Review Date Reviewer's Name Type of Review Description Status Comments
06/01/2005 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
06/02/2005 JIM EGAN COT NON-DSD FIRE Approved The Development Plan is approved June 02, 2005.
06/06/2005 JCLARK3 ENV SVCS REVIEW Denied * No known landfill with in 1000 feet of this development.
* Refuse enclosure can be serviced. Problem is the refuse trucks cannot make the turn to exit the property after servicing the enclosure. (Turning radius of the refuse service trucks are 35 feet for the rear wheels and 5o feet for the outside bumper.)
06/09/2005 TOM MARTINEZ OTHER AGENCIES AZ DEPT TRANSPORTATION Approved NO COMMENT
D05-0020
RICK ENGINEERING COMPANY
BEACON GROUP EXPANSION
06/14/2005 KAY MARKS PIMA COUNTY ADDRESSING Denied 201 N. STONE AV., 1ST FL
TUCSON, AZ 85701-1207

KAY MARKS
ADDRESSING OFFICIAL
PH: 740-6480
FAX #: 740-6370


TO: CITY PLANNING
FROM: KAY MARKS, ADDRESSING OFFICIAL
SUBJECT: D05-0020 BEACON GROUP EXPANSION/DEVELOPMENT PLAN
DATE: 6/14/05



The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and the following matters must be resolved prior to our approval:

Label section corners on Location Map.

Label proposed building as Bldg. 3.

Correct Block 40 (Lots 2, 3, 6, 7, & 10) to Block 25 on sheets 3 and 4.
06/15/2005 GLENN HICKS COT NON-DSD PARKS & RECREATION Approved DATE: June 15, 2005

TO: Ferne Rodriguez, Development Services

FROM: Glenn Hicks, Parks and Recreation

SUBJECT: CDRC Transmittal, D05-0020 Beacon Group Expansion

CC: Craig Gross
Patricia Gehlen, Development Services


Staff has no comments.






Glenn Hicks
Parks and Recreation
791-4873 ext. 215
Glenn.Hicks@tucsonaz.gov
06/22/2005 JOE LINVILLE LANDSCAPE REVIEW Denied 1) The retention/detention basin on the west side of the property is required to be revised. The eastern slope of the basin does not conform to DS 10-0-1.4, p.78. The slope shall be no steeper than 2:1 per the standard. The slope requirements also apply the basin along Balboa Avenue.

Additional trees should be provided for the southern portion of the basin, if possible. LUC 3.7.4.3.A

2) Revise the plans as necessary to show how grading, hydrology, and landscape structural plans are integrated to make maximum use of site storm water runoff for supplemental on-site irrigation purposes. Provide additional information to show how stormwater is routed to landscape areas.

The landscape plan shall indicate use of all runoff, from individual catch basins around single trees to basins accepting flow from an entire vehicular use area or roof area.

3) Remove any unused keynotes on sheet 3 of the development plan (13 & 20). DS 2-05.2.1.J

4) Revise the plans to curbing to protect landscape areas in the southern portion of the site. LUC 3.7.2.3.B

5) Revise the landscape and development plans to clearly show that the portion of the landscape border on the west side of the Glenn Street entrance meets the 10' minimum width requirement. LUC 3.7.2.4.A.1

6) Revise the parking design to include wheel stops or some other barrier to prevent parked vehicles from overhanging the street landscape borders. DS 2-06.3.3.E

7) Provide details for tree planters located within vehicle use areas. Planters are required to conform to DS 2-06.3.3.C.
See DS 2-06. Figure 5 and DS 3-05. Figure 3 for acceptable designs. DS 2-07.2.2.D

8) Show the parking lot in the southeast corner of the site on the landscape plan. This area is required to comply with all applicable code requirements. LUC 3.7.1.2.B

9) A 6' high masonry wall is required in order to screen the loading areas from Balboa Avenue. Revise the landscape and development plans to include and identify the required walls. LUC Table 3.7.2-I

However, Case # C9-02-10 requires that the loading areas be located on the west side of the site. Revise as necessary.

