3) parcels and a lot combination will be required. Provide a copy of the approved Pima County Combination Request Form with your next submittal.

3. D.S. 2-01.3.9.H.5.d Zoning acknowledges that you wish to use Section C-5.b.iv of the Main Gate UOD and have the proposed Short and long term Bicycle parking design reviewed and approved by the Director. Contact Adam Smith for this review at 520-837-6951 or Adam.Smith@tucsonaz.gov. Provide documentation that this review has been approved with your next submittal.

4. This comment was not fully addressed Demonstrate how the requirements of LUC Section 3.3.9.4.B.3 & 3.3.9.4.D are met. D.S. 2-01.3.9.H.5.d Show the location of the Long-term bicycle parking on the plan and provide a detail the shows how the requirements of LUC Section 3.3.9.4 are met

5. This comment was not addressed. D.S. 2-01.3.9.L There is a proposed "NEW 20' X 14' ELECTRICAL EASEMENT" shown on sheet 8, provide the sequence number on the plan.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.com

Sshield1 on DS1/planning/New Development Package/ DP12-0132

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package & Director review and approval of Short & Long term bicycle parking design.
10/23/2012 ZELIN CANCHOLA COT NON-DSD TRAFFIC Approved
10/24/2012 RONALD BROWN H/C SITE REVIEW Approved
10/24/2012 JENNIFER STEPHENS PIMA COUNTY ADDRESSING Approv-Cond AUDREY FARENGA
ADDRESSING REVIEW
PH #: 740-6800
FAX #: 623-5411


TO: CITY PLANNING
FROM: AUDREY FARENGA, ADDRESSING REVIEW
SUBJECT: DP12-0132 PARK AVE HOUSING/REVISED SITE DEVELOPMENT PACKAGE
DATE: October 24, 2012



The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and we hereby approve this project.

Note: Include all tax codes under Project Data.


1.) Submit a 24 x 36 Reverse Reading Double Matte Photo Mylar or bond paper of approved Development Plan to City Planning. Signed and dated Mylar will be forwarded to Pima County Addressing prior to assignment of addresses.
10/24/2012 PGEHLEN1 DESIGN EXAMINER REVIEW Approved Design Professional comments from review 1 have been addressed in Revision
2. This project *is approved* relative to CDRC Design Professional's
review.
10/25/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Comment not addressed. Provide justification for the size of the grease waste sewer.
2. Comment not addressed. Identify the responsible party for a gravity grease interceptor that could conceivably be supporting multiple tenants.
10/30/2012 JOE LINVILLE LANDSCAPE REVIEW Approv-Cond Approved, subject to TDOT City Engineer approval of improvements in the sidewalk area.
10/30/2012 ELIZABETH LEIBOLD ENGINEERING REVIEW Denied Elizabeth Leibold P.E., Engineering and Floodplain Review, 10/30/2012,
SUBJECT: Park Avenue Housing Campus Acquisitions
DP12-0132, T14S, R14E, SECTION 07

RECEIVED: Development Package
The subject submittal has been reviewed and it can not be approved at this time. Address the remaining comments. Prepare a detailed response that explains the revisions that were made and references the exact location in the drainage report and on the Development Package where the revisions were made:

BASE LAYER SHEET COMMENTS:
1. Provide status of lot combo required for this project.
2. All existing onsite easements shall be drawn on the plan. The recordation information, location, width, and purpose of all easements onsite will be stated. Blanket easements should be listed in the notes, together with recordation data and their proposed status. Should an easement be in conflict with any proposed building location, abandonment of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided (D.S. 2-01.3.8.B). Abandonment documents shall be provided for review and the easement shall be removed from the plans. Provide a recent Title Report.
3. The following information regarding existing private or public right-of-way adjacent to or within the site shall be provided: the name, right-of-way width, recordation data, type and dimensioned width of paving, curbs, curb cuts, and sidewalks (D.S. 2-01.3.8.C). Provide all missing information.
4. All proposed easements (utility, sewer, drainage, access, etc.) are to be dimensioned and labeled as to their purposes and whether they will be public or private (D.S. 2-01.3.9.L). This also applies to the area described in Keynote #11 on Sheet 8 of 21. Clarify if an easement is needed for the generator pad. Additionally, the proposed easement, described in Keynote #12 on Sheet 8 of 21, shall be processed and the recordation information shall be provided on the plan.

