Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - CDRC - DEV PLAN
Permit Number - D06-0046
Review Name: RESUBMITTAL - CDRC - DEV PLAN
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/15/2007 | FERNE RODRIGUEZ | START | PLANS SUBMITTED | Completed | |
| 03/16/2007 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | To: Patricia Gehlen DATE: April 16, 2007 CDRC/Zoning Manager SUBJECT: Brown/Rita Ranch Lot 28, 9098 E. Camino De Abril Development Plan D06-0046 (Second Review) T15S, R15E, Section 27 RESUBMITTAL REQUIRED: Development Plan and Drainage Statement. The Development Plan (DP) and Drainage Statement (DS) cannot be approved as submitted. Please address the following review comments prior to the next submittal. Development Plan: 1. Please include a response letter to the comments along with the corrected copies of the DP. 2. Please list estimated cut & fill quantities. The DP is a Site plan with a re-zoning history. The c/f quantities will be checked against the grading plan for consistency. The c/f quantities an estimate only. Revise as required. 3. Show refuse container location, size, and access thereto fully dimensioned per D.S. 2-02.2.1.32 and D.S. 6-01.0. The approach to the refuse enclosure still does not meet standards. Perhaps a meeting to discuss its location is necessary. Contact Paul Machado for an appt. Drainage Statement: 1. The DS has been accepted for DP purposes only. If you have any questions, I can be reached at 837-4932 or Paul.Machado@tucsonaz.gov Paul P. Machado Senior Engineering Associate City of Tucson/Development Services Department 201 N. Stone Avenue, P.O. Box 27210 Tucson, Arizona 85726-7210, (520) 837-4932 office, (520) 879-8010 fax, C:/9098 E Camino De Abril CDRC Lot 28_2 |
| 04/04/2007 | KAROL ARAGONEZ | ZONING | REVIEW | Denied | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Karol Aragonez Planner PROJECT: D06-0046 East Camino Abril Lot 28 Development Plan Resubmittal TRANSMITTAL DATE: April 4, 2007 DUE DATE: April 12, 2007 COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. Within the location map please label the S.P.R.R. line and the drainageway. DS 2-05.2.1.D.2 2. Uses that are indicated on the development plan must meet minimum motor vehicle and bicycle parking, off-street loading, and AEZ criteria. From the list of proposed uses and parking calculations, please remove the following uses: Salvaging, Communication, and Trade Service and Repair Major. These uses will require additional parking and/or special requirements to be done to the site which currently cannot be met as drawn. 3. Please make sure that surrounding zoning is readable. Current font/style does not reproduce well and cannot be read. 4. It is suggested that Class 1 bicycle parking be removed from the development plan. Any use providing less than fifty (50) motor vehicle parking spaces may substitute Class 2 spaces for Class 1 spaces. LUC 3.3.7.8.A 5. Please provide a minimum distance of five (5) feet for a pedestrian refuge area between the building and PAAL. Within this refuge area a four (4) foot wide sidewalk must be provided and be physically separated with curbing. (DS 3-05.2.2.B.1) The minimum width of a two-way traffic aisle is twenty-four (24) feet. (DS 3-05.2.1.C.1). This is to be shown on both the plan view and detail H/3 6. Detail I/3 does not make sense using dimensions less than two (2) feet. Please explain 7. Truncated domes are to be places at the beginning of the access aisle. Detectable warnings (truncated domes) are required at all accessible aisles. The area covered by the truncated domes shall be twenty-four (24) inch deep and extend the full width of the access aisles of handicapped motor vehicle parking spaces. The domes shall be located so the edge nearest the curb line is six (6) inches to eight (8) inches from the curb line. ANSI 406.12, ANSI 705 8. Please dimension the back-up spur at the southwest end of the parking lot. The spur will be a minimum of three (3) feet in depth and will have a three (3) foot radii. A minimum distance of three (3) feet will be provided between the back of spur and any wall, screen, or other obstruction over six (6) inches in height. DS 3-05.2.2.D 9. Please revise detail B/3. Signage for accessible parking is to be posted at seven (7) feet from the curb to the bottom of the sign per TDOT requirements. 10. Please add the off-street loading requirements per Table 3 (LUC 3.4.5.3), one (1) space required for GFA between 1,500-10,000 sq. ft. to show that this requirement is being met. Also provide the required length and wide of both spaces and indicate that the most restrictive is being used. LUC 3.4.5.1 & LUC 3.4.5.3 11. Please provide the street setback from Camino Abril. The required setback is the greater of twenty-one (21) feet or the building wall height measured from the back of travel lane. DS 2-05.2.4.I 12. Please dimension the minimum seventy-two (72) inch length per bicycle parking space (DS 2-09.5.1) in detail J/3. 13. Please revise detail G/3. Landscaping and sidewalk does not appear within the plan view along the northwest property line. 14. Please indicate that gate will remain open during business hours to allow access to required parking. 15. Please correct the acronyms from AHD to ADC in general note 22. The reviewer provided the wrong acronym. If you have any questions about this transmittal, please call Karol Aragonez, (520) 791-5550, ext. 1197. KAA S:\zoning review\karol\planning\cdrc\developmentplan\D06-046dpr.doc |