10) Provide written verification of any approvals received to locate a portion of the code required landscape border and irrigation in the public right-of-way area. Plans may not be approved unless permission is obtained. LUC 3.7.2.4.A.3

11) Revise the landscape plans to specify that the area between the right-of-way line and sidewalk and the area between the sidewalk and the curb, if not covered with vegetation, shall be covered with an appropriate inorganic ground cover, such as decomposed granite. LUC 3.7.2.4.A.4

12) Revise the plans to show any sidewalks/pedestrian facilities in the southern portion of the site. DS 2-07.2.1.A

13) Revise the plans to locate screening plants in accordance with DS 2-06.3.7.B.5.b. Hedges and other vegetative screens shall not extend more than three (3) feet into the street landscape border. If, based on the growing characteristics of the type of plant used, the ultimate
width of the vegetative screen will be greater than three (3) feet, the vegetative screen must be sufficiently set back from the landscape border to accommodate the wider growth.

14) Revise the native plant preservation plan as necessary to improve clarity. A few of the plants could not be located. We suggest an enlarged photo or a lightened photo.
06/23/2005 ROGER HOWLETT COT NON-DSD COMMUNITY PLANNING Denied DEPARTMENT OF URBAN PLANNING & DESIGN

Regarding

SUBJECT: Community Design Review Committee Application

CASE NUMBER: CASE NAME: DATE SENT

D05-0020 Beacon Group Expansion 06/23/05

() Tentative Plat
() Development Plan
() Landscape Plan
() Revised Plan/Plat
() Board of Adjustment
() Other

CROSS REFERENCE: C9-02-10

NEIGHBORHOOD PLAN:

GATEWAY/SCENIC ROUTE:

COMMENTS DUE BY: June 29, 2005

SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS:

() No Annexation or Rezoning Conditions, Not an RCP - No Comment
() Proposal Complies with Annexation or Rezoning Conditions
() RCP Proposal Complies With Plan Policies
() See Additional Comments Attached
() No Additional Comments - Complies With Planning Comments Submitted on:
() Resubmittal Required:
() Tentative Plat
() Development Plan
() Landscape Plan
() Other
REVIEWER: v f 791-4505 DATE: June 15, 2005
DEPARTMENT OF URBAN PLANNING & DESIGN
D05-0020 Beacon Group Expansion


Rezoning C9-02-10, condition #1, states that a development plan needs to be in “substantial compliance with the preliminary development plan dated March 19, 2002.” It appears that new development plans for the Beacon Group Expansion differ extensively from the original preliminary development plan - the proposed industrial building has increased 69.8% in size (from 22,600 to 38,380 sf) and it is now to be an addition to an existing building on site. The new development plan may not be in compliance with condition #1 and may require a change of condition.

New development plans are not in compliance with rezoning condition #6, which reads: “The loading zone and dumpster shall be located on the west side of the site.” New development plans show three (3) loading zones on the east side of the property, adjacent to residential properties. In order to comply with condition #6, please resubmit development plans showing loading zones away from adjacent residential properties to the east, and adjacent to the commercially zoned property to the west. NOTE: A site inspection by staff revealed that the new Habitat for Humanity townhomes along Balboa Avenue are in the final phases of completion, with residents already moving in. Any request to change rezoning conditions affects compatibility of the proposed use with the surrounding existing uses, including residential development, and it will require consideration by the Mayor and Council.
06/24/2005 TIM ROWE PIMA COUNTY WASTEWATER Denied June 23, 2005

TO: Bruce Paton, P.E.
Rick Engineering Company

THRU: Patricia Gehlen
City of Tucson, Development Services Department

FROM: Dickie Fernández, E.I.T.
Pima County Development Services Department
Development Review Division (Wastewater)

SUBJECT: Beacon Group Expansion
Development Plan - 1st Submittal
D05-0020

The proposed sewer collection lines to serve the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use.

1. This project will be tributary to the Roger Road Wastewater Treatment Facility via the Santa Cruz East Interceptor. Provide a letter from PCWWM Planning Services, written within the past 90 days, stating that treatment and conveyance system capacity for this project is available. Contact Robert Decker, PCWWM Planning Services, at (520) 740-6625 regarding this matter.

2. Based on the evaluation of historical sewer improvement district maps, this project would qualify for Participating sewer connection fee rates.

3. ALL SHEETS. Add the project number, D05-0020, to the title block of each sheet. This number should be shown larger or bolder than any cross-reference numbers.

4. A private Sewer Service Agreement for the proposed number of wastewater fixture unit equivalents has been sent to your office. After three original Sewer Service Agreements have been signed by the Owner of Record, the three originals should be returned to Pima County Wastewater Management in order to satisfy the necessary requirements needed to approve the development plan.

