Plan Review Detail
Review Status: Requires Resubmit
Review Details: TWPE 60% DESIGN REVIEW v.1
Plan Number - TW-PLAN-0826-0155
Review Name: TWPE 60% DESIGN REVIEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| TWPE Construction | APPROVED | ||||
| TWPE Project Managers | REQUIRES RESUBMIT | ||||
| TWPE Project Supervisor Oversight | REQUIRES RESUBMIT | ||||
| TWPE Cathodic Protection | REVIEW COMPLETED | ||||
| TWPE Civil Engineers (CE) | REVIEW COMPLETED | ||||
| TWPE Engineering Manager Oversight | REVIEW COMPLETED | Comments were provided during internal meeting with TW on 9/3. Comments included considering a revised alignment at the treatment facility, looking at placing the conveyance line in the alley instead of going out to Camino de O Oeste. Additionally, consultant shall consider revising the alignment on Mars St to follow the northern edge, maintaining sufficient offset so that the trench limits for the pipe lay outside of the curb&gutter/wedge curb. | |||
| TWPE Maintenance | REVIEW COMPLETED | ||||
| TWPE Pipeline Protection | REVIEW COMPLETED | ||||
| TWPE Senior Engineering Associates (SEA) | REVIEW COMPLETED | ||||
| TWPE System Planning | REVIEW COMPLETED | SP hydraulic analysis attached. 12-inch TM is sufficient for 1000 gpm design flow from Well Z-014C. |