Permit Review Detail
Review Status: Completed
Review Details: DEVELOPMENT PLAN
Permit Number - D07-0014
Review Name: DEVELOPMENT PLAN
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/10/2007 | FERNE RODRIGUEZ | START | PLANS SUBMITTED | Completed | |
04/12/2007 | LAITH ALSHAMI | ENGINEERING | REVIEW | Denied | Laith Alshami, Engineering and Floodplain Review, 05/17/2007, TO: Patricia Gehlen FROM: Laith Alshami, P.E. CDRC Engineering SUBJECT: Sorrento Square Retail Center D07-0014, T14S, R15E, SECTION 26 RECEIVED: Development Plan, Landscape Plan, and Drainage Report on April 11, 2007 The subject submittal has been reviewed. We offer the following comments. Prepare a detailed response that explains the revisions that were made and references the exact location in the drainage report and on the Development Plan where the revisions were made: Drainage Report: 1. The wash that crosses the southwestern corner of the parcel is designated as "Xeroriparian Intermediate Habitat". Identify the wash as such in the report. Additionally, it appears that the proposed improvements encroach slightly on the 100-year floodplain, which requires compliance with the provisions of Development Standard 2-13.0. Verify compliance with the said Standard and coordinate the work with the Landscape Section. Additionally, show on Figure 4 the wash pre and post development water surface elevations. 2. It is not clear if the erosion hazard setback lines are shown from the top of bank or from the 100-year floodplain limit. Clarify. 3. Revise Table 2 to include Watershed 220D. 4. It appears that Detention Basin "A" hydraulic information was not summarized in a table. Revise. 5. It appears that the proposed delay in peak discharges caused by the proposed detention basins might worsen the floodplain situation downstream. Address this issue and revise as necessary. 6. Provide in the text or on the drainage exhibit (Figure 4) the location of the proposed scuppers and curb openings. 7. The maintenance checklist shall be revised to include all proposed drainage structures within this development. 8. Since the upstream watershed is not designated as balanced or critical, the developments within the watershed are not expected to provide runoff detention. Accordingly, in order to determine the offsite runoff impact on this parcel, this development shall assume that the upstream parcels shall be fully developed, in accordance with their zoning. Revise the Hydrologic data sheets, the HEC RAS analysis and the overall drainage scheme accordingly. 9. It appears that the discharge, in watershed 100D, at the high point within the PAAL, travels north towards Golf Links. Explain if that is the case or clarify how that part of the runoff ends up at concentration point 100D. 10. If drainage is going to be concentrated in the P.A.A.L's, provide hydraulic ratings for them. 11. The drainage report shall recommend the finished floor elevations for the proposed buildings. 12. Show on Figure 4 additional flow arrows and spot grade elevations including grade breaks. 13. Show on Figure 4 the proposed drainage structure dimensions (i.e. the erosion control pads and spillways, maintenance access ramps and basin dimensions, etc.) P.A.A.L's, pipe basin sides and maintenance ramp slopes, drainage structure elevations (i.e. flow line and pipe invert elevations, etc.). 14. Show on Figure 4 all proposed drainage solutions/structures with all required details (i.e. type, materials, location, size and dimensions, slopes, grades, high and low points, water ponding and slope setback lines, retention/detention basins inlet details, waterharvesting basins, surface flow arrows, finished floor elevations, cross section locations and details, etc.) that would clarify how the proposed drainage scheme will work. The drainage information shown on the tentative plat and grading plan will be based on the information provided in the drainage report text and drainage exhibits. The information may be tabulated on Figure 4. 15. Water harvesting techniques shall be incorporated into the development by conveying surface flow and rooftop drainage to designated water harvesting areas. Please address, in more details, how water-harvesting techniques will be incorporated into the development. Refer to the newly adopted City of Tucson Water Harvesting Guidance Manual for design considerations. Copies of the above-referenced manual can be obtained from the Engineering Counter. Additionally, specify in the water harvesting section that landscaped areas shall be depressed a maximum of 6" for water harvesting. Please be advised that aggressive water harvesting may significantly reduce the volume of retention required. Please provide either an appropriately sized retention basin and/or a detailed water-harvesting plan. 16. The drainage report does not address roof drainage and sidewalk scuppers except for the proposed basins. According to D.S. 2-05.2.4.H.3. and D.S. 3-01.4.4.F. 10-year flow has to be completely conveyed under sidewalks when concentrated runoff crosses any sidewalk/walkway. Additionally, show the roof drainage direction on the drainage exhibit and provide sidewalk scuppers for the roof drains. Please be advised that the 10-year flow requirement does not apply to roof drainage. Roof drainage has to be discharged in its entirety to avoid prolonged ponding on the roof that might cause the roof to collapse. Demonstrate compliance with the sidewalk scupper requirement including design calculations. 17. Verify that Basin "A" discharge will not be concentrated, which might create an erosion problem within the downstream parcel. The discharge shall, at minimum, match the pre development conditions. 18. The HEC RAS analysis shall utilize the same contour map for existing and proposed conditions. Using Figure 3, which has less elevation contour information, for existing conditions is not acceptable. 19. It is not clear if the proposed detention/retention basins require security barriers as required by the "Stormwater Detention/Retention Manual". Revise as necessary and refer pages 81 and 82 of the Stormwater Detention/Retention Manual for additional information. 20. Provide the design calculations for all proposed erosion protection pads. 21. Provide a geotechnical report that addresses slope protection and required building setbacks from the proposed slopes and the detention/retention basins ponding limits. 22. As required by Rezoning Condition #20, sediment traps shall be incorporated in the detention/retention basin design. Revise the basins accordingly. 