5. SHEET 1. Revise General Note 5 to read as shown below

THIS PROJECT HAS 488 PROPOSED AND 313 EXISTING WASTEWATER FIXTURE UNIT EQUIVALENTS, PER TABLE 13.20.045(E)(1) IN PIMA COUNTY CODE 13.20.045(E).

6. SHEET 1. Add the following General Note

MAINTENANCE AND OPERATION OF THE PRIVATE SANITARY SEWER TO ITS POINT OF CONNECTION TO THE PUBLIC SEWER IS THE RESPONSIBILITY OF THE PROPERTY OWNER.

7. SHEET 1. Revise General Note 15 to read

ON-SITE SANITARY SEWERS WILL BE PRIVATE AND WILL BE CONSTRUCTED, OPERATED AND MAINTAINED ON A PRIVATE BASIS. THE LOCATION AND METHOD OF CONNECTION TO AN EXISTING PUBLIC SANITARY SEWER IS SUBJECT TO REVIEW AND APPROVAL BY THE PIMA COUNTY WASTEWATER MANAGEMENT DEPARTMENT AT THE TIME OF SUBMITTAL OF PLUMBING OR BUILDING PLANS.

8. SHEET 4. This project claims to have 313 existing wastewater fixture unit equivalents. Please show the existing private sewer and label it as existing.

9. SHEET 4. Show the size and Pima County plan number of the existing public sewer to which this project is connecting.

10. We will require a revised set of drawings and a response letter addressing each comment. Additional comments may be made during the review of these documents.

The next submittal of this project will be the 2nd submittal. A check for the review fee of this submittal in the amount of $100.00 made out to PIMA COUNTY TREASURER must accompany the revised set of bluelines and response letter.

For any questions regarding the fee schedule, please go to http://www.pimaxpress.com/SubDivision/Documents/Fees.PDF where you may find the appropriate wastewater review fees at the bottom of page 1. If the number of sheets changes, please adjust the review fee accordingly.

If you have any questions regarding the above mentioned comments, please contact me. Sincerely,





Dickie Fernández, E.I.T.
Telephone: (520) 740-6947

Copy: Project
06/28/2005 LIZA CASTILLO UTILITIES TUCSON ELECTRIC POWER Approved SUBJECT: BEACON GROUP EXPANSION
D05-0020

Tucson Electric Power Company has reviewed and approved the development plan
submitted for review June 1, 2005. It appears that there are no conflicts
with the existing facilities within the boundaries of this proposed
development.

Enclosed is a copy of a TEP facilities map showing the approximate location
of the existing facilities.

In order to apply for electric service, call the New Construction Department
at (520) 770-2062. Submit a final set of plans including approved site,
offsite and electrical load plans. Include a CD with the AutoCAD version of
the plans. If easements are required, they will be secured by separate
instrument.

Liza Castillo
Right of Way Agent
Land Management
Tucson Electric Power Co.
(520) 917-8745
lcastillo@tep.com <mailto:lcastillo@tep.com>
06/28/2005 DALE KELCH COT NON-DSD TRAFFIC Approved Traffic Engineering recommends APPROVAL of this DP.

D. Dale Kelch, PE
Senior Engineering Associate
Traffic Engineering Division
(520)791-4259x305
(520)791-5526 (fax)
dale.kelch@tucsonaz.gov
06/29/2005 JOSE ORTIZ ENGINEERING REVIEW Denied DATE: June 29, 2005
FROM: Jose E. Ortiz
Engineering Division

SUBJECT: 2851 N. Balboa Avenue
Development Plan D05-0020 (First Review)
T13S, R13E, Section 36

RESUBMITTAL REQUIRED: Development Plan and Drainage Report.

The Development Plan (DP) and Drainage Report (DR) cannot be approved as submitted. Please address the following review comments prior to the next submittal.

