Permit Number: D10-0015
Parcel: 14041062A

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - DEV PLAN

Permit Number - D10-0015
Review Name: RESUBMITTAL - CDRC - DEV PLAN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/30/2010 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
07/08/2010 JASON GREEN ENGINEERING REVIEW Approv-Cond DATE: July 8, 2010
SUBJECT: BLM Office Building Development Plan Core Review- 2nd Engineering Review
TO: Patricia Gehlen, CDRC Manager
LOCATION: 3201 E Universal Way, T15S R14E Sec03 Ward 5
REVIEWERS: Jason Green, CFM
ACTIVITY: D10-0015


SUMMARY: Engineering Division of Planning and Development Services Department has received and reviewed the proposed Development Plan Package, Drainage Report (Rick Engineering Company, Inc., 12MAY10), Geotechnical Engineering Report (Terracon Consultants, Inc., 18MAR10) and Stormwater Pollution Prevention Plan (Rick Engineering Company, Inc., 13MAY10). Engineering Division recommends conditional approval of the Development Plan Package at this time. The following items need to be addressed prior to final CDRC approval:

DRAINAGE STATEMENT:

1) DS Sec.10-01.2.1: Acknowledged. However the discussion within the Drainage Report, Section 3.2, should clearly explain why the 2 year event can not be reduced by 15%. The response in the letter provided is acceptable, but it must be stated in the report section so that future reviewers or applicants can understand why the City allowed a deviation from the Development Standards.

2) Complied.

DEVELOPMENT PLAN:

3) Complied.

4) Complied.

5) Complied.

6) Complied.

7) Complied.

8) Complied.

9) DS Sec.2-01.3.9.N.3: Acknowledged. However the development plan documents must be revised to clearly label Keynote 16 in plan view. Plan view on Sheet 5 calls out Keynote 17, which does not exist in the Keynote Legend.

10) Complied.

11) Complied.

12) Complied.

13) Complied.

14) Complied.

15) Complied.

STORMWATER POLLUTION PREVENTION PLAN:

16) Complied.

17) Complied.

GENERAL COMMENTS:

Please provide a revised Development Plan Package that addresses the comments provided above prior to final CDRC approval.

For any questions or to schedule meetings call me at 837-4929.



Jason Green, CFM
Senior Engineer Associate
Engineering Division
Planning & Development Services Department
07/16/2010 FERNE RODRIGUEZ PIMA COUNTY WASTEWATER Approved To: TRI MILLER
RICK ENGINEERING

Thru: Patricia Gehlen, CDRC Manager
City of Tucson Development Services Department


____________________________________________
From: Tom Porter, Sr. CEA (520-740-6719), Pima County Regional Wastewater Reclamation Department

Subject: BUREAU OF LAND MANAGEMENT OFFICE BUILDING
LOTS 62 & 63 OF AIRPORT COMMERCE CENTER
Dev. Plan – 2nd Submittal
D10-0015


The Pima County Regional Wastewater Reclamation Department (PCRWRD) has reviewed the proposed sewer collection lines for the above-referenced project. The following comments are offered for your use:
The Pima County Regional Wastewater Reclamation Department hereby approves the above referenced submittal of the development plan as submitted.
This comment letter has been reviewed and accepted for substantial conformance to Pima
County Code Title 13 by:

___________________________
Chad Amateau, P.E., Civil Engineer
PCRWRD, Planning Services Section, Development Liaison Unit

cc: Chad Amateau, PE
Kristin Borer, PE, DLU Manager
DLU Project folder
07/26/2010 RONALD BROWN ZONING HC REVIEW Approved
07/28/2010 STEVE SHIELDS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Planning and Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Bureau of Land Management Office Building
Development Package (2nd Review)
D10-0015

TRANSMITTAL DATE: July 28, 2010

DUE DATE: July 29, 2010

DEVELOPMENT PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Section 5.3.8.2, LUC, permits a maximum of one year from the date of application to obtain approval of a development package. If, at the end of that time, the development package has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this development plan is May 13, 2011

2. This development package was reviewed for compliance with the City of Tucson Development Standards (D.S.) and Land Use Code (LUC) for full code compliance.