23. Detention/retention basins shall be designed in accordance with Rezoning Conditions #21, #22, #23, 24, and #25. Revise the basins accordingly. 24. According to Section 14.3 of the "Standard Manual for Drainage Design and Floodplain Management In Tucson, Arizona", the proposed detention/retention basins require maintenance access ramps that shall be wide enough to accommodate vehicular access. The minimum width should be 15' and the ramp slope should not exceed 15 percent. Please be advised that maintenance ramps should be designed in such a way that does not allow access to vehicles except maintenance vehicles. Verify that the maintenance ramps will not reduce the required size of the basins. 25. According to Section 3.3.5 "Low-Flow Channels" of the Stormwater Detention/Retention Manual the proposed basins floors shall be sloped to provide positive drainage. The section recommends a minimum of 0.5% floor slope and 0.2% low flow concrete channel slope. Please be advised that based on the City's experience with similar projects, 0.5% slope was difficult to construct and maintain which resulted in nuisance ponding in the basins. Additionally, clarify how the basin floor elevations are called out on Figure 4, but a 0.5% basin bottom slope is also shown, which implies that the bottoms elevations vary. Provide the basin bottom elevations that are consistent with the bottom slopes. 26. In accordance with Chapter 4 of the Stormwater Detention/Retention Manual, the detention/retention basins shall be designed to be natural looking, aesthetically pleasing and have multi-use. Verify compliance with these recommendations. Development Plan: 1. Provide a brief legal description as required by D.S. 2-05.2.1.G.2. 2. Provide the correct D(yr)-______ subdivision case number as required by D.S. 2-05.2.2.B.2. 3. List the proposed use of the property (D.S. 2-05.2.2.B.3.). 4. A GPS based basis of bearing is not acceptable. The Basis of Bearing shall be established from two found, physically monumented points described and shown on the plan (D.S. 2-03.6.5.C.1.). Additionally, provide a tie between the basis of bearing and at least one of the subject parcel corners. 5. Show the parcel lines monuments and clarify if they are found or set. Provide the required survey information for all parcel line monuments. 6. Is the sewer easement, shown on sheet 8 of 10, existing or proposed. If the easement is existing, provide the recordation information and revise the Title Report to including. If the easement is proposed, call it out as such. 7. It does not appear that the easement information in the Title Report matches the information on the Development Plan (e.g. electrical easement recorded in Book 69 and Page 72 does not appear to be shown on the plan). Ensure that the Title Report information is updated and the Development Plan reflects correctly the Title Report information. 8. Verify, either on the plan or in written documentation, compliance with Rezoning conditions 2, 4, 6, 8, 11, 12, 15, 16, 20, 21, 22, 23, 24 and 25. 9. The 100-year floodplain does not appear to have been completely preserved as required by Rezoning Condition # 15. Revise the Development Plan to demonstrate compliance. 10. Additional right of way shall be dedicated for Houghton Road and Golf Links Road to their ultimate MS & R widths. 11. Add a general note, which states that this project is affected by the City of Tucson Floodplain Regulations (D.S. 2-05.2.2.C.2.a) 12. Add a general note, which states that a floodplain use permit is required for the proposed within the wash (D.S. 2-05.2.2.C.2.b). 13. Show clearly the existing 100-year floodplain as required by D.S. 2-05.2.3.I. The provided floodplain line is very light and hardly visible. 14. Provide Golf Links existing and future right of way information as required by D.S. 2-05.2.3.C and D.S. 2-05.2.4.D & E. 15. The property legal description includes two parcels, which do not appear to be delineated on the plan. Additionally, the legal description does not appear to be complete. Verify if the legals are accurate. 16. Provide the existing storm drainage facilities adjacent to the site as required by D.S. 2-05.2.3.F. 17. Show the existing 100-year floodplain limits including 100-year water surface elevations as required by D.S. 2-05.2.3.I. 18. It appears that some trash enclosures are located in tight areas and can not be accessed. Revise as required by D.S. 2-05.2.4.T. and D.S. 6-01.4.0. Additionally, it appears that some loading zones are inaccessible. Check and revise as necessary. 19. Building #5 does not appear to have a trash enclosure. Revise as needed. 20. The proposed sidewalk on Houghton Road shall be 6' per MS & R. Dimension Houghton Road sidewalk accordingly. 21. Sheet 9 of 10 is showing three detention basins, yet the sheet appears to have drainage information for two only. Additionally, the inflow/outflow information appears to be incorrect. Revise the detention basin information in accordance with the Drainage Report. 22. Show the Detention Basins 100-year ponding limits with water surface elevation (D.S. 2-05.2.4.H.1.). 23. The drainage solutions and structures shall be verified once the required information is provided on the Drainage Report Drainage Exhibits (D.S. 2-05.2.4.H.2 & 3.). 24. Building #9 appears to be very close to the wash, which makes it necessary to clarify how the erosion hazard setback was delineated as stated in the 2nd Drainage Report comment. Relocating the building might be required. 25. Based on the findings of the Geotechnical Report, show the proposed slope and ponding water setback lines. Proposed buildings shall be located outside the said setbacks (D.S. 2-05.2.4.I.). 26. Show the 100-year flood limits with water surface elevations for all flows of 100 cfs or more (D.S. 2-05.2.4.H.6.). 27. Dimension all existing and proposed sidewalks along abutting right of way to verify that the sidewalks are in compliance with the MS & R requirements (i.e. 6 foot sidewalks are required on MS & R streets (D.S. 2-05.2.4.L.). 28. Truncated domes shall be installed at all existing wheelchair ramps abutting the subject project. 29. Provide street cross sections, for Golf Links and Houghton Road that demonstrate proposed street improvements and compliance with the Rezoning Conditions. 30. The 26' wide curb opening shown on sheet 7 of 10 in front of Building #1 is wide enough to allow inadvertent vehicular access, which is not acceptable. Revise the opening and any other similar situation to prevent vehicles from entering the landscape areas. 31. Show the ratio of all proposed slopes. Additionally, all proposed slope protection shall be based on the recommendations of the geotechnical report. 