Permit Number: D08-0010
Parcel: 133452190

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - CORE REVIEW

Permit Number - D08-0010
Review Name: RESUBMITTAL - CDRC - CORE REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/17/2008 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
09/19/2008 STEVE SHIELDS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department Plans Coordination Office

FROM: Steve Shields
Lead Planner

PROJECT: Eastpoint Commercial Center - Core Review
D08-0010
Development Plan (3rd Review)

TRANSMITTAL DATE: October 16, 2008

DUE DATE: October 15, 2008

COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Section 5.3.8.2, LUC, permits a maximum of one year from the date of application to obtain approval of a development plan. If, at the end of that time, the development plan has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this development plan is January 23, 2009.

2. After discussions with Pete Salonga, P.E. it has been determined that due to changes in the proposed uses that will require a change in the parking calculation a re-submittal of the development plan is required.

3. Depending on how the above comments are addressed additional comments may be forth coming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956.

C:\planning\cdrc\developmentplan\D08-0010dp-3rd.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan and additional requested documents.
09/30/2008 FERNE RODRIGUEZ PIMA COUNTY WASTEWATER Approved September 30, 2008

To: Peter Salonga
Oracle Engineering

Thru: Patricia Gehlen, CDRC Manager
City of Tucson Development Services Department

___________________________
From: Tom Porter, Sr. CEA (520-740-6579), representing the Pima County
Departments of Wastewater Management and Environment Quality

Subject: Eastpointe Commercial Center, Lots 1-5
Dev. Plan – 3rd Submittal
D08-010


The proposed sewer collection lines for the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use.

The Pima County Department of Environmental Quality and Wastewater Management Department hereby approve the above referenced submittal of the development plan as submitted.

Please note the following: Approval of the above referenced submittal does not authorize the construction of public or private sewer collection lines, or water distribution lines. Prior to the construction of such features, a Construction Authorization (Approval To Construct) may need to be obtained from the Pima County Environmental Quality.

Also, air quality activity permits must be secured by the developer or prime contractor from the Pima County Department of Environmental Quality before constructing, operating or engaging in an activity which may cause or contribute to air pollution.


If you have any questions regarding the above-mentioned comments, please contact me.
10/14/2008 ANDY VERA ENV SVCS REVIEW Approv-Cond ES approves of this DP under the folling condition:

1. Sheet 4, The enclosure east of building 3 needs to be positioned so that it does not impede the continuous flow of traffic for collection vehicle. DS 6-01.4.1.H.

Please provide correction as mentioned above.

If you have any questions you may contact Andy Vera at (520) 791-5543 ext 1212 or e-mail: Andy.Vera@tucsonaz.gov
10/16/2008 JOE LINVILLE LANDSCAPE REVIEW Approv-Cond Revise the application to address preservation of the existing barrel cactus near the northern boundary of the site. The proposed retaining wall may impact the survival of these protected plants. We suggest that these be shown on the landscape plan. Assuming the cati can be preserved through the construction process, the current location of the cacti will even be less consistent with the requirement to locate protected native plants in locations able to support their long term health and viability, due to the additional shading created by the retaining wall.
10/21/2008 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

October 21, 2008

Peter Salonga
Oracle Engineering Group, Inc.
199 East Fort Lowell Road
Tucson, Arizona 85705

Subject: D08-0010 Eastpoint Commercial Center Development Plan

Dear Peter:

Your submittal of September 17, 2008 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLACKLINES MUST BE FOLDED

3 Copies Revised Development Plan (Zoning, ESD, DSD)

2 Copies Revised Landscape Plan (Zoning, DSD)





Should you have any questions, please call me at 837-4919.



Sincerely,



Patricia Gehlen
CDRC Manager

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/

Via fax: 292-6144
dp-resubmittal
10/21/2008 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied March 9, 2010

Peter Salonga
Oracle Engineering Group, Inc.
199 East Fort Lowell Road
Tucson, AZ 85705


SUBJECT: CLOSURE OF CDRC FILE


Development Plan

Per Section 5.3.8.2.A, Expiration Dates, of the Land Use Code, "an applicant has one (1) year from the date of application to obtain approval of a development plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A development plan application that has been in review for a period of one (1) year which has not been approved is considered denied. To continue the review of a development plan for the property, a new development plan which complies with regulations in effect at that time must be submitted. The new submittal initiates a new one (1) year review period."

Case # Case Name DSD Transmittal Date

D08-0010 Eastpoint Commercial Center February 14, 2008

Please note that this case has been closed and that, in order to continue review of the project, new development plan/tentative plat application is required which comply with regulations in effect at the time of the new submittals. CDRC members should be advised of their ability to review the new applications per the current regulations.

Thank you for your assistance.

Sincerely,



Patricia Y. Gehlen
CDRC Manager


xc: CDRC file D08-0010