Development Plan:

1. Please include a response letter to the comments along with the corrected copies of the DP.
2. Please label individual lot dimensions and bearings per D.S. 2-02.2.1.5
3. If the development plan consists of more than one (1) sheet, a small index drawing of the site showing the area represented on each sheet is to be placed on the first sheet. Exception: The project location map required in Sec. 2-05.2.1.D may be used, in lieu of a separate index map, on plans having two (2) or more sheets. DS 2-05.2.1.E
4. Label existing visibility triangles per D.S. 2-02.2.1.10.
5. Fully dimensioned loading space(s) and maneuvering area(s) per D.S. 2-02.2.1.14.
6. If applicable show the limits of the 100-year floodplain and water surface elevation per D.S. 2-02.2.1.15
7. Please list estimated cut & fill quantities per D.S. 2-02.2.1.17. Could not find in plan set, please provide.
8. All easement of record must be graphically shown on the plan together with recording docket and page per D.S. 2-02.2.1.20. Verify that all recording dockets are shown.
9. The following information regarding existing utilities shall be provided: the location and size of water wells, water pumping plants, water reservoirs, water lines, fire hydrants, sanitary and storm sewers, including the pipe diameter and the invert and rim elevations of all manholes and cleanouts; the Pima County Wastewater Management Department (PCWMD) reference number; locations of gas lines, electric and telephone lines, poles, and communications cables, on-ground junction boxes, and street lights. If water mains and sewers are not located on or adjacent to the tract, indicate the direction, distance to, and sizes of those nearest the property. Verify that all utilities are shown.
10. Dimension from street monument lines to existing and proposed curbs, sidewalks, driveways, and utility lines per D.S. 2-02.2.1.21.
11. Show all fences, walls, or vegetation for screening and sight visibility by type, material, height, location and spacing per D.S. 2-02.2.1.27. Verify that all required items are being shown.
12. Other significant conditions on the site, such as major rock outcrops, structures, etc., shall be shown. These elements should be indicated in a different line weight than the proposed improvements and labeled to be removed or retained. DS 2-05.2.3.G
13. Conditions on adjacent land significantly affecting the design of the project will be shown, such as the approximate direction and gradients of ground slope; character and location of adjacent development; and drainageways, arroyos, ditches, and channels, including their existing conditions. DS 2-05.2.3.H
14. Show Development plan number on all sheets per D.S. 2-02.2.1.29. (D05-0020)
15. Show refuse container location, size, and access thereto fully dimensioned per D.S. 2-02.2.1.32 and D.S. 6-01.0.
16. Draw locations and indicate types of off-site runoff acceptance points and/or on-site runoff discharge points. DS 2-05.2.4.H.7
17. Preliminary sewer layout, including points of connection to existing sewers, proposed rim and invert elevations at all manhole locations, length and percent of grade between manholes, size of pipe, and proposed flow-thru locations, should be shown if applicable. DS 2-05.2.4.J.1
18. The preliminary sewer layout shall be designed so that manholes will not interfere with street survey monuments. However, survey monuments may be offset from manhole locations if so indicated on the plan. DS 2-05.2.4.J.1.a
19. Show existing or proposed sidewalks along abutting right-of-way. Such sidewalks must comply with accessibility requirements for the physically disabled. DS 2-05.2.4.L
20. Minimum Sidewalk width shall be 5 feet along roadway.
21. Indicate the locations and types of proposed signs (wall, free-standing, pedestal) to assure there are no conflicts with other requirements such as sight visibility and that minimal location requirements can be met. DS 2-05.2.4.W
22. Call out the Grade Breaks at the D/W, if applicable.
23. Please show the proposed roof drainage patterns, 100% of the 10-year flow must be conveyed under the sidewalks including any other site drainage as well. Please provide supporting calculations to demonstrate compliance with D.S. 3-01.4.4. If the location(s) of the roof scuppers have not yet been decided, a general note indicating sidewalk scuppers will be used when the roof scuppers locations have been designed and located will suffice.
24. Add note: "Depress all landscaped areas 6" maximum for water harvesting".
25. "A grading permit and Stormwater Pollution Prevention Plans (SWPPP's) will be required for this project. Submit 3 sets of grading and SWPPP's with text; upon completion and submittal of a grading permit application. A grading permit may not be issued prior to site plan approval. Subsequent comments may be necessary, depending upon the nature and extent of revisions that occur to the plans". Contact Jose E. Ortiz at 791-5550 x1191 for additional information.
26. Depending on flood zone status a Flood Use Permit may be required. The Grading Permit will not be issued prior to the Flood Use Permit approval.
27. Due to the length and change in flow direction of the 42"X29" SRP arch pipes manholes may be required for proper maintenance of the pipes. Verify whether or not manholes are required.
28. Detail B/2 does not appear in horizontal view. Is this the correct detail for this project?


