Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - DEVELOPMENT PLAN
Permit Number - D04-0026
Review Name: RESUBMITTAL - DEVELOPMENT PLAN
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/13/2004 | FERNE RODRIGUEZ | START | PLANS SUBMITTED | Completed | |
08/16/2004 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | DATE: August 16, 2004 To: Craig Gross Planning Administrator FROM: Loren Makus Engineering Division SUBJECT: Pantano Gardens Development Plan D04-0026 (Second Review) T14S, R15E, Section 9 RESUBMITTAL REQUIRED: Development Plan and Drainage Report. The Engineering Section has reviewed the Development Plan (DP) for Pantano Gardens and does not recommend approval of the DP at this time. The following review comment needs to be addressed in the next submittal. Development Plan: 1. As previously commented, provide a letter from the Department of Transportation confirming that funds contribution for drainage improvements has been made as required by zoning condition 10. As indicated in the response letter, maximization of water harvesting will be demonstrated in the grading plan submittal. If you have any questions, or if you wish to set up a meeting, I can be reached at 791-5550 x1161 or loren.makus@tucsonaz.gov. Loren Makus, E.I.T. Senior Engineering Associate |
08/17/2004 | JOE LINVILLE | LANDSCAPE | REVIEW | Approved | |
08/18/2004 | JCLARK3 | ENV SVCS | REVIEW | Approved | |
08/26/2004 | DAN CASTRO | ZONING | REVIEW | Approved | |
08/29/2004 | DALE KELCH | COT NON-DSD | TRAFFIC | Approved | Traffic Engineering REJECTS this DP: 1.The required TIA has still not been submitted. 2. The curb return radii at the access points to the site are required to be 25' radius minimum. Label the returns as to their radius. D. Dale Kelch, EIT Senior Engineering Associate Traffic Engineering Division (520)791-4259x305 (520)791-5526 (fax) dale.kelch@tucsonaz.gov |
08/29/2004 | DALE KELCH | COT NON-DSD | TRAFFIC | Approved | Traffic Engineering is in receipt of and APPROVES the submitted Traffic Study for this project. This submission satisfies condition 1.G for the rezoning case (C9-95-32) associated with this project. D. Dale Kelch, EIT Senior Engineering Associate Traffic Engineering Division (520)791-4259x305 (520)791-5526 (fax) dale.kelch@tucsonaz.gov |
09/10/2004 | TIM ROWE | PIMA COUNTY | WASTEWATER | Approved | August 16, 2004 TO: James King, Rick Engineering Company THRU: FROM: ____________________________________ representing the Pima County Departments of Wastewater Management and Environmental Quality SUBJECT: Pantano Gardens - Submittal D04-026 The proposed sewer collection lines to serve the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use. 1. While there is no objection to this development plan, it may not be approved until the capacity response letter and the sewer service agreements have been received. Upon receipt of these documents, the project will be approved. If you wish to discuss the above comments, please contact me at the phone number provided above, under my signature. Copy: Project |
09/10/2004 | TIM ROWE | PIMA COUNTY | WASTEWATER | Approved | SEWER SERVICE AGREEMENTS HAVE BEEN RECEIVED. |
09/13/2004 | CRAIG GROSS | ZONING-DECISION LETTER | REVIEW | Completed |