Plan Review Detail
Review Status: In Review
Review Details: TWPE 90% DESIGN REVIEW v.1
Plan Number - TW-PLAN-0326-0052
Review Name: TWPE 90% DESIGN REVIEW v.1
Review Status: In Review
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| TWPE Civil Engineers (CE) | PENDING ASSIGNMENT | ||||
| TWPE Deputy Director - Authorization | REQUIRES RESUBMIT | Some areas we are relocating for drainage structures. Other locations we are replacing in-kind with the same size pipe. Is this based on age or other? Need to justify. | |||
| TWPE Engineering Manager - Authorization | REQUIRES RESUBMIT | ||||
| TWPE Engineering Chief - Authorization | REVIEW COMPLETED | TW-PLAN-0326-0052 22nd St Camino Seco to Houghton Rd 1) Sheet W1: Use updated title block which has signature lines for Chief Engineer and Deputy Director sign off. 2) Sheet W1: Why are there 3 plan numbers shown. There is the legacy # 1-2025-004 and then TW-PLAN-0326-0052, what is 4-014-2025? 3) Sheet W6: What is the purpose of the line extension on the eastern end of this sheet past station 52+00? 4) Sheet W6: Add callout for lateral at station 52+80 5) Sheet W7: We typically do not have additional corrosion protection for lines less than 16”. Has the TW corrosion team, Victor Ruedas, reviewed these plans? 6) Sheet W9: Clarify if the existing 8” Stl gas line is being abandoned? Previous sheets show line work “ABAND” 7) Sheet W13: Can we go shallower on the new pipe around station 105+00? 8) Sheet W14: From around station 107+00 to station 110+00, can we not maintain a consistent pipe slope? |
|||
| TWPE Survey | REVIEW COMPLETED |