32. Security barriers shall be installed for all proposed detention basins where applicable. 33. All proposed riprap shall be installed over filter fabric. Revise the plans accordingly. 34. All proposed easements shall be labeled and dimensioned as required by (D.S. 2-05.2.4.G). 35. Any work in the public right of way may require an excavation permit and/or a private improvement agreement. Check with Permits and Codes (Steve Tineo @ 791-5100) for additional information. 36. According to D.S. 2-05.2.4.H.3. and D.S. 3-01.4.4.F. 10-year flow has to be completely conveyed under sidewalks when the runoff crosses any sidewalk/walkway. This also applies to roof drainage. Demonstrate compliance with this requirement. 37. Additional construction details will be required on the Grading Plan. 38. Show on the trash enclosure detail that the provided minimum depth is 10'. 39. Revise the Development Plan in accordance with the Drainage Report revisions. Landscape Plan: 1. Demonstrate that the proposed landscaping will not conflict with the retention/detention basin maintenance access ramp and inlet and outlet structures. 2. Demonstrate compliance with water harvesting requirements. 3. It appears that the sight visibility triangle areas are proposed to be landscaped heavily. For safety reasons, ensure, on the Landscape Plan, that either plants are not proposed within the existing and future sight visibility triangles, or the plants must comply with the requirements of Development Standard 3-01.5.1.A.1. at all times. Show on the Landscape Plans existing and future sight visibility triangles and demonstrate compliance with "no obstruction" requirement. RESUBMITTAL REQUIRED: Revised Development Plan, Landscape Plan and Drainage Report |
04/17/2007 | TOM MARTINEZ | OTHER AGENCIES | AZ DEPT TRANSPORTATION | Approved | NO COMMENT D07-0014 SBBL ARCHITECTURE AND PLANNING SORRENTO SQUARE RETAIL CENTER -------------------------------------------------------- Confidentiality and Nondisclosure Notice: This email transmission and any attachments are intended for use by the person(s)/entity(ies) named above and may contain confidential/privileged information. Any unauthorized use, disclosure or distribution is strictly prohibited. If you are not the intended recipient, please contact the sender by email, and delete or destroy all copies plus attachments. |
04/18/2007 | LIZA CASTILLO | UTILITIES | TUCSON ELECTRIC POWER | Approved | 4350 E. Irvington Road, Tucson, AZ 85714 Post Office Box 711, Tucson, AZ 85702 WR#180143 April 18, 2007 Dear Thomas Sayler-Brown : SUBJECT: SORRENTO SQUARE RETAIL CENTER D07-0014 Tucson Electric Power Company has reviewed and approved the development plan submitted April 13, 2007 It appears that there are no conflicts with the existing facilities within the boundaries of this proposed development. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. In order to apply for electric service, call the New Construction Department at (520) 918-8300. Submit a final set of plans including approved site, offsite and electrical load plans. Include a CD with the AutoCAD version of the plans. If easements are required, they will be secured by separate instrument. Your final plans should be sent to: Tucson Electric Power Company Attn: Ms. Mary Boice New Business Project Manager P. O. Box 711 (DB-101) Tucson, AZ 85702 520-917-8732 Please call the area Designer Nancy DiMaria at (520) 918-8267, should you have any questions. Sincerely, Henrietta Noriega Office Specialist Design/Build hn Enclosures cc: N. DiMaria, Tucson Electric Power |
04/30/2007 | TIM ROWE | PIMA COUNTY | WASTEWATER | Denied | April 27, 2007 To: Thomas Saylor-Brown, SBBL Architecture & Planning Thru: Patricia Gehlen, CDRC Manager City of Tucson Development Services Department ____________________________________ From: Tom Porter, Sr. CEA (520-740-6579), representing the Pima County Departments of Wastewater Management and Environmental Quality Subject: Sorrento Square Retail Center Development Plan – 1st Submittal D07-0014 The proposed sewer collection lines for the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use. Obtain a letter from the PCWMD's Development Services Section, written within the past 90 days, stating that treatment and conveyance system capacity for the project is available in the downstream public sewerage system and provide a copy of that letter to this office. The required form to request such a letter may be found at: http://www.pima.gov/wwm/forms/docs/CapResponseRequest.pdf. The development plan for this project cannot be approved until a copy of this letter has been received by this office. All Sheets: Add the case number, D07-0014, to the title block of each sheet. This number should be shown larger or bolder than any cross reference numbers. No wastewater review fees will be charged for sheets where this is the only required revision. Sheet 1: Add a General Note that states: THIS PROJECT WILL HAVE ______ EXISTING AND______ PROPOSED WASTEWATER FIXTURE UNIT EQUIVALENTS PER TABLE 13.20.045(E)(1) IN PIMA COUNTY CODE 13.20.045(E). And fill in the blanks with the appropriate values. Sheet 1: Add a Permitting Note that states: A PROJECT CONSTRUCTION PERMIT MUST BE SECURED FROM PIMA COUNTY WASTEWATER MANAGEMENT DEPARTMENT BEFORE BEGINNING ANY WORK ON THIS PROJECT. Sheet 1: Add a Permitting Note that states: NO PERMITS FOR PERMANENT STRUCTURES (I.E., MASONRY WALLS, FENCES, ETC.) ON OR THROUGH THE PUBLIC SEWER EASEMENT WILL BE ISSUED WITHOUT SEPARATE WRITTEN CONSENT OF PIMA COUNTY WASTEWATER MANAGEMENT DEPARTMENT. Sheet 1: Add a Permitting Note that states: ALL LANDSCAPING WITHIN THE PUBLIC SEWER EASEMENTS SHOWN HEREON SHALL BE IN ACCORDANCE WITH THE PLANTING GUIDELINES CONTAINED WITHIN PIMA COUNTY/COT STANDARD DETAIL WWM A-4 Sheet 3: In the SYMBOL LEGEND the symbols for manholes and cleanouts should be marked as either PRIVATE or PUBLIC. This office will require a revised set of bluelines, and a response letter, addressing these comments. Additional comments may be made during the review of these documents. Pima County Code Title 13.20.030.A.2 requires that a wastewater review fee be paid for each submittal of the development plan. The fee for the first submittal is $166 plus $50 per sheet. For the second submittal, the review fee is $50 per sheet. For all subsequent submittals, the review fee is $39 per sheet. The next submittal of this project will be the 2nd submittal. A check for the review fee of this submittal in the amount of $200(made out to PIMA COUNTY TREASURER) must accompany the revised set of bluelines and response letter. If the number of sheets changes, please adjust the review fee accordingly. If you have any questions regarding the above mentioned comments, please contact me . CC: Project File |