Drainage Report:
1. Please include a response letter to the comments along with the corrected copies of the DR.
2. This review was performed for Development Plan purposes only. Final review and acceptance will be done at the grading plan stage.
3. Addendums to any Drainage Reports and Hydrology Reports etc. are not accepted. The new layout or revisions must be incorporated into the approved Drainage Report.
4. The proposed off-site discharge of 291cfs at concentration point 2 at the 100 year event exceeds the existing discharge of 283cfs at the same location. The increase in the proposed discharge is minimal but shall not exceed existing conditions. Please

If you have any questions, I can be reached at 791-5550 x1191 or Jose.Ortiz@ci.tucsonaz.govs
Jose E. Ortiz
Civil Engineer
City of Tucson/Development Services Department
201 N. Stone Avenue
P.O. Box 27210
Tucson, Arizona 85726-7210
(520) 791-5550 x1191 office
(520) 879-8010 fax
07/01/2005 FRODRIG2 COT NON-DSD REAL ESTATE Denied The following items are needed for the right of way dedication per rezoning,

1.) Legal description of the right of way with a sketch,

2.) Title report dated within 30 days,
07/07/2005 FRODRIG2 OTHER AGENCIES PIMA ASSN OF GOVTS Approved 390 ESTIMATED DAILY TRIPS IN 24 HR PERIOD.
07/22/2005 HEATHER THRALL ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department Plans Coordination Office


FROM: Heather Thrall
Senior Planner

PROJECT: D05-0020
308 W. Glenn Street
Development Plan

TRANSMITTAL: 07/22/05

DUE DATE: June 29, 2005

COMMENTS:

1. Section 5.3.8.2, LUC, permits a maximum of one year from the date of application to obtain approval of a development plan. If, at the end of that time, the development plan has not been approved, it must be revised to be in compliance with all regulations in effect at that time, and must be resubmitted for a full CDRC review. The one-year expiration date for this development plan is May 31, 2006.

2. This project was reviewed in accordance with applicable divisions of the Land Use Code (LUC), Development Standard (DS), American National Standard (ANSI) and International Building Code 2003 (IBC). For reference, the Land Use Code can be found on the internet at www.ci.tucson.az.us/planning under Land Use Code. The Development Standard can be found at www.ci.tucson.az.us/dsd under Codes.

3. Per 3.4.3.7.B of the LUC, if an expansion of land area, floor area or vehicular use area is proposed greater than 25%, the entire site must meet current code requirements. This plan was reviewed under such circumstances.

4. Per DS 2-05.2.1.D.3, please provide the section corners (as in Township, Range and Section) to the project location map on the first page of the plan.

5. Per DS 2-05.2.2.B.1 and B.2, list the current zoning for the proposed development area is O-3, and C-2 for the existing development. Place a note next to the existing zoning note stating "Proposed zoning (for the proposed development sites) is C-2." In addition, please list the Development Plan number "D05-020" to the plan in the lower right hand corner of each page.

6. Per DS 2-05.2.2.B.3, the correct proposed use of the development is required on the plan. Per advisement of the Zoning Administrator, this project is classified as "Craftwork", an Industrial Use. Please amend all references on the plan pertaining to the proposed use as educational to read "Craftwork/Industrial Use."

7. Per DS 2-05.2.2.B.10, a note is required on the plan stating this project is designed to meet the Major Streets and Routes (MS&R) overlay zone requirements, as depicted in Section 2.8.3. of the LUC.

8. Per DS 2-05.2.3, identify existing conditions within 50 feet of the site, and due to the property abutting a Major Street & Route, include conditions on the south side of Glenn Street.

9. Per DS 2-05.2.3.B, if applicable, please include any easements on the development plan, with their respective recording information.

10. Per DS 2-05.2.3.C, the right of way information listed on the plan for Glenn Street indicates the total right of way is only 60 feet, when in actuality it is 64 feet per the City Major Streets and Routes Map. Please revise the plan accordingly.

11. Per DS 2-05.2.3.C, please call out all sidewalk areas throughout and surrounding the project.

12. Per DS 2-05.2.4.A, Coupled with the facet these parcels cannot function independently from one another and buildings generally cannot be built over lot lines, a combination of all lots and associated covenants will be required for this development to proceed. To obtain a copy of the covenants, please log onto the Development Services web site at www.tucsonaz.gov/dsd/Forms To obtain a copy of the tax combination forms, please contact the Pima County Assessor's Office.

13. Per DS 2-05.2.4.B, show existing zoning classifications on and adjacent to the project, with zoning boundaries clearly defined.

