Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - CDRC - DEV PLAN
Permit Number - D08-0019
Review Name: RESUBMITTAL - CDRC - DEV PLAN
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/14/2008 | FERNE RODRIGUEZ | START | PLANS SUBMITTED | Completed | |
08/15/2008 | JIM EGAN | COT NON-DSD | FIRE | Approved | |
08/19/2008 | STEVE SHIELDS | ZONING | REVIEW | Approv-Cond | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Lead Planner PROJECT: Holiday Inn Express - Wilmot & I-10 D08-0019 Development Plan (2nd Review) TRANSMITTAL DATE: August 19, 2008 DUE DATE: September 12, 2008 COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. The Zoning Review Section conditionally approves the development plan for this project, subject to the following changes on the sign-off copies. However, should there be any changes requested by other CDRC members, the Zoning Review Section approval is void, and we request copies of the revised development plan to verify that those changes do not affect any zoning requirements 2. Provide a copy of the signed approved tentative plat for this subdivision, S07-0025, with your next submittal. The provided tentative plat has not been signed by CDRC. 3. This comment has not been addressed. Per the development plan submitted for "EXCLUDED 1" there is PAAL access across the parcels lines. D.S. 2-05.2.4.D.3 Provide an overall plan showing how the proposed parking area access lanes (PAALs) that cross over property lines will work. Provide a copy of the cross access agreements required by the rezoning. 4. Additional comments may be forth coming depending on how each comment has been addressed. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956. C:\planning\cdrc\developmentplan\D08-0019dp-2nd.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan and additional requested documents. |
08/20/2008 | FERNE RODRIGUEZ | PIMA COUNTY | WASTEWATER | Denied | August 19, 2008 To: TONY TSANG A.C. TSANG ENGINEERING GROUP, INC. Thru: Patricia Gehlen, CDRC Manager City of Tucson Development Services Department ____________________________________ From: Tom Porter, Sr. CEA (520-740-6579), representing the Pima County Departments of Wastewater Management and Environmental Quality Subject: HOLIDAY INN EXPRESS Development Plan – 2nd Submittal D08-019 The proposed sewer collection lines for the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use. The improvement plan(G2007-085 ) does not show the BCS in the same location as shown on this plan. Either change this on the improvement plan or change it here on the development plan so that the two plans match. Also the lot lines and lot numbers shown on the improvement plan will need to be revised to match the Final Plat. Currently they do not match. We have sent to your office via e-mail, a .pdf file containing a Sewer Service Agreement for the proposed number of wastewater fixture unit equivalents. Three originals will need to be printed out from this file for notarized signatures by the Owner of Record. The three signed originals of the Agreement must be returned to this office in order to satisfy the necessary requirements needed to approve the Mylars of thedevelopment plan . This office will require a revised set of bluelines, and a response letter, addressing these comments. Additional comments may be made during the review of these documents. Pima County Code Title 13.20.030.A.2 requires that a wastewater review fee be paid for each submittal of the development plan. The fee for the first submittal is $166 plus $50 per sheet. For the second submittal, the review fee is $50 per sheet. For all subsequent submittals, the review fee is $39 per sheet. The next submittal of this project will be the third(3rd ) submittal. A check for the review fee of this submittal in the amount of $39.00 (made out to PIMA COUNTY TREASURER) must accompany the revised set of bluelines and response letter. If the number of sheets changes, please adjust the review fee accordingly. If you have any questions regarding the above mentioned comments, please contact me . |
08/28/2008 | PETER MCLAUGHLIN | LANDSCAPE | REVIEW | Approved | |
09/04/2008 | ROGER HOWLETT | COT NON-DSD | COMMUNITY PLANNING | Approved | |