05/01/2007 | JIM EGAN | COT NON-DSD | FIRE | Approved | |
05/02/2007 | ROGER HOWLETT | COT NON-DSD | COMMUNITY PLANNING | Denied | DEPARTMENT OF URBAN PLANNING & DESIGN COMMENTS Regarding SUBJECT: Community Design Review Committee Application CASE NUMBER: CASE NAME: DATE SENT D07-0014 Sorrento Square Retail Center 4/27/07 () Tentative Plat ( X ) Development Plan ( X ) Landscape Plan () Revised Plan/Plat () Board of Adjustment () Other CROSS REFERENCE: C9-06-03 NEIGHBORHOOD PLAN: South Pantano GATEWAY/SCENIC ROUTE: COMMENTS DUE BY: May 8, 2007 SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS: () No Annexation or Rezoning Conditions, Not an RCP - No Comment () Proposal Complies with Annexation or Rezoning Conditions () RCP Proposal Complies with Plan Policies ( X ) See Additional Comments Attached () No Additional Comments - Complies With Planning Comments Submitted on: ( X ) Resubmittal Required: () Tentative Plat ( X ) Development Plan ( X ) Landscape Plan () Other REVIEWER: JBeall 791-4505 DATE: April 27, 2007 Comments Defer to Traffic Engineering for comments and compliance of the following rezoning conditions: 2, 3, 4, 8, 9, 10, and 11. Defer to Development Services for comments and compliance of the following rezoning conditions: 1, 12, 15, 17, 18, 19, 20, 21, 22, 23, 24, 31, 33, and 34. Defer to Tucson Police Department for comments and compliance of the following rezoning conditions: 25 and 32. The rezoning conditions call out for a one foot no access easement along the west and south perimeter of the project. Please show this on the development plan and identify this in the Keynotes Section. (Rezoning Condition no. 6) The rezoning conditions call out for no rear vehicular access to the five buildings along the west and southwest side of the project. Please call this out on the development plan and identify in the Keynotes section. (Rezoning Condition no. 7) The rezoning conditions call that a variety of rooflines are to be utilized in the architectural design of the project. Please provide elevations for the project’s various buildings that show a variety of rooflines being used in the architectural design of the project. (Rezoning Condition no. 13) The rezoning conditions call out that project lighting at the front of the five buildings along the west and southwest of the project shall not exceed 20 feet in height. Please call this out on the development plan and identify in the Keynotes section. (Rezoning Condition no. 14) Add a note to the General Notes section that project lighting shall be of metal halide design. (Rezoning Condition no. 14) The rezoning conditions call out for a pedestrian path along the natural drainageway on the property located on the southwest portion of the site. This pedestrian path shall be constructed of natural materials and incorporate benches and trash containers. Please show this on the development plan and identify in Keynotes section. (Rezoning Condition no. 16) On sheet DP2.0, please correct 20’ Bldg. Setback Landscape Buffer to read like the wording on sheet DP2.2 i.e., “ 20’ Building Setback and Landscape Buffer. (Rezoning Condition no. 19) Please add wording “ dumpsters and loading zones to be located a minimum 50 feet from all residentially used or zoned property” to the following Keynotes: sheet DP2.0 Keynote 10; sheet DP2.1 Keynote 9; and sheet DP2.2 Keynote 10. (Rezoning Condition no. 26.) Please add the following wording to the General Notes Section, “Hours of operation, along with loading and delivery times shall be restricted to between 7:00 am and 11:00 pm for the five buildings along the west and southwest side of the project." (Rezoning Condition no. 27) The rezoning conditions call out for all walls visible from a public right-of-way and/or adjacent to an existing residential development to be graffiti resistant with a variety of design features and treatments. Also four inch or less block shall not be used on perimeter walls. Please provide a typical that details the design features and treatments, block width, and calls out that walls shall be graffiti resistant. (Rezoning Condition no. 28 and 29) The rezoning conditions call out that the developer agrees to work with the adjacent neighborhoods to mitigate sign pollution. Please include a note in the General Notes section, which details how this rezoning condition is to be implemented. (Rezoning Condition no. 35) The rezoning conditions call out that Larsen and Baker shall be the contact party during the construction process, and that neighborhoods will be provided with contact information, including telephone numbers. Please provide information that the neighborhoods have been provided this contact information. (Rezoning Condition no. 36) The rezoning conditions call out that community agreements be made in writing and that the community agreements shall be recorded with the Pima County Recorder’s Office. Please provide in the General Notes section wording that states that community agreements between the developer and the neighborhood will be in writing and recorded with the Pima County Recorder’s Office. And that such agreements will be submitted to Urban Planning and Design and Development Services to be kept on file. (Rezoning Condition no. 37 and 38) |
05/03/2007 | JOE LINVILLE | LANDSCAPE | REVIEW | Denied | 1) Add the CDRC case number and any related case numbers to the landscape and native plant preservation plans. DS 2-07.2.1.B 2) The site contains regulatory floodplain areas that may contain riparian habitat. Per C9-06-03 the floodplain shall be preserved in it's natural state as shown on the Preliminary Development Plan. Revise the plans as necessary to comply. Riparian habitat may not be unnecessarily altered per TCC Sec. 26-5.2. Refer to DS 2-13 for the preparation, submittal, and review procedures for development within areas that have environmentally valuable habitat in conformance with Article 1, Division 1, Floodplain and Erosion Hazard Area Regulations. 3) Submit an Environmental Resource Report (ERR) per DS 2-13.2.5.B.1. The report will document (1) the areas that contain riparian and wildlife habitat that is to be preserved and (2) those areas without such habitat within the regulatory floodplain. 