14. Per DS 2-05.2.4.D.3 and DS 3-05.C.1, please provide measurements for all PAALs and all points of ingress/egress shown on the plan. The minimum width required for all two-way PAALs is 24 feet.

15. Per DS 2-05.2.2.B.3, a two foot distance must be maintained between any fence or similar structure, and a PAAL. It appears a fence is to be installed along the west lot line, along the PAAL proposed in the areas identified now as lots 1 and 4. Please review the plan, advise if the item shown is a fence. If it is a fence, please ensure the project is revised to meet the above standard.

16. Per DS 2-05.2.4.E, and condition 3 of Rezoning Case C9-02-10, please list the docket and page recording information for the right of way spandrel dedication at the southwest corner of Balboa Avenue and Laguna Avenue.

17. As a review of the entire site is required, please list the building setbacks -for existing and proposed -per current code standards. Note, the required setback for any building along Glenn Street frontage is the greater of 21 feet or the height of the exterior building wall, measured from the back of the future curb. For setback purposes only, Balboa Avenue is considered a developing area because the site is bounded by a Major Streets and Routes. The required setback for any building along Balboa is based on the greater of 21 feet or the height of the exterior building wall, measured from the outside edge of the nearest adjacent travel lane. Please change the building setback notes on the plan to reflect the above information.

Label and dimension existing and future curbs for both Balboa Avenue and Glenn Street, and the travel lane for Balboa Avenue.

Please note, should building setbacks not meet the above, a Board of Adjustment process may be applicable, and further review comments may be forthcoming. See comment 34 for further information on the Board of Adjustment process.

18. Per DS 2-05.2.4.K, 2-08.3.1 and 2-08.5.1.A, a continuous pedestrian pathway is required throughout the development. Sidewalks should be constructed at a minimum of 4' wide. The pedestrian pathway should connect all buildings and the street sidewalks to the site.

Please clarify the pedestrian area located along the west side of the proposed and existing buildings meets the required width.

In addition, please provide a 4' wide sidewalk connecting from the existing sidewalk at building 2, along the existing parking lot to Glenn Street.

Please clarify if access is provided throughout existing building 1 to existing building 2, existing building 3, and the proposed building expansions.

19. Per 2-05.2.4.L, all sidewalks abutting right of way areas and vehicle use areas must meet accessibility standards for physically disabled, thus access ramps at crosswalks connecting to sidewalks must be provided. Per ANSI Chapters 4 and 5, all handicapped ramps must be constructed at a slope of 1:12 or less. Please revise the plans to show such ramps at all areas where sidewalks meet vehicular use areas. Provide a typical detail drawing of the handicapped accessible ramps with dimensions and ratios.

In addition, condition 4 of rezoning case C9-02-10 also requires installation of verification of existing sidewalks, curbing, and access ramps along all street frontages.

Truncated Domes (early warning systems) must be added to all access ramps where transitioning from the pedestrian area to the vehicular use area or at HC access aisles transitioning to the sidewalk area. Please revise the plan accordingly.

20. Per DS 2-05.2.4.M, the plan shows a third smaller existing building on the area listed as lot 8. Please clarify if this building is to remain or be demolished. Should this building remain, please provide the square footage (and height and setbacks) for it and revise the Floor Area Ratio Calculations to reflect its inclusion.

21. Per DS 2-05.2.4.N, label all building heights - from finished grade. Provide building footprint dimensions for all buildings and their specific use.

22. Per DS 2-05.2.4.O and LUC 3.4.5.1, the number and size of loading zones required for this project depends upon the total gross floor area and property use. With the Craftwork Industrial Use, a total of 3 loading spaces are required, at a minimum dimension of 12 feet wide by 55 feet long. The plan indicates the loading zones are only 12 feet by 45 feet. Note, after addressing comment 20, should the square footage of the buildings increase to over 110,000, an additional loading space will be required. Please amend the plan accordingly.

22. Per condition 6 of rezoning case C9-02-10, the loading zones shall be located on the west side of the site. The submitted development plan shows the loading zones positioned on the east side of the site. This proposal requires Mayor and Council approval, as this is a change of conditions to a rezoning case. Please revise the plan to meet the requirements of this rezoning case. The alternative is to obtain permission from Mayor and Council for a change in the rezoning conditions. Please contact the Rezoning Division staff at DSD for further information on this process.

