Permit Number: D07-0008
Parcel: 14122004G

Address:
8500 S RITA RD

Review Status: Completed

Review Details: REVISION - DEV PLAN

Permit Number - D07-0008
Review Name: REVISION - DEV PLAN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/19/2007 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
10/22/2007 PAUL MACHADO ENGINEERING REVIEW Denied To: Patricia Gehlen DATE: November 28, 2007
CDRC/Zoning Manager
SUBJECT: Global Solar Energy, 8500 S. Rita Ranch Road
Development Plan D07-0008 Revision (First Review)
T15S, R15E, Section 28

RESUBMITTAL REQUIRED: Development Plan and Drainage Statement.

The Development Plan (DP) and Drainage Statement (DS) cannot be approved as submitted. Please address the following review comments prior to the next submittal.

Development Plan:

1. Please include a response letter to the comments along with the corrected copies of the DP.
2. It is not clear what is being proposed by the partial removal of the existing 24" culvert. Show in detail what is being proposed on the plans.

Drainage Statement:
1. Please include a response letter to the comments along with the corrected copies of the DS.
2. A Drainage Statement is a brief description of drainage conditions applicable for a site which are not affected by 100 year flows of 100 cfs, of more……per S.M.D.D.F.M., chap. II, 2.1.2. The DS must be submitted along with the site plan and accepted with the approval of the grading plan.
3. The content and format of the Drainage Statement should follow S.M.D.D.F.M., chap. II, 2.2.
4. Show the project address or administration address on the cover sheet of the DS.
5. If applicable, add the basin(s) maintenance responsibility note and checklist per S.M.D.D.F.M. 2.3.1.6 C 1 and 2 to the DS.

If you have any questions, I can be reached at 791-5550 x1193 or Paul.Machado@ci.tucsonaz.govs
Paul P. Machado
Senior Engineering Associate
City of Tucson/Development Services Department
201 N. Stone Avenue
P.O. Box 27210
Tucson, Arizona 85726-7210
(520) 837-4932 office
(520) 879-8010 fax,
C:/8500 S. Rita Ranch Rd CDRC_REV
10/22/2007 JIM EGAN COT NON-DSD FIRE Approved
10/24/2007 KAROL ARAGONEZ ZONING REVIEW Approv-Cond CDRC TRANSMITTAL

TO: Development Services Department Plans Coordination Office

FROM: Karol Aragonez
Planner

PROJECT: D07-0008
Global Solar Energy Facility
Development Plan Revision

TRANSMITTAL DATE: October 24, 2007

DUE DATE: November 19, 2007

COMMENTS:

The Zoning Review Section approves the development plan for this project, subject to the following changes on the sign-off copies. However, should there be any changes requested by other CDRC members, the Zoning Review Section approval is void, and we request copies of the revised development plan to verify that those changes do not affect any zoning requirements.

1. Please add the proposed height of the solar panels as a general note. Panels cannot exceed one hundred and forty (140) feet in height.

2. Please provide dimension from edge of panel or proposed concrete pads, whichever is greater, to the property lines to north, east, and south.


If you have any questions about this transmittal, please call David Rivera, (520) 791-5608.

KAA S:\zoning review\karol\planning\cdrc\developmentplan\D07-0008dprev.doc
10/26/2007 ROGER HOWLETT COT NON-DSD COMMUNITY PLANNING Approved DEPARTMENT OF URBAN PLANNING & DESIGN COMMENTS

Regarding

SUBJECT: Community Design Review Committee Application

CASE NUMBER: CASE NAME: DATE SENT

D07-0008 Global Solar Energy New Facility 10/25/07

() Tentative Plat
(XXXX) Development Plan
(XXXX) Landscape Plan
() Revised Plan/Plat
() Board of Adjustment
() Other

CROSS REFERENCE: C9-84-84 & C15-00-04

NEIGHBORHOOD PLAN: Esmond Station

GATEWAY/SCENIC ROUTE:

COMMENTS DUE BY: 11/19/07

SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS:

() No Annexation or Rezoning Conditions, Not an RCP - No Comment
( Proposal Complies with Annexation or Rezoning Conditions
() RCP Proposal Complies with Plan Policies
() See Additional Comments Attached
(XXXX) No Additional Comments - Complies With Planning Comments Submitted on: 03/14/07
() Resubmittal Required:
() Tentative Plat
() Development Plan
() Landscape Plan
() Other

REVIEWER: drcorral 791-4505 DATE: 10/24/07
11/05/2007 JOE LINVILLE LANDSCAPE REVIEW Approved
11/14/2007 GLYNDA ROTHWELL UTILITIES TUCSON ELECTRIC POWER Denied 4350 E. Irvington Road, Tucson, AZ 85714
Post Office Box 711, Tucson, AZ 85702


WR#177734 March 5, 2007


Dear : Richard Cordova:

SUBJECT: GLOBAL SOLAR ENERGY – NEW FACILITY
D07-0008


Tucson Electric Power Company has reviewed and disapproved the development plan submitted November 7, 2007. It appears that there are conflicts with the existing facilities within the boundaries of this proposed development. Please identify any and all TEP facilities within the mapped area of the development plan for approval, both on site and off ste. Refer to TEP map or original approved development plan. A facilities map is attached for reference. Conflicts can not be determined until facilities are properly indicated on the plan. Any relocation costs will be billable to the customer.

Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities.

In order to apply for electric service, call the New Construction Department at (520) 918-8300. Submit a final set of plans including approved site, offsite and electrical load plans. Include a CD with the AutoCAD version of the plans. If easements are required, they will be secured by separate instrument. Your final plans should be sent to:

Tucson Electric Power Company
Attn: Ms. Mary Boice
New Business Project Manager
P. O. Box 711 (DB-101)
Tucson, AZ 85702
520-917-8732

Please call the area Designer Steve Garcia at (520) 917-8739, should you have any questions.

Sincerely,


Henrietta Noriega
Office Specialist
Design/Build
hn
Enclosures
Cc S. Garcia, Tucson Electric Power
P. Gehlen, City of Tucson (E-Mail)
11/29/2007 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

November 29, 2007

Richard Corodova
DOWL Engineers
166 W Alameda
Tucson, Arizona 85701

Subject: D07-0008 Global Solar Energy Facility Revised Development Plan

Dear Richard:

Your submittal of October 19, 2007 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLACKLINES MUST BE FOLDED

4 Copies Revised Development Plan (Engineering, Zoning, TEP, DSD)

3 Copies Revised Landscape Plan (Zoning, Engineering, DSD)

2 Copies Revised Drainage Statement (Engineering, DSD)




Should you have any questions, please call me at 837-4919.

Sincerely,


Patricia Gehlen
CDRC Manager

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/

Via fax: 624-0384
dp-resubmittal