| 01/11/2012 | GBONILL1 | START | PLANS SUBMITTED | Completed | |
| 01/12/2012 | RONALD BROWN | ADA | REVIEW | Passed | |
| 02/02/2012 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Approved | |
| 02/02/2012 | RONALD BROWN | ZONING HC | REVIEW | Denied | 1. Please provide 1 "Van Accessible" parking space with signage, accessible aisle and access to the accessible route. 2. Decomposed granite is not an acceptable pedesttrian accessible route finish material. Please reference zoning comments. END OF REVIEW |
| 02/09/2012 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
| 02/09/2012 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 02/14/2012 | JOE LINVILLE | LANDSCAPE | REVIEW | Denied | 1) Landscaping proposed in right-of-way or MS&R areas must be approved by the City Engineer or designee and comply with the City Engineer's requirements on construction, irrigation, location, and plant type. Provide verification, in writing, of any approvals obtained. Contact Gary Wittwer, DOT Landscape Architect (837-6618) for specific requirements. 2) Revise the landscape plans to include the following standard notes for landscaping in the public right-of-way (if approved): All planting and irrigation that is proposed within the ROW must receive a permit prior to construction. Plans should be submitted to the City of Tucson Permits and Code section at 201 N. Stone, 4th floor. Once the permit has been approved, the applicant must call for a "Blue Stake " prior to the required pre-construction meeting with the City Landscape Architect, and prior to starting any work. It is the property owner's responsibility to keep the Sight Visibility Triangles (SVT), and the pedestrian access area clear of vegetation at all times, per Land Use Code (LUC) section 3.7.2.9. Final plant locations must be in compliance with all utility setback requirements. The owner understands that if the City of Tucson Transportation Department or any utility company needs to work within the ROW in the landscaped area, plants and irrigation may be destroyed without replacement or repair. The property owner assumes full liability for this landscape and irrigation, and any damage to roadway, sidewalk and utilities within the public right-of-way. The only private irrigation equipment that is allowed within the ROW is polyethylene type tubing and emitters that are not under constant pressure. All other equipment except for the water meter must be on site.Standard Notes for Planting in ROW |
| 02/15/2012 | JOSE ORTIZ | COT NON-DSD | TRAFFIC | Approv-Cond | February 15, 2012 ACTIVITY NUMBER: DP12-0008 PROJECT NAME: Headley Midvale Park PROJECT ADDRESS: Midvale at Headley PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering recommends a conditional approval of the Development Plan. The following items must be revised or added to the development plan prior to final approval. 1. Illustrate on the plans whether the sidewalk along Elizabeth Drive and Headley Road will be in public right-of-way or in a pedestrian easement. 2. A private improvement agreement (PIA) will be necessary for the proposed work to be performed within the right-of-way. Callout on the plans that the offsite improvements will be reviewed by TDOT through the PIA review process. If you have any questions, I can be reached at 837-6730 or Jose.Ortiz@tucsonaz.gov |
| 02/15/2012 | MARTIN BROWN | COT NON-DSD | FIRE | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 02/21/2012 | FERNE RODRIGUEZ | OUT TO CUSTOMER | Completed |