Plan Review Detail
Review Status: Approved
Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1
Plan Number - TP-PRE-0826-00161
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| Fire New Construction * | REVIEW COMPLETED | -Based on the information provided. TFD would ask to keep the driveways as wide as possible. 20' is the requirement, however, we are willing to accept a narrower driveway within reason. john.vincent@tucsonaz.gov 5203495581 |
|||
| ROW Engineering Review * | REVIEW COMPLETED | DTM Review Comments: 1) Sidewalk meeting PAG 200 standards - 5' Sidewalk with 3' landscape buffer between curb and sidewalk 2) Placement of Curb will be required along Santa Cruz frontage as continuation curb line coming off 29th st. 3) All Driveway will be required to meet PAG 206, Technical Standards 10-01.4.3, COT Code Chapter 25 - Sec 25-38. Driveway to maintain 20' max width maintaining 12' Separation. Share Driveway Access not to exceed 30' combine with. 4) Unused curb cut located along 29th street will be required to be closed and curb restored to PAG standard detail along with Sidewalk in that area. Note that Fire and Environmental services will require minimum access width to lots of 20' 5) Plan reviewed and considered as Conceptual design as current parcel and lot information on Map Tucson does not match proposed lot lines. Not all lots are time of separation will required that street frontage access be maintained. Parcel information for this location is limited as noted by Zoning and Site engineering. Please Refer to City of Tucson web site - Transportation permit section for update Permit fees and review conditions - https://www.tucsonaz.gov/Departments/Transportation-Mobility/Permits-and-Codes-Section/Rate-and-Fee-Changes Contact information : Zane.Swenson@tucsonaz.gov |
|||
| Site Engineering * | REVIEW COMPLETED | Permit Activity Number: TP-PRE-0826-00161 Project: Multifamily Subdivision Location: 11809046G Review Date: 8/27/2026 Reviewer: Marco Contreras – Engineering Associate – Site Engineering Related Cases: *This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-6 and Technical Standards Manual (TSM) Section for waste management, Pedestrian Access, Hydrology -Retention/Detention Requirements, and all site standard code.* City of Tucson Code: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes Drainage Manual Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/cot-drainage-manual-searchable.pdf Design standards for Stormwater Detention and Retention Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf Site Engineering Review Comments: 1. Based on the proposed 16 dwelling units, that would require potentially 16 trash APC’s and 16 recycling APC’s. It will need to be shown how APC’s will be effectively screened and stored, and how trash collection will function on this site. Site Engineering has coordinated with Environmental Services, and they have determined that as currently proposed, complete waste management will not be feasible based on required distancing requirements regarding APC positioning. It will be required the coordination with Environmental Services be done so that a reasonable solution can be devised. The contact to reach out to at ES will be Andy Vera at Andy.vera@tucsonaz.gov. Site Engineering will be flexible in regard to navigating how compliance will be achieved based on ES's determination. 2. Please submit a supplemental overall site plan with permit. 3. It will need to be determined whether the proposed development qualifies under a Minor Subdivision designation per UDC Section 8.4.3.B. All applicability criteria must be met to proceed under this process. a. If the intended Minor Sub does not meet ALL criteria, then submitted application will switch to Final Plat and a Tentative Plat (development package, DP) will be required to be submitted in addition. *** Please note: this review is for Pre-Application purposes. Please be aware that additional comments may be forthcoming during formal review process. If you have any questions or concerns, please contact Marco Contreras at marco.contreras@tucsonaz.gov |
|||
| Site Landscape * | REVIEW COMPLETED | PLANNING AND DEVELOPMENT SERVICES DEPARTMENT REVIEWER: CHAD KELLER, PLA SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION PROJECT: PROPOSAL FOR A SINGLE LOT TO BE SUBDIVIDED INTO 4 LOTS ACTIVITY NO: TP-PRE-0826-00161 ADDRESS: 11809046G ZONING: RESIDENCE ZONE (R-1) LAND USE: MIDDLE HOUSING; OPTION - MULTIFAMILY 8.25.26 THE COMMENTS PROVIDED ARE PRELIMINARY AND ARE NOT TO BE ASSUMED AS A COMPLETE REVIEW OF THE PROPOSAL. DURING THE DEVELOPMENT PACKAGE REVIEW PROCESS, A FULL REVIEW WILL BE MADE BY THE SITE LANDSCAPE/NPPO REVIEW SECTION TO ENSURE COMPLIANCE WITH THE APPLICABLE CITY OF TUCSON UNIFIED DEVELOPMENT CODE, TECHNICAL STANDARDS MANUAL AND ADMINISTRATIVE MANUAL REQUIREMENTS FOR SITE LANDSCAPE, NATIVE PLANTS AND RAINWATER HARVESTING. SITE LANDSCAPE/NPPO SECTION REVIEW COMMENTS MIDDLE HOUSING COMMENTS: 1. If these parcels are eligible and feasible for a Middle Housing development, then please see site zoning comments for the Middle Housing site landscape requirements. 