09/12/2008 | ELIZABETH EBERBACH | ENGINEERING | REVIEW | Denied | DATE: September 12, 2008 TO: Patricia Gehlen; CDRC Coordinator FOR: A. C. Tsang Engineering SUBJECT: Wilmot/I-10 Holiday Inn Express 2nd submittal Engineering Review REVIEWER: Elizabeth Eberbach ACTIVITY NUMBER: D08-0019 SUMMARY: The revised Development Plan was reviewed by Engineering as part of the development for the Wilmot I-10 Commercial Center. The package included the Development Plan for the Holiday Inn Express, copies of the Tentative & Final Plat, the revised drainage report with response letter, and landscape plans. Development Services Department Engineering Division does not recommend approval of the Development Plan at this time. The drainage report was reviewed for Development Plan purposes only. DEVELOPMENT PLAN COMMENTS: 1) City of Tucson Development Standards (DS) Section No. 2-05.2.3.I.1, 2-05.2.3.E.1, 2-05.2.4.H, & 10-02.2.3.1.5, 10-02.1.5: Address the remaining drainage comments for the development plan and drainage report: a) Clarify pedestrian access area across basin showing grades/slopes. Revise elevations to reflect scupper crossing at pedestrian crossing for basin. Scuppers are required for sidewalks. b) Clarify basin outlets for offsite discharge areas. Revise Basin A details on sheet 3. c) Clarify types of off-site runoff acceptance points and/or on-site runoff discharge points on planview. It is unclear where the basin outlet flow is to be directed. d) Show basin maintenance access on planview. Access ramp is in conflict with proposed outlet structure slopes. Revise basin design to match drainage report. e) For the proposed roof drainage from north and south sides, show where sidewalk scuppers will be needed at north and south sides of sidewalks, and provide calculations in report. f) Provide information on planview showing provision for water harvest areas. Show curb inlet and spot elevations or flow arrows where landscape areas receive water harvest stormwater flows. g) Planview sheets for the development plan shall match drainage exhibits. 2) DS Sec.2-05.3.2.D, 2-05.1.1: In response letter, explain how Rezoning condition 26 is addressed for this project. Clarify access improvements to be completed prior to Holiday Inn Express C of O. Also address any revised TIA requirements and explain in response letter how the access will be provided for this use. 3) DS Sec.2-05.2.4.D.4: Access is indicated with pavements areas through this project, and only the north access easements is delineated and dedicated for such use. For this and other private easements, protective covenants establishing the right of access and incorporation of future phases into this project are required. 4) DS Sec.2-05.2.4.G: Further clarify the following easements: a) Delineate clearly the easements on the plan view sheet to differentiate the private stormdrain, flowage, basin access & Maintenance Easement from other entities on the sheet. b) Include the 24-ft Private Stormdrain, Flowage, Basin Access & Maintenance Easement. 5) DS Sec.2-05.2.4.L: Further clarify the following elements: a) Clarify truncated domes for the proposed southside of the pedestrian accessible walkway at the south pavement area. b) Clarify widths of all pedestrian walkways and sidewalks. Not all are labeled with widths. c) Clarify locations of all curb (with type of curb) on planview. d) Clarify elevations for each element, distinguishing between top of curb and pavement elevations. This may be clarified with legend or planview. 6) DS Sec.2-05.2.4.R: Show and dimension SVT's for all access points on planview. Submit the revised Development Plan addressing all of the comments. Include the revised development plan, the revised drainage report, the revised Final Plat block plat, copy of rezoning conditions, copy of cross access agreement, and response letter thoroughly explaining each comment. If you have questions or would like to set up a meeting, call me at 837-4934. Elizabeth Eberbach, PE Civil Engineer Engineering Division Development Services |
09/15/2008 | KAY MARKS | PIMA COUNTY | ADDRESSING | Approved | 201 N. STONE AV., 1ST FL TUCSON, AZ 85701-1207 JENNIFER STEPHENS ADDRESSING OFFICIAL PH: 740-6480 FAX #: 740-6370 TO: CITY PLANNING FROM: JENNIFER STEPHENS, ADDRESSING OFFICIAL SUBJECT: D08-0019 HOLIDAY INN EXPRESS/REVISED DEVELOPMENT PLAN DATE: 9/12/08 The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and we hereby approve this project. 1.) Submit a 24 x 36 Reverse Reading Double Matte Photo Mylar of approved Development Plan to City Planning. Signed and dated Mylar will be forwarded to Pima County Addressing prior to assignment of addresses. 2.) All addresses will need to be displayed per Pima County Address Standards at the time of final inspection. ES |