Permitting/General Notes:
5. Since the Storm Sewer is mainly in the public right of way, the contact shall be TDOT Permits and Codes and possibly Streets Maintenance. Contact TDOT for additional information and revise the contact information as needed.

Site Plan:
6. Are there and storm drainage facilities on Park Avenue? (D.S. 2-01.3.8.F.). If yes, show them.
7. Provide the dimensions all proposed onsite and offsite sidewalks as required by (D.S. 2-01.3.9.H.4).

Grading Plan:
8. Show the driveway widths and curb radii.
9. According to D.S. 11-01.9.0, the minimum cut or fill setback shall be 2' from the parcel line. Verify compliance with this requirement. Label adjacent existing contour lines.

If you have any questions, I can be reached at 837-4934 or elizabeth.leibold@tucsonaz.gov
RESUBMITTAL REQUIRED: Revised Development Plan Package and comprehensive response letter.
10/30/2012 ELIZABETH LEIBOLD ENGINEERING REVIEW Denied REVISED COMMENTS: 2NOV12
REVIEWER: Elizabeth Leibold P.E., Engineering and Floodplain Review
SUBJECT: Park Avenue Housing Campus Acquisitions
LOCATION: T14S, R14E, SECTION 07
ACTIVITY: DP12-0132

The revised Development Package submittal has been re-reviewed after further discussions with the consultant. Engineering review is sufficient at this time for building plan submittal (applicant would be proceeding at risk if there are any conflicts in easements or other Title Report items). Please note that the Title Report will need to be submitted for Engineering review before consideration of changing from Denied to Approved for Engineering Review status. Please address the remaining comments. Prepare a detailed response that explains the response or revisions that were made and reference the exact location in the drainage report and on the Development Package where the revisions were made:

BASE LAYER SHEET COMMENTS:
1) Provide status of lot combo required for this project.
2) DS 2-01.3.8.B: Easement related comments:
A) Provide a recent Title Report.
B) Abandonment of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided. Abandonment documents shall be provided for review and the easement shall be removed from the plans.
C) All proposed easements shall be processed and the recordation information shall be provided on the plan. Provide the required easement sequence number for the required TEP easement area.

GRADING PLAN:
3) DS 11-01.9: Show offsite grading construction easement for proposed improvements on south portion of project.

FURTHER DISCUSSION:
4) Clarify objective in response letter. If objective is to obtain an approved Development Plan only, without construction (no permit issuance), then the package may be approvable once lot combo is addressed and the Title Report is submitted, reviewed, and found acceptable. The Development Package may be resubmitted with sequence numbers at a later date for grading / construction permitting.

A revised Development Plan Package, Title Report, and comprehensive response letter is required for resubmittal. If you have any questions, I can be reached at 837-4934 or elizabeth.leibold@tucsonaz.gov
10/31/2012 ROGER HOWLETT COT NON-DSD COMMUNITY PLANNING Approved
10/31/2012 PGEHLEN1 PIMA COUNTY WASTEWATER Approved PIMA COUNTY
REGIONAL WASTEWATER RECLAMATION DEPARTMENT
201 NORTH STONE AVENUE
TUCSON, ARIZONA 85701-1207
JACKSON JENKINS PH: (520) 740-6500
DIRECTOR FAX: (520) 620-0135


October 31, 2012

To: GRENIER ENGINEERING, INC.

Thru: Patricia Gehlen, CDRC Manager
City of Tucson Development Services Department


____________________________________________
From: Tom Porter, Sr. CEA (520-740-6719), Pima County Regional Wastewater Reclamation Department

Subject: PARK AVENUE HOUSING
Development Plan - 2nd submittal
DP12-0132

The Pima County Regional Wastewater Reclamation Department (PCRWRD) has reviewed the proposed sewer collection lines for the above-referenced project. The following comments are offered for your use:
The Pima County Regional Wastewater Reclamation Department hereby approves the above referenced submittal of the development plan.
11/01/2012 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied This review has been completed. Revisions are required.
11/01/2012 GARY WITTWER COT NON-DSD TDOT Approved I have reviewed the project for Landscape and Irrigation and have no comments. Nice job.
11/01/2012 KBROUIL1 COT NON-DSD FIRE Approved