23. Per DS 2-05.2.4.P, the parking requirements for the development should be listed on the plan. Please revise the plan notes to state the development is to have parking per Land Use Code section 3.3.4, which requires Craftwork uses to have parking at a ratio of 1 space per 500 feet of gross floor area.

With the approximate gross floor area of the entire development (scaled measurements were used for the smallest existing building to derive 860 square feet) consisting of 75,440 square feet, 151 parking spaces are required at minimum for the project. The plan lists 116 parking spaces are provided for the site. Staff's review determined only 113 parking spaces were shown on the plan. Please review and revise the plan to meet parking requirements. The alternative is to apply for and obtain a Board of Adjustment variance to delete a portion of required parking spaces. See comment 34 for further information on the Board of Adjustment process.

24. Per DS 3-05.2.3.C.1, 2 and 3, please install wheel stop barriers for all parking spaces to prevent damage to adjacent landscaping and vehicles. The wheel stop barriers must be installed to also ensure pedestrian walkway width of 4 feet is not compromised. In addition, the wheel stop barriers should be installed within 2.5 feet from the front of the parking space. Please provide a typical detail drawing of the wheel stop barrier.

25. Per DS 3-05.2.2.D, please provide back up spurs at the north part of the existing parking lot on Lot 1, and at the west end of the row of handicapped parking spaces shown in front of the proposed building. Please review DS 3-05.2.2 for requirements for back up spurs, either dimensioning the plan or providing a typical detail drawing.

26. Per IBC 2003, for development with 151 parking spaces required, 6 handicapped accessible parking spaces are required at minimum. Of those 6 handicapped parking spaces required, 1 must be van accessible. Please label all handicapped parking spaces, and their accessibility type, on the plan.

27. The submitted plan shows an area to the west side of the site to have 60 degree angled parking spaces. Per DS 3-05.6.0.Table 1, for a 60 degree angled parking space at a width of 8.5 feet, a minimum depth of 19.8 feet is required for the parking space. Please revise the typical drawings submitted accordingly. If this requirement cannot be met, a redesign of the parking spaces would be applicable.

28. Per DS 2-05.2.4.P, provide a typical drawing for a non-handicapped parking space.

29. Per DS 2-05.2.4.Q and LUC 3.3.4, the number of bicycle parking spaces required is equal to 8 percent of the total amount of vehicle parking spaces required or offered (greater number prevails). Of this ratio, 90 percent shall be class 1 (locker type) and 10 percent shall be class 2 (lock to fixture type). Please revise the plan notes and bicycle details accordingly. Please provide typical detail drawings of both bicycle parking types, including aerial and elevation drawings with dimensions. Be sure to clarify the width of the sidewalk area between the bicycle parking clearance space and the proposed building.

30. Per DS 2-05.2.4.T, be advised staff noted the dumpster location appears to be in conflict with the paths of passenger vehicles should the dumpster enclosure doors be open. In addition, waste collection vehicle access appears compromised. Please contact Environmental Services review staff for assistance with positioning the dumpster enclosure to code and to requirements of rezoning case C9-02-10 (stating the dumpster enclosure must be positioned on the west side of the site).

31. If applicable, provide locations of signs with dimensions. In addition, staff noted possible free-standing lighting was provided in the proposed parking lot north of the proposed building. Please provide typical detail drawings for the pole, with height and type of lighting information.

32. Staff acknowledges the landscaping plan shows a 5 foot vegetative buffer in front of the proposed screen wall (scaled at 85 feet long) at the east side of the site along Balboa Avenue. Please provide a clarification how this wall will meet condition 8 of rezoning case C9-02-10.

33. Please review the plan and ensure a revision to the development requirement notes is done, based upon the prior review comments.

34. Once all corrections are made to the plan, staff will be able to provide official Board of Adjustment referral comments indicating the variances needed to proceed with the project and to obtain zoning approval.

35. Please provide a separate response letter advising how conditions of rezoning case C9-02-10 have been met for this project.

36. Please note, depending upon the information provided on the resubmittal, further review comments may be forthcoming. Should you have any questions on this review, please contact me via email at Heather.Thrall@tucsonaz.gov or at 791-4541x1156.

If you have any questions about this transmittal, please call (520) 791-5608.

C:\planning\cdrc\developmentplan\D005-020.308w.glenn.doc


RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development plan, and additional requested documents.
07/25/2005 CRAIG GROSS ZONING-DECISION LETTER REVIEW Completed