4) All tentative plats, development plans, site plans, plot plans or other plans providing for approval of development within property that includes any Regulated Area as defined in Development Standard 2-13.2.2.A shall identify and delineate the Regulated Areas and the Protected Riparian Area (SEE COMMENT 9). Revise the tentative plat to use a more distinct line weight for the existing floodplain and delineate any Protected Riparian Areas. 5) All development within the Protected Riparian Area shall be reviewed to insure that there is no unnecessary disturbance of the riparian resources. Refer to DS 2-13.2.5.B.2 for the section on Development Restrictions and revise the plans as necessary to comply. 6) Where any development encroaches within the Protected Riparian Areas, mitigation will be required. A mitigation report shall be submitted with the Environmental Resource Report demonstrating that the proposed mitigation is in conformance with this subsection and applicable codes. DS 2-13.2.5.C 7) Landscape plans are required to document compliance with the mitigation plan requirements. A summary of mitigation and preservation requirements shall be included on the plans. The plans shall show the location of mitigation areas; techniques used for mitigating impacts to, or preservation of, natural areas; specifications for restoration and revegetation of disturbed areas; and general compliance with the applicable standards. Revise as necessary. 8) Encroachments that cross the Protected Riparian Area shall be located and constructed to minimize disturbance of the habitat and wildlife movement. Where a roadway, paved walkway, or bike path improvement or utility encroachment occurs within the Protected Riparian Area, mitigation in conformance with subsection 3 shall be provided. DS 2-13.2.5.B.2 9) Where the Protected Riparian Area is on property that remains under the ownership of a single person or entity following the development, the Protected Riparian Area shall be protected through a conservation or public easement or other legal restriction upon further development. Revise the tentative plat to document the required easement. 10) All lettering and dimensions shall be the equivalent of twelve (0.12") point or greater in size per DS 2-05.2.1.A. Revise all plans as necessary. 11) No grubbing, grading, or construction will occur on a project site which includes areas designated as Protected Riparian Area to be retained in a natural state until those designated areas are temporarily fenced. Identify Protected Riparian Areas on the NPP Plan. 12) Basin slopes are required to have slopes no steeper than 4:1 where depths are three feet or greater per DS 10-01.4. Per C9-06-03 basins are to have slopes no steeper than 4:1. Revise all plans as necessary to comply. 13) The proposed sewer line and connection at East Lurlene Drive crosses the area identified on sheet DP2.2 as an "Archaeological site to remain undisturbed". Revise the plans to eliminate the conflict. 14) Revise the landscape plans to provide same wall heights along the south and west property lines per the development plan and the requirements of C9-06-03. 15) Screen the loading area west of Building 1a from Golf Links Road with a 6' high masonry wall or locate the loading area behind buildings or at least 100 feet from the street property line. 16) The project is subject to the provisions of the Scenic Corridor Zone. A separate application and review are required. Modifications to the plans may be requested in the course of that review and the development plan may not be approved unless the SCZ application is approved. A grading plan showing areas of cut or fill is required with the application. LUC 2.8.2 17) Provide the grading information per DS 2-07.2.2.B: A. Existing grades on adjacent rights-of-way and adjacent sites. If an adjacent right-of-way or site is (or will be) under construction, show the proposed finish grades. B.Extent of grading boundaries if a portion of the site is to be kept in its natural undisturbed state. Indicate natural contours of undisturbed areas, such as the Scenic Route Buffer Area and the archaeological site. C. The methods by which water harvesting or storm water runoff is used to benefit planting areas on the site. D. Slope ratios for any resulting cut or fill slopes. The grading of the site is required to keep cut and fill to a minimum and should be sensitive to natural topography. 18) Revise the landscape plan as necessary to conform to the development/grading plans. 30" screen walls are noted where it is evident that retaining walls or new slopes will be required. 19) Clarify why grading is proposed in scenic route buffer area and why grading or disturbance is not limited at the archaeological site. Grading is restricted in these areas. Revise the grading limits on the landscape and NPP plans. LUC 2.8.2.4, C9-06-03 20) Revise the NPP plans to :"preserve in place" protected native plants in the Scenic route buffer area. Plants 29 & 8 should be preserved, unless there is a permitted improvement per LUC 3.7.5.2.C. LUC 2.8.2.4 RESUBMITTAL OF ALL PLANS IS REQUIRED. IN ADDITION AN ENVIRONMENTAL RESOURCE REPORT AND MITIGATION PLAN ARE REQUIRED. |
05/03/2007 | KAY MARKS | PIMA COUNTY | ADDRESSING | Denied | PIMA COUNTY ADDRESSING 201 N. STONE AV., 1ST FL TUCSON, AZ 85701-1207 KAY MARKS ADDRESSING OFFICIAL PH: 740-6480 FAX #: 740-6370 TO: CITY PLANNING FROM: KAY MARKS, ADDRESSING OFFICIAL SUBJECT: D07-0014 SORRENTO SQUARE RETAIL CENTER/DEVELOPMENT PLAN DATE: 5/03/07 The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and the following matters must be resolved prior to our approval: 1.) Correct Bonanza Rd to Bonanza Av on Location Map. 2.) Spell out Road for Golf Links and Houghton on all applicable sheets. 3.) Delete 1a and 6a. Renumber the buildings so that all buildings are numbered consecutively (ie: Bldg 1a should be Bldg. 2). |
