Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: D06-0006
Parcel: 133233580

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - DEV PLAN

Permit Number - D06-0006
Review Name: RESUBMITTAL - CDRC - DEV PLAN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/22/2006 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
05/23/2006 JOE LINVILLE LANDSCAPE REVIEW Denied Revise the development/landscape plan to clearly show the future sidewalk location along Broadway Boulevard at the proposed turn lane. As shown, the future sidewalk appears to extend past the future curb into the turn lane and extends into the street landscape border, both are unacceptable.
05/25/2006 JCLARK3 ENV SVCS REVIEW Approved
06/05/2006 MARILYN KALTHOFF PIMA COUNTY WASTEWATER Denied June 5, 2006

TO: Maurita Walker
RSP Architects

THRU: Patricia Gehlen
City of Tucson, Development Services Department

FROM: Mike Henrich
Pima County Development Services Department
Development Review Division (Wastewater)

SUBJECT: US Bank
Development Plan - 2nd Submittal
D06-006

The proposed sewer collection lines to serve the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. This submittal was compared to the previous review comments from this office dated February 25, 2006. The following summarizes the status of those comments in the same order:

1. Addressed, although a copy of the letter from PCWWM was not included as stated in the response letter.

2. Addressed.

3. Addressed.

4. Addressed.

5. Partially addressed. The requested note was added to the General Notes on page 1 of the development plan, but it was not completed. The note indicates that 0 fixture units are proposed.

6. Addressed.

7. Partially addressed. As previously requested, delete Engineer's Note 16 as well as the Manhole Notes on sheet 2.

8. Partially addressed. The plan numbers are shown. However, delete "COT" at the beginning of each.

9. Partially addressed. Delete the "COT" from the beginning of each.

10. We will require a revised set of drawings and a response letter addressing each comment. Additional comments may be made during the review of these documents.

The next submittal of this project will be the 3rd submittal. A check for the review fee of this submittal in the amount of $78.00 made out to PIMA COUNTY TREASURER must accompany the revised set of bluelines and response letter.

For any questions regarding the fee schedule, please go to http://www.pimaxpress.com/SubDivision/Documents/Fees.PDF where you may find the appropriate wastewater review fees at the bottom of page 1. If the number of sheets changes, please adjust the review fee accordingly.

If you have any questions regarding the above mentioned comments, please contact me. Sincerely,




Mike Henrich
Telephone: (520) 740-6832

Copy: Project
06/11/2006 DAVID RIVERA ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department Plans Coordination Office
FROM: David Rivera
Principal Planner

PROJECT: D06-0006
US Bank
Development Plan

TRANSMITTAL DATE: June 11, 2006

DUE DATE: June 20, 2006

COMMENTS:

1. Section 5.3.8.2, LUC, permits a maximum of one year from the date of application to obtain approval of a development plan. If, at the end of that time, the development plan has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this development plan is February 1, 2007.

2. The previous comment was not addressed as requested. See development standards requirements below.

(Previous Comment:) A small, project-location map shall be drawn on the first sheet of the development plan, preferably in the upper right corner. The map should cover approximately one (1) square mile, be drawn at a minimum scale of 3" = 1 mile, and provide the following information.
a. Show the subject property approximately centered within the one-(1) square mile area.
b. Identify conditions within the square mile area, such as major streets and watercourses.
c. Section, township, and range; section corners; north arrow; and the scale will be labeled.
d. The City's jurisdictional limits will be shown, if within the mapped area.
DS 2-02.2.1.D


3. The previous comment was not addressed as requested.

(Previous Comment:) The future curb and sidewalk for Broadway Boulevard must be drawn, labeled and dimensioned. See related comments by the Engineering reviewer on this item.
DS 2-05.2.3.C

4. I acknowledge that A DSMR was requested. Please list the DSMR case number in the lower right corner of all plan sheets, list the date of approval, and any conditions of approval. Provide a copy of the approval memo with the next submittal package.

5. The previous comment was not completely addressed. Please add the requested information in paragraph two.

(Previous Comment:) This development must be provided with bicycle parking at a ratio of eight percent of the number of vehicle parking spaces provided, 25 percent of the space must be class one and 75 percent class two. Per the bicycle parking calculation four class two spaces have been provided. Please draw, label and dimension on the plan the location for the bicycle parking facility.

