Permit Number: D10-0015
Parcel: 14041062A

Review Status: Completed

Review Details: REVISION - DEV PLAN

Permit Number - D10-0015
Review Name: REVISION - DEV PLAN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/31/2010 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
09/15/2010 JASON GREEN ENGINEERING REVIEW Denied DATE: September 14, 2010
SUBJECT: BLM Office Building Revised Development Plan- Engineering Review
TO: Patricia Gehlen, CDRC Manager
LOCATION: 3201 E Universal Way, T15S R14E Sec03 Ward 5
REVIEWERS: Jason Green, CFM
ACTIVITY: D10-0015


SUMMARY: Engineering Division of Planning and Development Services Department has received and reviewed the revised Development Plan Package. Engineering Division does not recommend approval of the Development Plan Package at this time. The following items need to be addressed prior to Development Plan approval:


DEVELOPMENT PLAN:

1) DS Sec.2-01.3.9.R: Refer to comments from Ron Brown, RA Structural Plans Examiner for all handicap accessibility comments that may be associated with this project. Specifically the crosswalk area that is proposed from the building to the sidewalk along the west property line. The location of the pedestrian cross walk can not cross behind parking spaces.

2) DS Sec.2-01.3.9.R: Revise the development plan documents to clearly label and dimension the required 3-foot wide gate for the proposed sidewalk connection at the northwest corner of the site where the Security Fencing crosses the sidewalk location at the property line.

3) DS Sec.2-01.3.9.T: Revise the development plan documents to clearly label and dimension the required clear approach for both proposed refuse container and enclosure location. Per 6-01.4.1.C each service area is required to have a clear approach of fourteen (14) feet by forty (40) feet for the collection vehicle.


GENERAL COMMENTS:

Please provide a revised Development Plan Package that addresses the comments provided above prior to CDRC approval.

For any questions or to schedule meetings call me at 837-4929.



Jason Green, CFM
Senior Engineer Associate
Engineering Division
Planning & Development Services Department
09/15/2010 STEVE SHIELDS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Planning and Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Bureau of Land Management Office Building
Development Package (3rd Review)
D10-0015

TRANSMITTAL DATE: September 15, 2010

DUE DATE: September 30, 2010

DEVELOPMENT PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Section 5.3.8.2, LUC, permits a maximum of one year from the date of application to obtain approval of a development package. If, at the end of that time, the development package has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this development plan is May 13, 2011

2. This development package was reviewed for compliance with the City of Tucson Development Standards (D.S.) and Land Use Code (LUC) for full code compliance.

3. This comment was not addressed provide a copy of the recorded Covenant Regarding Development and Use of Real Property. The Covenant Regarding Development and Use of Real Property must be recorded prior to approval of the development package. As this project comprises two (2) parcels a lot combination is required. Provide a copy of the approved Pima County Combination Request Form and a copy of the recorded Covenant Regarding Development and Use of Real Property with the next submittal.

4. D.S. 2-01.3.9.S The proposed pedestrian circulation, stripped crossing, shown in the northwest parking area, needs to run perpendicular to PAAL and not angled behind vehicle parking spaces.

5. D.S. 2-01.3.9.T It does not appear that adequate vehicle maneuverability has been provided to the refuse collection area.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.com

Sshield1 on DS1/planning/New Development Package/ D10-0015
RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package, recorded Covenant Regarding Development and Use of Real Property.



CDRC TRANSMITTAL

TO: Planning and Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Bureau of Land Management Office Building
Development Package (35d Review)
T10BU00794

TRANSMITTAL DATE: September 15, 2010

DUE DATE: September 30, 2010

GRADING PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning cannot approve the grading plan until the development package has been approved.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.com

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
09/16/2010 DAVID MANN COT NON-DSD FIRE Denied Fire Comments:

The new gate prevents fire access. A fire key box will be required and the gate must meet IFC 503.6.2 as amended.
09/22/2010 RONALD BROWN ZONING HC REVIEW Denied There are too many variables shown on the site plan that effect accessibility. A meaningful accessibility review is not possible. Please submit a complete drafted, to scale site plan showing all proposed design changes proposed.
END OF REVIEW
09/30/2010 JOHN WILLIAMS ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
PLANNING & DEVELOPMENT SERVICES

September 30, 2010

Tri Miller
Rick Engineering Inc.
3945 E. Fort Lowell Road, #111
Tucson, Arizona 85712

Subject: D10-0015 BUREAU OF LAND MANAGEMENT OFFICE
Development Package

Dear Tri:

Your submittal of April 22, 2010 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and 6 sets of the DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLACKLINES MUST BE FOLDED

6 Copies Revised Development Package (Engineering, Zoning, Fire, Zoning HC, PDSD)

2 Copies Recorded Covenant (Zoning, PDSD)


Should you have any questions, please call me at 837-4917.

Sincerely,





John Williams
Planning Technician

All comments for this case are available on our website at http://www.tucsonaz.gov/dsd/

Via fax: (520) 322-6956
09/30/2010 JOE LINVILLE LANDSCAPE REVIEW Approved