Plan Number: TR-FTTP-1026-00017
Parcel: 13106003A

Review Status: Requires Resubmit

Review Details: RIGHT OF WAY REVIEW v.1

Plan Number - TR-FTTP-1026-00017
Review Name: RIGHT OF WAY REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
ROW Engineering Review Standard REQUIRES RESUBMIT Zone 238 TCP revisions required for construction coverage. Orientate the traffic control plans to match the orientation of the plan review sheet where applicable. Ensure all road names clearly identified. Provide a call out identifying which traffic control phase goes to which plan design sheet.

Please revise the Zone 238 traffic control plan to clarify coverage for the construction activities listed below. The TCP maps the general work corridors, but several phases lack an explicit setup assignment or sufficient detail for the proposed boring, vault installation and associated surface operations.

References below use PDF page numbers. Suggested revisions address the identified review gaps; the TCP designer should verify each setup against actual conditions and the applicable MUTCD, Arizona Supplement and City of Tucson requirements before resubmittal.

1. E 32nd Street from Jefferson Avenue to Sahuara Avenue
References: Zone 238.3, drawings 1-3; design PDF pp. 36-38. Includes the labeled 397-foot, 945-foot and 484-foot boring segments and vault installations. TCP reference: p. 2.
Finding: Phases 13-17 appear on the inset map, but the note assigning locations to the Phase 1 detail lists only Phases 7-12. The applicable setup for Phases 13-17 is therefore not explicitly established.


Provide a phase schedule with street limits, design-sheet references and the work activity. Show drill equipment, launch and receiving pits, potholes, vault excavations and support vehicles within the protected work area.

Show usable travel width, warning signs, tapers, channelizers and actual flagger stations where alternating traffic is required. Address intersecting streets and alleys, pedestrian routes and driveway access.

2. E 36th Street from Jefferson Avenue to the eastern curve near Sahuara Avenue

References: Zone 238.1, drawings 1-3; design PDF pp. 10-12. Includes the labeled 760-foot and 941-foot boring segments, vaults and connecting work. TCP reference: p. 2.

Finding: Phases 18-22 appear on the inset map but are omitted from the note identifying the phases that use the illustrated typical. The setup and operating limits for this corridor remain unclear.

Show the sequence for boring, vault installation and restoration. Establish whether each stage maintains two-way traffic or requires alternating one-way traffic, and dimension the remaining travel width.

Adapt the setup for the eastern curve, intersections and driveways. Verify visibility to warning signs and flagger stations; show pedestrian routing and equipment placement where the standard example does not fit.

3. E 32nd Street and Van Buren Avenue intersection
References: Zone 238.3, drawing 2; design PDF p. 37, including the 159-foot connecting bore south along Van Buren Avenue. TCP references: pp. 3-4.
Finding: The TCP depicts the general location but labels the operation as flagging with aerial crossing. The corresponding design shows underground boring. Traffic control is partially shown, but the proposed operation and its surface footprint are not adequately defined.

Label actual staffed flagger stations separately from flagger warning signs. Provide an intersection operating sequence, communication method and controls for each approach that can enter the restricted section. Show suitable stopping locations, visibility and pedestrian crossings.

4. Sahuara Avenue alley mouths and tie in vaults
References: Zone 238.2, drawing 1, design PDF p. 24; Zone 238.4, drawing 1, p. 48; Zone 238.5, drawing 1, p. 60. TCP references: alley phase mapping and p. 10 typical; compare with pp. 11-12 where applicable.

Finding: The alley phases identify these general locations, but roadside protection is unclear where equipment or vault access reaches Sahuara Avenue. Several endpoint vaults are referenced to another project, leaving the current tie-in scope uncertain.

Suggested revisions:
Identify the current scope at each endpoint: new vault installation, access to an existing vault, cable pulling, splicing or connection to work under another permit. Clearly distinguish the referenced project work.

Show the excavation and equipment footprint relative to Sahuara Avenue, the shoulder and pedestrian route. If all operations remain inside the alley, demonstrate that the alley setup protects them without encroaching on the roadside.

Where roadside space is affected, assign an appropriate shoulder, lane or pedestrian-control detail. Do not assume the existing Sahuara detail applies to every alley mouth; show its applicability and any necessary modifications.

5. Moving bore potholing and vault operations throughout the alleys
References: Construction sheets throughout Zones 238.1-238.5. TCP reference: p. 10, the 180-foot alley-closure example applied to Phases 34-82.

Finding: One short closure example is applied to numerous alley phases without explaining how the closure moves, where equipment and excavations sit, or how intervening entrances are controlled. The corridors are mapped, but operating limits are not sufficiently defined.

Suggested revisions:
Add a phase schedule or annotated alley map showing active closure limits, work direction, access points and the applicable typical. State whether only one phase operates at a time; show how concurrent work will be coordinated if proposed.

Show the drill rig, support vehicles, pits, potholes and vault work inside each active closure. Adjust its length to the actual footprint rather than treating 180 feet as suitable for every location.

Specify physical closure barricades and ROAD CLOSED signing at both ends and at intermediate entrances that lead into the work area. Show local access and emergency passage arrangements; where passage cannot be maintained, identify the approved alternate arrangement.
Transportation Application Review Express REVIEW COMPLETED Application completeness check done