| 04/10/2007 | JOSE ORTIZ | COT NON-DSD | TRAFFIC | Denied | April 10, 2007 ACTIVITY NUMBER: D06-0046 PROJECT NAME: East Camino Abril Lot # 28 PROJECT ADDRESS: 9098 E. Camino Abril PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the Development Plan; therefore a revised Development Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. Ensure that the solid waste vehicle can maneuver on-site to gather and leave the site without backing into the public roadway. The exhibit provided does not correctly illustrate the maneuvering motion of a standard solid waste vehicle. Please revisit and revise exhibit to ensure that solid waste vehicles can maneuver on site and leave the site face forward. If you have any questions, I can be reached at 791-4259 x305 or Jose.Ortiz@tucsonaz.gov |
| 04/11/2007 | JOE LINVILLE | LANDSCAPE | REVIEW | Approved | |
| 04/11/2007 | KAY MARKS | PIMA COUNTY | ADDRESSING | Approved | 201 N. STONE AV., 1ST FL TUCSON, AZ 85701-1207 KAY MARKS ADDRESSING OFFICIAL PH: 740-6480 FAX #: 740-6370 TO: CITY PLANNING FROM: KAY MARKS, ADDRESSING OFFICIAL SUBJECT: D06-0046 EAST CAMINO ABRIL LOT 28/REVISED DEVELOPMENT PLAN DATE: 4/11/07 The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and we hereby approve this project. Submit a 24 x 36 Reverse Reading Double Matte Photo Mylar of approved Development Plan to City Planning. Signed and dated Mylar will be forwarded to Pima County Addressing prior to assignment of addresses. 2.) All addresses will need to be displayed per Pima County Address Standards at the time of final inspection. ES |
| 04/18/2007 | ANDY VERA | ENV SVCS | REVIEW | Denied | * Not adequate and safe acess for service vehicle to maneuver within the development... Must be able to position vehicle so exits in forward movement. No backing into street. DS 6-01.3.1A * Refuse maneuverability detail on sheet 3 is not accurate as demonstrated. Turning radius does not work for present standard trucks (36ft length). * Enclosure detail will work as shown. |
| 04/24/2007 | FRODRIG2 | PIMA COUNTY | WASTEWATER | Approv-Cond | April 25, 2007 TO: Steve Wollerman, P.E. Southwestern Consulting Engineers, L.L.C.. THRU: Patricia Gehlen, CDRC Manager City of Tucson, Development Services Department FROM: Chandubhai C. Patel, P.E., Civil Eng. Manager Development Review Division (Wastewater) Pima County Development Services Department SUBJECT: Lot 28, East Camino Abril Commercial Craft Site Development Plan – 2nd Submittal D06-046 The proposed sewer collection lines to serve the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use. On sheet 2, the adjacent Lot 29 needs to be identified and shaded, as it is on sheet 1. SUBJECT TO THE ABOVE, the Pima county Department of Environmental Quality and the Wastewater Management Department hereby CONDITIONALLY approve the above referenced submittal of the Development Plan as received by us on March 19, 2007. The revision may be shown on the Mylars. Please note the following: Approval of the above referenced submittal does not authorize the construction of public or private sewer collection lines, or water distribution lines. Prior to the construction of such features, a Construction Authorization (Approval to Construct) may need to be obtained from the Pima County Department of Environmental Quality. Also, air quality active permits must be secured by the developer or prime contractor from the Pima County Department of Environmental Quality before constructing, operating, or engaging in any activity which may cause or contribute to air pollution. If you have any questions regarding the above mentioned comments, please contact me. Sincerely, Chandubhai Patel, P.E. Telephone: (520) 740-6563 Copy: Project file |
| 04/25/2007 | PATRICIA GEHLEN | ZONING-DECISION LETTER | REVIEW | Denied | COMMUNITY DESIGN REVIEW COMMITTEE DEVELOPMENT SERVICES April 25, 2007 Steve Wollerman Southwestern Consulting Engineers, LLC 435 East 9th Street Tucson, Arizona 85705 Subject: D06-0046 East Camino Abril Lot 28 Development Plan Dear Steve: Your submittal of March 15, 2007 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed: ALL BLACKLINES MUST BE FOLDED 5 Copies Revised Development Plan (ESD, Zoning, Traffic, Engineering, DSD) 3 Copies Revised Landscape Plan (Zoning, Engineering, DSD) 2 Copies Revised Drainage Statement (Engineering, DSD) Should you have any questions, please call me at 791-5608 extension 1179. Sincerely, Patricia Gehlen CDRC Manager All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/ Via fax: 628-1063 |