05/03/2007 | JOSE ORTIZ | COT NON-DSD | TRAFFIC | Denied | May 2, 2007 ACTIVITY NUMBER: D07-0014 PROJECT NAME: Sorrento Square Retail Center PROJECT ADDRESS: Golf Links Rd/Houghton Rd PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the Development Plan; therefore a revised Development Plan is required for re-submittal. The following items must be revised or added to the development plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. Provide right of way dimensions along Golf Links on sheets 4 & 5 to confirm compliance. 3. Call out curb return radii's on all driveways along Houghton Road. 4. Provide lane width for proposed right-hand turn lane along Golf Links. 5. Consider providing typical cross-sections of roadway/driveways throughout the project. 6. Provide the Traffic Impact Analysis (TIA) Category III as required by rezoning condition 8 as shown on the Development plan. 7. A meeting maybe in order to discuss possible vehicular conflicts created by the existing acceleration/merge lane (along Houghton in the southbound direction as motorists turn right off of Golf Links) and the proposed right turn lane into this development along Houghton. The Traffic Impact Analysis should discuss this issue and if possible provide recommendations for minimizing this conflict. 8. Along Golf Links the proposed right turn/decel lane could create vehicular conflicts with exiting motorists from this development (using the right turn lane as an acceleration lane) with motorists decelerating off of Golf Links to enter this development, therefore provide a individual right turn lanes for each driveway. 9. Is a right turn lane warranted for the most western driveway entering the development off of Golf Links? Address whether a right turn lane is warranted in the TIA 10. A private improvement agreement (PIA) will be necessary for the proposed work to be performed within the Right-of-way. An approved tentative plat is required prior to applying for a PIA. Contact the PIA Coordinator for additional PIA information at 791-5550 ext. 1107. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
05/07/2007 | ANDY VERA | ENV SVCS | REVIEW | Denied | 1. Safe and adequate access and vehicle maneuverability must be provided within each refuse enclosure service area. Per DS section 6-01.4.0 a. Enclosure by building #2 does not work because the service vehicle will have to back into the right of way in order to clear the enclosure area and enter into its next forward motion. Recommend postioning the enclosure further back or east far enough to allow service vehicle to back up and perform the necessary left turn to proceed south onto PAAL. This will eliminate backing into street. b. Enclosure by building #3 demonstrates that the approach is in conflict with the loading zone. c. Enclosure by building #9 is in conflict with parking spaces when service vehicle is required to back away from the enclosure . Need to provide a 14ft X 40FT approach starting at the face of the enclosure gates if only capable of opening to 90 degrees. If gates are designed to open to 180 degrees then the current approach will work. 2. Single and Double enclosure gates, should be mounted at the face of the wall. This will ensure that the required 10ft inside clear between the rear wall protector and the front gate is provided. Per DS 6-01.4.1.B. Recommend designing gates so that they open to a minimum of 180 degrees. 3. Gates must be designed so that they can be secured in the open postion. Per DS 6-01.4.2.4. Recommend including in enclosure detail on sheet 2, additonal 1" dia. galvanized pipe for securing gates in the open postion. Must include and demonstrate for both single and double enclosures. Make all necessary corrections and include with resubmittal. |
05/08/2007 | FRODRIG2 | COT NON-DSD | REAL ESTATE | Denied | I need the legal description for the one foot no access easement running along the west and south perimeter of the project. (re-zoning condition no. 6.) |
05/09/2007 | PGEHLEN1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Passed | |
05/09/2007 | PGEHLEN1 | OTHER AGENCIES | PIMA ASSN OF GOVTS | Approved | CASE: D07-0014 SORRENTO SQUARE RETAIL CTR, DEVEL PLAN COMMENT: NO OBJECTIONS OR ADVERSE COMMENTS Please call if you have questions or need additional information. Tom Cooney, Travel Forecasting Manager Pima Association of Governments 177 N. Church Ave, #405 Tucson, AZ 85701 Tel: (520) 792-1093, Fax: (520) 620-6981 Web: www.PAGnet.org and www.RTAmobility.com |
05/09/2007 | ED ABRIGO | PIMA COUNTY | ASSESSOR | Passed | |
05/09/2007 | ROBERT YOUNG | PIMA COUNTY | PIMA CTY - DEV REVIEW | Passed | |
05/16/2007 | KAROL ARAGONEZ | ZONING | REVIEW | Denied | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Karol Aragonez Planner PROJECT: D07-0014 Sorrento Square Retail Center Development Plan TRANSMITTAL DATE: May 15, 2007 DUE DATE: May 8, 2007 COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. Section 5.3.8.2, LUC, permits a maximum of one year from the date of application to obtain approval of a development plan. If, at the end of that time, the development plan has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this development plan is April 10, 2008. 2. Please center the subject property include the section, township, and range within the location map DS 2-05.2.1.D & D.3 3. Case number D07-0014 has been assigned to this development plan (DP). Please place this number in the right corner of all sheets of the development plan, landscape plan, NPPO, and any other associated sheets. DS 2-05.2.2.B.2 4. Please correct the development designator for administrative and professional office to "29". Remove automotive service and repair since this requires a special exception which has not been approved. DS 2-05.2.2.B.3 & LUC 2.5.3.2.A.1 5. Please provide a separate response letter detailing compliance with rezoning conditions. DS 2-05.2.4.U 6. Please draw all existing easements on the plan along with recordation information, location, width, and purpose. If an easement is no longer in use and scheduled to be vacated or has been abandoned, so indicate. If none exist provide response to reviewer's comments. Also if easements are purposed please draw, dimension and label as to their purpose and whether they will be public or private. If none exist provide response to reviewer's comments. DS 2-05.2.3.B & DS 2-05.2.4.G 7. Please provide a one (1) foot N.A.E. along the west and south property line as required by rezoning condition 6. It appears that keynote 20 on sheet DP 2.0 should be labeled as one (1) foot No Access Easement, and should be added to sheet DP2.2. C9-06-03 Condition 6 8. Please provide the recordation information and dimension existing pavement, curbs and sidewalks within Golf Links and Houghton Road. DS 2-05.2.3.C 9. The Pima County Assessor's maps show and additional small parcel in the southeast corner of the site (136-12-001M) under separate ownership. Please indicate if this parcel was combined with the project as it appears to be part of the Houghton Road dedication. Provide a copy of the lot combo. 