Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: DP12-0058
Parcel: 13214078K

Address:
3737 S PARK AV

Review Status: Completed

Review Details: RESUB - SITE/GRADING ALL

Permit Number - DP12-0058
Review Name: RESUB - SITE/GRADING ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/15/2012 RONALD BROWN H/C SITE REVIEW Denied The following comments and requirements are not required because of building area expansion, they are as a result of all modifications made to the site plan that must meet code.
1. How does one access the mobile offices from the 2 new accessible parking spaces?
a. Please provide a large scale detail showing all accessibility requirements from the accessible parking aisle to the front entrance of both mobile units.
b. Please show all accessibility requirements for the two accessible parking spacers including all dimensions, grade slopes, ramp as required, parking aisle, signage and "Van Accessible" assignments.
2. Please show a large scale detail of the accessible route from Ajo Way to the existing buildings.
a. Provide detectable warnings at both ends of all marked crossings.
b. Provide a concrete walk surface as required by Zoning. Reference Zoning comments.
c. Connect the two new 5' wide stripped accessible routes on either side of the storage building.
3. A pedestrian way to the Park Av. right of way may be required by Zoning. This pedestrian way must be accessible. Reference Zoning comments.
4. Show all entry access ways of all existing mobile offices and Storage buildings.
5. Please reference comments of 1st submittal and respond to all comments that have a response of "Not required due to no building area expansion".
END OF REVIEW
10/18/2012 ANDREW CONNOR LANDSCAPE REVIEW Denied 1. According to the approved site plan provided additional buildings are shown on the plan, building square footage expansion has occurred. Provide accurate expansion calculations

2. If the expansion is less than fifty (50) percent, the requirements of the LUC apply only to the proposed expansion area.

3. If the expansion is greater than fifty (50) percent the requirements of the LUC apply to the entire site, all of the landscaping and screening will need to be upgraded.

4. Provide a separate landscape/irrigation plan within information specified within. DS 2-06.

5. Provide the following information:

a. Screening along street frontages for vehicle use area and storage area per LUC Table 3.7.2-I

b. Location, size, and name of existing vegetation to remain in place.

c. Both the proper and common name of each type of plant

6. Within a vehicular use area, one (1) canopy tree is required for each 10 motor vehicle parking spaces and every parking space shall be located within forty (40) feet of the trunk of a canopy tree (as measured from the center of the tree trunk) per LUC 3.7.2.3.A.1.

7.Ensure that all Zoning and Engineering comments and concerns are addressed

8. Additional comments may apply
10/23/2012 ANDREW CONNOR NPPO REVIEW Approved
10/25/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied Comment not resolved. Revise the site drawing to include the location of the building connection to the public sewer. Reference: City of Tucson Development Standard No. 2-01.0.0, Section 3.8 D and Section 103.2.3, UPC 2006.
10/25/2012 STEVE SHIELDS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Planning and Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Camell Motors
Development Package (2nd Review)
DP12-0056

TRANSMITTAL DATE: October 25, 2012

DEVELOPMENT PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Zoning acknowledges that with the removal of structures from the site that this review is no longer full code for the entire site.

2. D.S. 2-01.3.9.H.5.d As you have elected to use the current vehicle parking space requirements you must meet the current bicycle parking requirements. That said per LUC Section 3.3.5.2.B RETAIL TRADE USE GROUP, Construction Material Sales, Furniture, Carpet, or Appliance Store; Heavy Equipment Sales; and Vehicle Rental and Sales, Short-term 2 spaces required, Long-term 2 spaces required

3. D.S. 2-01.3.9.H.5.d Show the required Short & Long term bicycle parking on the plan and provide details that meet the requirements of LUC Sections 3.3.9.2, .3 & .4 on the plan.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.com

Sshield1 on DS1/planning/New Development Package/ DP12-0053

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package.
11/02/2012 PAUL MACHADO ENGINEERING REVIEW Approved