3. The Covenant Regarding Development and Use of Real Property must be recorded prior to approval of the development package. As this project comprises two (2) parcels a lot combination is required. Provide a copy of the approved Pima County Combination Request Form and a copy of the recorded Covenant Regarding Development and Use of Real Property with the next submittal.

4. This comment was not addressed correctly. The floor area ratio (FAR) is a ratio expressing the amount of square feet of floor area permitted for every square foot of land area within the site. That said the FAR for the I-1 area of the site is 2.0 or 2.0 x 88,685 (97% of the site area 91,428) = 177,370 allowed FAR, proposed FAR = the total proposed floor area. Until comment 6 is addressed the proposed FAR cannot be verified.

5. D.S. 2-01.3.9.H.5.a & d Until comment 6 is addressed the vehicle and bicycle parking calculation cannot be verified.

6. D.S. 2-01.3.9.Q Sheet 1, under "PARKING CALCULATION #3 Vehicle" shows "PROFESSIONAL OFFICE USE : 14,708 SF (9,755 SF OFFICE + 4,953 SF WAREHOUSE = 14,708 SF TOTAL". Sheet 4 within the building foot print shows "GFA 14,708 SF" "OFFICE USE 13,400 SF" " STORGAE USE GFA 4,953 SF". Clarify what office square footage is correct and revise all applicable calculations.

7. Zoning acknowledges the provided agreement. Provide the recordation information, docket and page on the plan. D.S. 2-01.3.9.R There is a proposed sidewalk shown running along the west side of the parcel that extends up to Valencia Road. Provide a pedestrian access easement across the property to the north. Show the easement graphically on the plan along with the recordation information. For your information this is not a required sidewalk.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.com

Sshield1 on DS1/planning/New Development Package/ D10-0015
RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package, recorded Covenant Regarding Development and Use of Real Property.



CDRC TRANSMITTAL

TO: Planning and Development Services Department
Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Bureau of Land Management Office Building
Development Package (2nd Review)
T10BU00794

TRANSMITTAL DATE: July 28, 2010

DUE DATE: July 29, 2010

GRADING PLAN COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning cannot approve the grading plan until the development package has been approved.

If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.com

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
07/29/2010 JOHN WILLIAMS ZONING-DECISION LETTER REVIEW Approv-Cond COMMUNITY DESIGN REVIEW COMMITTEE
PLANNING & DEVELOPMENT SERVICES


July 29, 2010

Tri MIller
Rick Engineering Company, Inc.
3945 E. Fort Lowell Road # 111
Tucson, Arizona 85712

Subject: D10-0015 Bureau of Land Management Office Building Development Package

Dear Tri:

The above referenced development plan has been CONDITIONALLY APPROVED by the Community Design Review Committee. Once the necessary corrections are made per Zoning, Engineering, please submit the following documents for sign-off.

1 Rolled blue line COMPLETE SET of the Development Plan, Landscape Plan, and the Native Plant Preservation Plan (if part of the original submittal). Please include applicable sheets from any other concurrent reviews.

1 CD that contains all of the drainage/hydrology and other reports submitted for the review and approval of this plan.

Additional black line copies will be made from the complete set and distributed to various review agencies for their files. These copies will be ordered from the City's contracted print company and billed to you unless you already have an account at another printing company. Please let us know which printing company you would prefer to use and list them on your attached transmittal form when submitting your mylars to the CDRC office for sign-off approval.

PLEASE HAVE THE CITY OF TUCSON APPROVAL STAMP PLACED ON EACH SHEET OF THE SUBMITTAL SET, PREFERABLY IN THE LOWER RIGHT HAND CORNER NEAR THE TITLE BLOCK. THE STAMP IS LOCATED AT http://www.tucsonaz.gov/dsd/CDRC___Rezoning/CDRC/CDRC_Stamp/cdrc_stamp.html.
BLUELINE SETS THAT DO NOT HAVE THE STAMP WILL BE RETURNED FOR CORRECTION.

*** Please send PDF's to Steve Shields (Steve.Shields@tucsonaz.gov)
PRIOR to submitting to the CDRC office***

Should you have any questions, please call me at 837-4917.

Sincerely,





John Williams
Planning Technician

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/