10. Please provide the zoning designation for the CVS property (C-1). Correct the zoning designation for the south (R-1) and west (RX-1). DS 2-05.2.4.B 11. Please dimension all PAALs within the site or provide general note stating all PAALs are a minimum of twenty-four (24) feet unless otherwise designated. Dimension the PAAL between the off-street loading spaces and trash compactor and parking spaces on the west side of building 1 and building 9 to assure a minimum PAAL width of twenty-four (24) has been maintained. DS 3-05.2.1.C.1 12. Please dimension the back-up spurs between buildings 3 and 4, the northeast of building 5, and northeast of building 9. The spur will be a minimum of three (3) feet in depth, will have a three (3) foot radii, and will have a wheel barrier to prevent encroachment onto any unsurfaced areas. DS 3-05.2.2.D 13. Please dimension the drive-through lane for building 7. The minimum drive-through lane width is eleven (11) feet and must be striped, marked, or otherwise clearly delineated. The minimum drive-through lane width at the window is nine (9) feet. No more than two car lengths may be less than the minimum width of eleven (11) feet. DS 3-05.2.1.C.1.b 14. The minimum stacking for one (1) drive-through lane is six (6) spaces including the space at the window. The DP shows seven (7). This should be reduced to six (6) to allow relocating the pedestrian path from crossing across the stacking area. DS 3-05.2.1.C.1.a & c 15. A minimum setback of one (1) foot must be maintained between the building and drive-through lane. DS 3-05.2.2.B.4 16. The numbers of motor vehicle parking spaces indicated in the parking calculations and the number shown in plan view appear not to match. Calculations indicate 627 spaces but the 631 are shown on the plan. Please verify and correct as needed. 17. The special concrete area abutting the HC space in the northeast corner of building 1a must be physically separated from the parking space since it is not intended as an access aisle. DS 2-08.4.1 18. Truncated domes are to be placed at the top of the access aisle to warn the pedestrian that they are entering a vehicle use area. The area covered by the truncated domes shall be twenty-four (24) inch deep and extend the full width of the crosswalk, preceding the crosswalk, including access aisles of handicapped motor vehicle parking spaces. The domes shall be located so the edge nearest the curb line is six (6) inches to eight (8) inches from the curb line. ANSI 406.12, ANSI 705 19. Rehabilitation and physical therapy require twenty (20) percent, but not less than one (1), of the portion of patient and visitor parking spaces to be accessible. Please provide separate parking calculations for the additional accessible spaces required or indicate that medical services will not include these uses. 2003 IBC Sec. 1106.4 20. Please provide a detail of the proposed carports demonstrating that supports for the carports are no more than three and one-half (3 1/2) feet from the front of the parking space. Putting supports at a greater distance will hinder passengers from entering and exiting their vehicles. 21. Please verify that the minimum overhead clearance of eight-four (84) inches for sidewalks is provided where the carports overhang over the sidewalk area at building 3 and 4. DS 2-08.5.1.B 22. Sheet DP1.0 indicates that there is 4,790 sq. ft. of outdoor dining area. The plan view only shows areas added up to 2,645 sq. ft. Please provide the location of the remainder of the outdoor dining areas. 23. LUC Sec. 3.5.9.2.C restricts the number of fuel dispensing locations to twelve (12). These locations have been defined as spaces that vehicles use to get gasoline. It appears that there will be ten (10) pumps with dispensing ability of twenty (20) spaces, which exceed the performance criteria. Please revise. LUC 3.5.9.2.C 24. Please remove general note 16. General restrictions of C-1 zone require that all land use activities except vehicular use areas to be conducted entirely within an enclosed building unless specifically provided otherwise. LUC 2.5.3.6 25. Please label building 4 and square footage on sheet DP1.2 26. A minimum setback distance of five (5) feet for a pedestrian refuge area, which includes a four (4), foot sidewalk that is physically separated from the PAAL must be provided between and enclosed structure and a PAAL. This is required for building 1 along the south and west side of structure, the west side of building 6, the east side of building 6a, and the west side of building 8. DS 3-05.2.2.B.1 27. Rezoning condition 16 requires a pedestrian path along the natural drainageway on the portion of the property on the southeast. This path shall be constructed of natural materials such as crushed aggregate and shall incorporate benches and trash containers to be maintained by the developer. The plan does not show compliance to this condition. Please provide. C9-06-03 Condition 16 28. Please provide a copy of any and all community agreements made between the developer and affected neighborhood associations that were required to be recorded with the Pima County Recorders Office as specified in rezoning condition 37-38. C9-06-03 Condition 37 & 38 29. Residential property along the south is zoned R-1. The required setback is one and one-half (1 1/2) the height of the exterior building wall which would be thirty feet unless elevations of building 5 based on the wall height indicate a different setback. Please revise. LUC 3.2.6.4 Perimeter Yard Indicator DD 30. Per DS 2-08.3.1 a continuous pedestrian circulation path must connect all buildings within a development, which is also an accessible route. This route will be a minimum four (4) foot wide concrete sidewalk. Please label or provide note indicating minimum sidewalk width through-out project site. Areas within this project that appear not connect to other areas of the project site is building 9 which does not connect to the rest of the site, and buildings 2-5 which does not connect to buildings 1 and 1a. Also the pedestrian connection from Houghton Road does not connect to buildings 1, 1a, and 6-8. Please revise. 31. Please dimension all building footprints on the development plan. DS 2-05.2.4.N 32. Please provide wheel-stop curbing for standard parking space in detail 3/DP1.1 and dimensioned in detail 9/DP1.1. Wheel-stops are to be shown for all parking spaces that would require it to prevent the vehicle from extending onto a sidewalk reducing the width to less than four (4) feet or landscape areas to prevent damage to vegetation. The wheel-stop curbing is to be placed two and one-half (2 1/2) feet from the front of the parking space. DS 3-05.2.3.C 33. Bicycle parking provided on the DP does not meet the requirements of Development Standard 2-09. Per DS 2-09.4.1 Class 2 bicycle parking facilities will be located no more than fifty (50) feet from the main building entrance(s) and will be along the front side of the building as well as along other sides of the building that has an entrance. Bicycle access through the development will be separate from the pedestrian ways. Vehicular access may be used as bicycle access. Bicycle access to a parking facility may cross a pedestrian way at a right angle (DS2-09.3.2). Lighting will be provided such that all facilities are thoroughly illuminated and visible from adjacent sidewalks, parking lots, or buildings, during working hours. The surface of the facility can be surfaced the same as for motor vehicle parking or with a minimum of one (1) inch thickness of one-fourth (1/4) inch aggregate material. 