09/15/2008 | GLYNDA ROTHWELL | UTILITIES | TUCSON ELECTRIC POWER | Approved | 4350 E. Irvington Road, Tucson, AZ 85714 Post Office Box 711, Tucson, AZ 85702 WR#195232 September 12, 2008 A.C.Tsang Engineering Group Attn: Antony C.Tsang 4626 E. Fort Lowell Ste S Tucson, AZ 85712 To Antony Tsang: SUBJECT: Holiday Inn Express - Resubmittal D08-0019 Tucson Electric Power Company has reviewed and approved the development plan submitted September 3, 2008. It appears that there are no conflicts with the existing facilities within the boundaries of this proposed development. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. The customer is responsible for the new trenching to relocate them as well as the relocation cost. In order to apply for electric service, call the New Construction Department at (520) 918-8300. Submit a final set of plans including approved site, offsite and electrical load plans. Include a CD with the AutoCAD version of the plans. If easements are required, they will be secured by separate instrument. Your final plans should be sent to: Tucson Electric Power Company Attn: Ms. Mary Boice New Business Project Manager P. O. Box 711 (DB-101) Tucson, AZ 85702 520-917-8732 Please call the area Designer Warren McElyea at (520) 918-8268, should you have any questions. Sincerely, Henrietta Noriega Office Specialist Design/Build hn Enclosures cc: City of Tucson, (Email only) W. McElyea, Tucson Electric Power |
09/16/2008 | TOM MARTINEZ | OTHER AGENCIES | AZ DEPT TRANSPORTATION | Approved | DSD_CDRC.DSPO2.CHDOM2@tucsonaz.gov |
09/17/2008 | ANDY VERA | ENV SVCS | REVIEW | Approv-Cond | 1. Solid waste enclosure on the north side does not provide the minimum required 14 ft x 40 ft approach nor allow the collection vehicle to position itself perpendicular to the enclosure. Enclosure needs to be positioned at a 30 degree angle and demonstrate adequate maneuverability into approach. 2. Recommend moving the north enclosure and positioning it directly west of the south enclosure so face each other in a mirror image perspective. This will allow a more adequate central location for collection and user. Please provide corrections as noted above. If you have any questions you may contact Andy Vera at (520) 791-5543 ext 1212 or e-mail: Andy.Vera@tucsonaz.gov |
09/17/2008 | JOSE ORTIZ | COT NON-DSD | TRAFFIC | Denied | September 17, 2008 ACTIVITY NUMBER: D08-0019 PROJECT NAME: Holiday Inn PROJECT ADDRESS: 7648 S Wilmot Rd PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the Development Plan; therefore a revised Development Plan is required for re-submittal. The following items must be revised or added to the development plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. The development plan needs to schematically illustrate the required off-site improvements that will be designed for in the private improvement agreement (PIA). DSD requires that any off-site improvements associated with a development be illustrated on the development plan. Again, a schematic layout of the off-site improvements are acceptable at this time, but need to be illustrated to ensure that there are no adverse impacts to the adjacent properties. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
09/18/2008 | PGEHLEN1 | OTHER AGENCIES | PIMA ASSN OF GOVTS | Passed | |
09/24/2008 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Denied | COMMUNITY DESIGN REVIEW COMMITTEE DEVELOPMENT SERVICES September 24, 2008 Antony C. Tsang A.C. Tsang Engineering Group, Inc. 4626 East Fort Lowell Road, Suite S Tucson, Arizona 85712 Subject: D08-0019 Holiday Inn Express Development Plan Dear Tony: Your submittal of August 14, 2008 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed: ALL BLACKLINES MUST BE FOLDED 6 Copies Revised Development Plan (Wastewater, Zoning, Traffic, ESD, Engineering, DSD) 3 Copies Revised Landscape Plan (Zoning, Engineering, DSD) 2 Copies Revised Drainage Report (Engineering, DSD) 2 Copies Cross Access Agreement (Engineering, DSD) Should you have any questions, please call me at 837-4919. Sincerely, Patricia Gehlen CDRC Manager All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/ Via fax: 325-0979 |