Show, on the drawing, off-street bicycle parking locations, including materials for lighting and paving, type of security, dimensions,, and the location and type of directional signage. When adjacent to pedestrian paths, indicate the width of clearance available for the pedestrian area. For specifics, refer to Development Standard 2-09.0.
DS 2-05.2.4.Q

6. Add a note stating that the postal service will be delivered inside.

(Previous Comment:) Indicate location and type of postal service to assure there are no conflicts with other requirements, such as pedestrian accessibility, utilities, and landscaping.
DS 2-05.2.4.V

7. I acknowledge that the signs will be permitted under separate permit. Key note 21 for the monument sign could not be verified on the plan. Please ensure that the sign is shown and labeled on the plan.

(Previous Comment:) Indicate the locations of proposed freestanding and pedestal signs to assure there are no conflicts with other requirements and those minimal location requirements can be met. Also if indicate the location of any existing billboards.
DS 2-05.2.4.W

If you have any questions about this transmittal, please call David Rivera, (520) 791-5608.

DGR C:\planning\cdrc\developmentplan\D060006dp2.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan, and additional requested documents.
06/14/2006 DALE KELCH COT NON-DSD TRAFFIC Approved Traffic Engineering approves the proposed development plan.
06/16/2006 KAY MARKS PIMA COUNTY ADDRESSING Approved 201 N. STONE AV., 1ST FL
TUCSON, AZ 85701-1207

KAY MARKS
ADDRESSING OFFICIAL
PH: 740-6480
FAX #: 740-6370


TO: CITY PLANNING
FROM: KAY MARKS, ADDRESSING OFFICIAL
SUBJECT: D06-0006 US BANK/REVISED DEVELOPMENT PLAN
DATE: June 16, 2006



The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and we hereby approve this project.

NOTE:

1: Submit a 24 x 36 Reverse Reading Double Matte Photo Mylar of approved
Development Plan to City Planning. Signed and dated Mylar will be forwarded to Pima
County Addressing prior to assignment of addresses.

2: All addresses will need to be displayed per Pima County Address Standards at the time of final inspection.














jg
06/16/2006 ROGER HOWLETT COT NON-DSD COMMUNITY PLANNING Approved DEPARTMENT OF URBAN PLANNING & DESIGN

Regarding

SUBJECT: Community Design Review Committee Application

CASE NUMBER: CASE NAME: DATE SENT

D06-0006 US Bank 06/14/06

(XXXX) Tentative Plat
(XXXX) Development Plan
(XXXX) Landscape Plan
() Revised Plan/Plat
() Board of Adjustment
() Other

CROSS REFERENCE: C9-00-39, SE-01-28, D02-0041, D02-0034 & S02-011

NEIGHBORHOOD PLAN: Pantano East

GATEWAY/SCENIC ROUTE: Broadway and Pantano

COMMENTS DUE BY: 06/20/06

SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS:

() No Annexation or Rezoning Conditions, Not an RCP - No Comment
() Proposal Complies with Annexation or Rezoning Conditions
() RCP Proposal Complies With Plan Policies
() See Additional Comments Attached
(XXXX) No Additional Comments - Complies With Planning Comments Submitted on: 3/03/06
() Resubmittal Required:
() Tentative Plat
() Development Plan
() Landscape Plan
() Other –
06/21/2006 LOREN MAKUS ENGINEERING REVIEW Approved DATE: June 21, 2006
To: Patricia Gehlen
CDRC/Zoning Manager
FROM: Loren Makus, EIT
Engineering Division


SUBJECT: US Bank
Development Plan D06-0006 (Second Review)
T14S, R15E, Section 08

RESUBMITTAL REQUIRED: None
1. The development plan has been reviewed by the Engineering Division and we recommend approval at this time.

If you have any questions, I can be reached at 791-5550 x1161 or loren.makus@tucsonaz.gov.

Loren Makus, EIT
Senior Engineering Associate
06/24/2006 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

June 24, 2006

Maurita Walker
RSP Architects
502 South College Avenue, Suite 203
Tempe, Arizona 85281

Subject: D06-0006 US Bank Development Plan

Dear Maurita:

Your submittal of May 22, 2006 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter for each agency explaining how each outstanding requirement has been addressed:

ALL BLUELINES MUST BE FOLDED

4 Copies Revised Development Plan (Wastewater, Landscape, Zoning, DSD)

3 Copies Revised Landscape Plans (Zoning, Landscape, DSD)




Should you have any questions, please call me at 791-5608, ext. 1179.

Sincerely,


Patricia Y. Gehlen
CDRC Manager

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/
Via fax: (480)-889-2011