34. Provide a detail of the type of rack being proposed. Short-term bicycle parking must provide a secure, two-point support system that supports the bicycle and allows the user to securely lock the frame and wheels. Please review DS 2-09.8.0 Figure 2 - 7 for acceptable and unacceptable rack designs. DS 2-09.2.3 35. Please verify with Environmental Services if an additional dumpster is not required for building 5. It appears that the distance to the nearest dumpster at building 4 may be excessive. 36. Please indicate the location and type of postal service to assure there are no conflicts with other requirements. If mail is to be delivered to an area within a building please state so on the plan. DS 2-05.2.4.V 37. Please indicate if there are existing billboards on site. Billboards will be required to meet all LUC requirements as stated in LUC Sec. 3.5.4.26. If none exists please state so. DS 2-05.2.4.W & LUC 3.5.4.26 Scenic Corridor (SCZ) 38. A separate Special Application, review, and approval for the SCZ overlay is required. For more information the applicant must contact Patricia Gehlen at 791-5608 ext. 1179. The application form is on the DSD website at http://www.tucsonaz.gov/dsd/Forms_Fees___Maps/Applications/Overlay_Zone_Application.pdf. Once approved please place the overlay case number, date of approval in the lower right corner of all sheets of the development plan, landscape plan, and NPPO. A note should also be provided in the general notes providing the overlay case number, date of approval, and any applicable conditions on sheet DP1.0 39. Please add the view corridor calculations to the plan. Any development which has at least two hundred (200) feet of frontage along a scenic route will have view corridors, with a combined width of at least twenty (20) percent of that frontage, which allow vision from a least one point into and through that portion of the project. 40. Please add the appropriate following notes to the tentative, development, or site plan plat. a. No grading beyond that is necessary for siting of buildings, drives, private yards, and structural improvements. All viable vegetation with a caliper of 4 inches or greater and all saguaro cacti will be preserved or relocated on the site per the Native Plant and Preservation Ordinance. b. Drainageways are to be maintained in their natural state. c. Fencing and freestanding walls facing Houghton Road will meet material restrictions in Land Use Code Sec. 3.7.3, Screening Requirements. d. All areas between the MS & R right-of-way line and the existing street right-of-way that are disturbed by development shall be revegetated with native vegetation. e. All disturbed areas on the site that are visible from Houghton Road and are not covered by permanent improvements shall be revegetated with native plants, plants from the Drought Tolerant Plant List, or a combination of both. f. Exposed cut and fill slopes shall be no greater than 1-foot rise or fall over a 3-foot length. 41. Revise general note 31 to read: "All new utilities for development on private property or public right-of-way along Houghton Road will be underground. Trenching is permitted for the placement of utilities lines, if area is revegetated in accordance with Land Use Code Sec. 3.7.5.2.D" 42. Revise general note 33 to read: "Building or structure surfaces, which are visible from Houghton Road will have natural earth tone colors, which are, predominate within the surrounding landscape". 43. Regulations for signs are stipulated in Sec. 3-32, Scenic Route District, of Chapter 3, Advertising and Outdoor Signs, of the Tucson Code, and further supplemented by the following: a) On any conflicts in requirements between the LUC and Sec. 3-32, the more strict of the two prevails. b) Signs are to use colors, which are predominant within the surrounding landscape, such as desert and earth tones. c) No commercial advertising sign, except a sign pertaining to a use conducted on the premises or a sign advertising the sale or lease of the property upon which the sign is located, and no billboard shall be erected within four hundred (400) feet of the right-of-way line on any street or route designated "scenic". 44. All changes, modifications, and/or corrections must be made on all applicable plans including the development plan, landscape plan, and NPPO. Once changes, modifications, and/or corrections are made and reviewed further comments may result. If you have any questions about this transmittal, please call Karol Aragonez, (520) 791-5550, ext. 74960. KAA S:\zoning review\karol\planning\cdrc\developmentplan\D07-0014dp.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan and additional requested documents. |
05/18/2007 | GLENN HICKS | COT NON-DSD | PARKS & RECREATION | Approved | DATE: May 17, 2007 TO: Ferne Rodriguez, Development Services FROM: Glenn Hicks Parks and Recreation 791-4873 ext. 215 Glenn.Hicks@tucsonaz.gov CC: Patricia Gehlen SUBJECT: D07-0014 Sorrento Square Retail Center: Development Plan(4-11-07) Staff has no comments. |
05/23/2007 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Denied | COMMUNITY DESIGN REVIEW COMMITTEE DEVELOPMENT SERVICES ***REVISED*** May 23, 2007 Thomas Sayler-Brown SBBL Architecture and Planning 1001 N. Alvernon Way, Ste 105 Tucson, Arizona 85711 Subject: D07-0014 Sorento Square Retail center Dear Thomas: Your submittal of April 4, 2007, for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed: ALL BLUELINES MUST BE FOLDED 10 Copies Revised Development Plan (Traffic, Landscape, Zoning, Engineering, Wastewater, DUPD, Addressing, Real Estate, ESD, DSD) 5 Copies Revised Landscape Plans (Engineering, Landscape, Zoning, DUPD, DSD) 2 Copies Revised NPPO Plans (Landscape, DSD) 2 Copies Revised Drainage Report (Engineering, DSD) 2 Copies Color Elevations (DUPD, DSD) 3 Community Agreements (Zoning, DUPD, DSD) 2 Traffic Impact Analysis (Traffic, DSD), 2 Environmental Resource Reports (Landscape, DSD) Should you have any questions, please call me at 791-5608, ext 1179. Sincerely, Patricia Gehlen CDRC Manager All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/ Via fax: 620-0535 |