Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: TP-PRE-0923-00335
Parcel: 13323164A

Review Status: Approved

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - TP-PRE-0923-00335
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Fire New Construction REVIEW COMPLETED TP-PRE-0923-00335 • Pre-Application Conference Review v1 • 7150 E SPEEDWAY BL TUCSON, AZ 85710: Based on the information provided, TFD has the following comments:
Separate permits required for:
- Underground storage tank (fire construction permit)
- Flammable and combustible liquids (operational permit)
Contact inspector Jesus Silva - 520.837.7094 / jesus.silva@tucsonaz.gov
Questions regarding this review: patricia.shelton@tucsonaz.gov / 520.837.7082
Site Engineering REVIEW COMPLETED 1. Pedestrian circulation required to Speedway, Finance Center Drive, the refuse enclosure.
2. Refuse enclosure needs capacity for both trash and recycling, and must meet the requirements of TSM 8-01.
3. Maximize Water Harvesting
Joshua Garcia
joshua.garcia@tucsonaz.gov
Site Landscape REVIEW COMPLETED Comments:
1. Landscape/NPPO has no concerns or questions about this proposed project.
2. All landscaping and water harvesting areas shall also be protected from fueling and gas tank watershed areas. The drainage report shall clearly address this issue and provide proper recommendations as to the appropriate locations for water harvesting.
3. Any and all changes to the landscape borders and interior parking lot landscaping, including but not limited to shade trees will require full landscape plans.

If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988
Site Zoning REVIEW COMPLETED CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review

FROM: Wyatt Berger, Lead Planner

PROJECT: Thursday Pre-submittal meeting – TP-PRE-0923-00335
Address: 7150 East Speedway Boulevard
Parcel(s): 133-23-164A
Zoning: PAD-3, Gateway Centre Planned Area Development
Existing Use: “Retail Commercial”
Proposed Use: “Retail Commercial”

TRANSMITTAL DATE: October 9, 2023

COMMENTS:
1. Development must comply with Administrative Manual Section 2-06.0.0: Development Package (Tentative Plats and Site Plans). Building permits may be applied for concurrently with the development package; however, the development package must be approved prior to zoning approval of any associated building permits.

2. The site is within Development Area 1 of PAD-3, Gateway Centre Planned Area Development. The proposal is considered a “Retail Commercial” land use and is permitted in Development Area 1.

3. Per Page IX-37 of the PAD document, the minimum required setback to all adjacent rights-of-way is a distance equal to 60% of building height, but not less than twenty feet.

4. Per Page IX-37 of the PAD document, maximum building height shall not exceed 30 feet within 100 feet of the Speedway Boulevard or Kolb Road rights-of-way, not to exceed 45 feet on the remainder of the site.

5. Per UDC Table 7.4.4-1, one motor vehicle parking space is required per 300 square feet gross floor area for retail uses. Ensure the entire site meets this parking requirement. Areas at gasoline pumps do not count toward required parking (UDC 7.4.6.C.2).

6. Per UDC UDC Table 7.4.8-1, one short-term bicycle parking space is required per 5,000 square feet gross floor area, with a minimum requirement of two spaces. One long-term bicycle parking space is required per 12,000 square feet gross floor area, with a minimum requirement of two spaces.

7. Ensure compliance with Technical Standards Manual Section 7-01.4.3. All sidewalks must be a minimum of four feet wide and installed to avoid any obstruction which decreases the minimum width to less than four feet.

8. Provide a pedestrian circulation path from the development to the proposed waste enclosure as well as to the existing sidewalk along any adjacent street (TSM 7-01.3.3.A and .B).

9. The bollards proposed between the motor vehicle parking and the pedestrian circulation area in front of the fuel center cannot be separated more than five feet from each other (TSM 7-01.4.2.B).

10. Ensure access standards found in Section 7.8 of the UDC and Sections 7-01.0.0 and 10-01.0.0 of the Technical Standards Manual are met.

11. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions, please contact me at Wyatt.Berger@tucsonaz.gov or at 520-837-4951.
Traffic Engineering Review REVIEW COMPLETED TP-PRE-0923-00335
7150 E. Speedway Blvd.

Comments:
1. A Traffic Impact Analysis will be required.

David Stiffey
DTM Project Coordinator
David.Stiffey@tucsonaz.gov
TW New Area Development REVIEW COMPLETED TP-PRE-0923-00335 - Pre-Application Conference Review v1 – 7150 E SPEEDWAY BL

1. Tucson Water has no objections to, or comments on, the proposed development.

2. The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to:

Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
201 N. Stone Avenue, #2-220
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov