Permit Number: D04-0023
Parcel: 12108001B

Address:
1101 N WILMOT RD

Review Status: Completed

Review Details: RESUBMITTAL - DEVELOPMENT PLAN

Permit Number - D04-0023
Review Name: RESUBMITTAL - DEVELOPMENT PLAN
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/16/2004 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
07/16/2004 JOE LINVILLE LANDSCAPE REVIEW Approv-Cond 1) Per LUC 3.7.3.2.B, "screens along a street frontage must be located on the development side of the street landscape border so that they do not obstruct the view of the street
landscape border from the street". The existing screen wall does not conform to the regulation. Revise the plans as necessary to conform with LUC 3.7.3.2.C.

2) Tree plantings in the vicinity of the refuse storage area may require relocation in order to provide the vertical clearance of 15' required by DS 6-01.2.1.B.1
07/16/2004 JOE LINVILLE LANDSCAPE REVIEW Approv-Cond Per plans presented at meeting on 8/06 relevant criteria has been met. Mylars to reflect compliance with previous comment.
07/19/2004 KAY MARKS PIMA COUNTY ADDRESSING Approv-Cond 201 N. STONE AV., 1ST FL
TUCSON, AZ 85701-1207

KAY MARKS
ADDRESSING OFFICIAL
PH: 740-6480
FAX #: 740-6370


TO: CITY PLANNING
FROM: KAY MARKS, ADDRESSING OFFICIAL
SUBJECT: D04-0023 STARBUCKS COFFEE / REVISED DEVELOPMENT PLAN
DATE: JULY 19, 2004



The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and the following matters must be resolved prior to our approval:

1: Add recorded Book and Page to Catalina Heights Annex in Title Block.
07/21/2004 GLYNDA ROTHWELL UTILITIES TUCSON ELECTRIC POWER Approved SUBJECT: Starbucks Coffee
D04-0023

Tucson Electric Power Company has reviewed and approved the development plan dated July 14, 2004.

Please submit a final set of plans including electrical load plans, to determine how TEP will serve this commercial development. If easements are required, they will be secured by separate instrument. Submit your final plans a minimum of eight (8) weeks prior to requiring service.



Liza Castillo
Land Management
Tucson Electric Power Company
lcastillo@tep.com
Office: (520) 917-8479
Cell Phone/Pager: (520) 904-2668
Fax: (520) 917-8400
07/27/2004 ROGER HOWLETT COT NON-DSD COMMUNITY PLANNING Approved DEPARTMENT OF URBAN PLANNING & DESIGN

Regarding

SUBJECT: Community Design Review Committee Application

CASE NUMBER: CASE NAME: DATE SENT

D04-0023 Starbucks Coffee 07/27/04

( ) Tentative Plat
() Development Plan
() Landscape Plan
( ) Revised Plan/Plat
( ) Board of Adjustment
( ) Other

CROSS REFERENCE: C9-85-80, CD9-85-80

NEIGHBORHOOD PLAN: Arcadia/Alamo Area Plan

GATEWAY/SCENIC ROUTE: none

COMMENTS DUE BY: July 29, 2004

SUBJECT DEVELOPMENT PLAN/PLAT HAS BEEN REVIEWED BY COMMUNITY PLANNING AND PRESERVATION, AND STAFF SUBMITS THE FOLLOWING COMMENTS:

( ) No Annexation or Rezoning Conditions, Not an RCP - No Comment
( ) Proposal Complies with Annexation or Rezoning Conditions
( ) RCP Proposal Complies With Plan Policies
( ) See Additional Comments Attached
() No Additional Comments - Complies With Planning Comments Submitted on: 6/22/04
( ) Resubmittal Required:
( ) Tentative Plat
( ) Development Plan
( ) Landscape Plan
( ) Other

REVIEWER: K. Aragonez 791-4505 DATE: 7/21/04
07/28/2004 JCLARK3 ENV SVCS REVIEW Approved
07/29/2004 PETER MCLAUGHLIN ZONING REVIEW Approv-Cond CDRC TRANSMITTAL


TO: Development Services Center
Plans Coordination Office

FROM: Peter McLaughlin
Senior Planner

FOR: Patricia Gehlen
Principal Planner

PROJECT:
D04-023
Starbucks Coffee
NWC Speedway & Wilmot
Development Plan

TRANSMITTAL: July 29, 2004
DUE DATE: July 29, 2004

The Zoning Review Section approves the development plan for this project, subject to the following changes on the sign-off copies. However, should there be any changes requested by other CDRC members, the Zoning Review Section approval is void, and we request copies of the revised development plan to verify that those changes do not affect any zoning requirements.


1. If the project site is part of the whole shopping center property rather than a separate lot, remove the Parcel 1 label, Pad 1 lot dimensions, bearings, square footages, acreage, and the statement that reads "legal description available under separate document" from the aerial photograph.

If you have any questions about this transmittal, please call Peter McLaughlin, (520) 791-5608.
08/02/2004 CRAIG GROSS ZONING-DECISION LETTER REVIEW Completed
08/02/2004 JIM TATE ENGINEERING REVIEW Approved TO: Craig Gross; CDRC Coordinator
DATE: August 2, 2004

SUBJECT: Engineering review of the Starbucks Coffee Development Plan. The activity number is D04-0023.

SUMMARY: The Development Plan and Drainage Report were received by Engineering on July 17, 2004. Engineering has reviewed the received items recommends approval of the Development Plan and the Drainage Report.

APPROVAL: DP, DR

GENERAL COMMENTS

1. The Drainage Report was reviewed for Development Plan purposes only.

2. A Grading Plan and Permit will be required. Proposed grading in excess of 5,000 yards is designated "engineered grading" and a soils engineering report is required with the Grading Plan submittal. IBC Chapter 36, Section 9. The Soils Report must also address the requirements detailed in the Standards Manual for Drainage Design and Floodplain Management, SMDDFM, 14.2.6.

James C. Tate, P.E., CFM
Civil Engineer