Permit Number: D06-0044
Parcel: 141113840

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - DEV PLAN

Permit Number - D06-0044
Review Name: RESUBMITTAL - CDRC - DEV PLAN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/29/2007 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
06/12/2007 KAROL ARAGONEZ ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department Plans Coordination Office

FROM: Karol Aragonez
Planner

PROJECT: D06-0044
East Camino Abril Lot 21
Development Plan Resubmittal

TRANSMITTAL DATE: June 9, 2007

DUE DATE: June 26, 2007

COMMENTS: Please resubmit revised drawings along a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Previous Comment - Please add the off-street loading requirements per Table 3 (LUC 3.4.5.3), one (1) space required for GFA between 1,500-10,000 sq. ft. to show that this requirement is being met. Also provide the required length and wide of both spaces and indicate that the most restrictive is being used.
LUC 3.4.5.1 & LUC 3.4.5.3

This comment was made to have the off-street loading calculation show both tables indicating that providing one space meets both requirements depending on the actual principal use that will occupy the site. It was not intended to make the applicant supply two off-street loading spaces. The total square footage did not exceed 10,000 sq. ft. (both building and work area). A single off-street loading space 12'x55' is required and will meet the requirements of both tables. What must be demonstrated is the vehicles ability to maneuver into and out of the space without crossing into or reducing a parking space.

Per LUC Sec. 3.4.4.2.A: A street may be used for maneuvering of a delivery vehicle into, or out of, a loading space, provided it is for a use with only one (1) space, and if:
1. The street is not shown on the Major Streets and Routes (MS&R) Plan; or
2. The street is not a local residential street; or
3. The street does not abut a residential zone within the same block or within three hundred (300) feet of the nearest point of access to the loading zone. The three hundred (300) foot distance does not apply to the opposite side of a major street.

2. In cross section J/3 please dimension the five foot pedestrian refuge area as required by DS 3-05.2.2.B.1. The dimension currently shown is four and one-half (4 ½) feet.

3. Please add truncated domes at the entrance to the cross walk on both sides. The domes are to provide a warning and direction to visually impaired individuals of a vehicle use area. The current placement would direct that person into fencing or directly into traffic. The area covered by the truncated domes shall be twenty-four (24) inches deep and extend the width of the crosswalk.
ANSI 406.12, ANSI 705

If you have any questions about this transmittal, please call Karol Aragonez, (520) 791-5550, ext. 74960.

KAA S:\zoning review\karol\planning\cdrc\developmentplan\D06-0044dpr1dp.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan.
06/13/2007 CDRC1 ENV SVCS REVIEW Approved
06/13/2007 CDRC1 PIMA COUNTY WASTEWATER Approv-Cond June 12, 2007

To: Steve Wollerman, Southwestern Consulting Engineers, LLC

Thru: Patricia Gehlen, CDRC Manager
City of Tucson Development Services Department

____________________________________
From: Felipe Ip, Sr Civil Eng. Assistant, Development Review Division
Pima County Development Services Department

Subject: Lot 21, East Camino Abril Commercial Craft Site
Development Plan - 3rd Submittal
D06-0044

The proposed final plat for the above-referenced project has been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use.

1. Sheet 2: Revise the plan to show the invert elevation of the existing BCS connection.

2. Sheet 2: Revise the plan to show the existing public manhole 3953-04 downstream from the BCS connection. Also, provide the rim and invert elevations.

Subject to the above, the Pima County Department of Environmental Quality and Wastewater Management Department hereby CONDITIONALLY approve the above referenced development plan submitted to us on May 30, 2007. The required revision(s) may be shown on the Mylars.

Please note the following: Approval of the above referenced submittal does not authorize the construction of public or private sewer collection lines, or water distribution lines. Prior to the construction of such features, a Construction Authorization (Approval To Construct) may need to be obtained from the Pima County Environmental Quality.

Also, air quality activity permits must be secured by the developer or prime contractor from the Pima County Department of Environmental Quality before constructing, operating or engaging in an activity which may cause or contribute to air pollution.

If you have any questions regarding the above mentioned comments, please contact me at 520-740-6706.

CC: Project File
06/18/2007 PAUL MACHADO ENGINEERING REVIEW Approved
07/06/2007 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

July 6, 2007

Steve Wollerman
Southwestern Consulting Engineers, LLC
435 East 9th Street
Tucson, Arizona 85705

Subject: D06-0044 East Camino Abril Lot 21 Development Plan

Dear Steve:

Your submittal of May 30, 2007 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLACKLINES MUST BE FOLDED

3 Copies Revised Development Plan (Zoning, Wastewater, DSD)






ALTHOUGH PIMA COUNTY WASTEWATER CONDITIONALLY APPROVED THIS DEVELOPMENT PLAN, THE CITY OF TUCSON CDRC OFFICE CAN NOT REVIEW FOR THE CONDITIONS SO ANOTHER SUBMITTAL WILL BE REQUIRED TO WASTEWATER.

Should you have any questions, please call me at 791-5608 extension 1179.

Sincerely,

Patricia Gehlen
CDRC Manager

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/
Via fax: 628-1063