2. A Native Plant Preservation Plan will be required for this development prior to any disturbance on site. See UDC 7.7 for requirements. MULTIFAMILY REQUIREMENTS: 3. If it is determined that this site and configuration can only support a multifamily commercial development, then the following comments will be applicable. 4. Provide a Native Plant Preservation Plan (NPPP) or a NPPO waiver per UDC 7.7. See UDC 7.7.3. Applicability; UDC 7.7.4 NPPO General Provisions and Standards; UDC 7.7.4.c. Plan Approval Prior to Permitting; UDC 7.7.4.d. Professional Expertise 7.7.5.c.5; also see AM 2-11.3.0 Permitted Exceptions. If applicable, the Planning and Development Services Department will provide the applicant with the NPPO waiver form upon request. COPY THE FOLLOWING LINK INTO YOUR INTERNET BROWSER FOR ACCESS TO THE NPPO WAIVER: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/applicationsforms/nppoapp-2025-v.2-fillable-1.pdf 5. UDC 7.6.2. APPLICABILITY The provisions of this section apply to the following: All new developments require the submittal of a landscape plan set. Preparation of the landscape plans shall adhere to UDC 7.6 and Administrative Manual 2-10. 6. Parking lot canopy trees are required at 1 tree for every 4 parking spaces provided, see UDC 7.6.4.B. Structurally covered parking spaces do not count toward the ratio, see UDC 7.6.4.B.1.c (8). Trees are to be distributed evenly throughout the parking area, see UDC 7.6.4.1.a.(1). See Technical Standards Manual 5-01.3.0 for additional landscaping in vehicular use area requirements. 7. Interior landscape borders per UDC 7.6.4.C.3 and Table 7.6.4-1 and proposed multifamily land use: A. An interior landscape border is required on multifamily land use sites adjacent to residence zones. This is the case at multiple property lines within this proposal. 8. Street landscape borders per UDC 7.6.4.C.2 and Table 7.6.4-1 and proposed multifamily land use along MS&R and non-MS&R: A. Santa Cruz and Silverlake require 10’ landscape borders. All street landscape borders shall be designed on the project side of the ROW/Future ROW. 9. DTM review is required for all planting and irrigation in the ROW prior to the approval of the development package. Reach out to David Marhefka (david.marhefka@tucsonaz.gov) for review and approval if applicable for this project. 10. A drip irrigation plan and details are required for all proposed landscape planting areas. 11. All landscape plans shall incorporate water conserving design as defined in UDC Section 7.6.6, Use of Water, and as described in the Technical Standards Manual 5.01-5.11. 12. A Commercial Rainwater Harvesting plan is required: See Technical Standards Manual 4-01.3.0 RAINWATER HARVESTING PLAN. A Rainwater Harvesting Plan shall be submitted with all applications for commercial developments at which landscaping is required. The Rainwater Harvesting Plan shall consist of two elements: a Site Water Budget and a Water Harvesting Implementation Plan. Preparation of the Rainwater Harvesting Plan elements requires coordination between project managers, site engineers and landscape architects from the inception of the project. The two elements of the Rainwater Harvesting Plan shall illustrate water harvesting how will meet 50% of annual landscape water demand, as required by the ordinance. 13. Coordinate the Landscape Plan, Commercial Rainwater Harvesting Plan and the Civil Grading Plans to have identical basin size, grades/percent slopes, spot elevations and curb cut inlet and outlet locations. 14. Maximize rainwater harvesting across the site into all landscape areas, including the street landscape borders and planting islands for the required trees in the parking area. 15. A separate irrigation water meter is required. Please label irrigation meter as “irrigation only”. See TSM 4-01.6.0. Or see City of Tucson Ordinance 10597 -- Sec. 6-182. Rainwater Harvesting Plan: Number 3 (a) A separate water meter connected to the main water supply; or (b) An irrigation sub-meter. 16. **If it is determined that any of the above provided site landscape standards cannot be met due to the nature of the development, then a Design Development Option (DDO) may be an option to gain partial relief from some landscape requirements, see UDC 3.11.1.B.3 for landscape and screening modifications allowed. A Board of Adjustment Variance to the UDC site landscape requirements is also a viable alternative. Please reach out to Mark Castro or Georgia Pennington with PDSD for more information on the DDO and Variance process. Mark.Castro@tucsonaz.gov – Georgia.Pennington@tucsonaz.gov Thank you. CHAD KELLER - PLA LANDSCAPE ARCHITECT CITY OF TUCSON - PDSD CHAD.KELLER@TUCSONAZ.GOV 520.837.4923 |
|||
| Site Zoning * | REVIEW COMPLETED | CDRC Thursday Pre-Submittal Transmittal PDSD Zoning Review FROM: Krista Hansen, Lead Planner PROJECT: Pre-submittal meeting TP-PRE-0826-00161 Parcel: 11809046E Zoning: R-1 Existing Use: Single Family Residence Proposed Use: Middle Housing TRANSMITTAL DATE: 8/27/26 COMMENTS: 1. Any proposed development must comply with the City of Tucson Unified Development Code (UDC) Administrative Manual Chapter 2-06 – Development Package (DP). Building permits can be submitted and reviewed concurrently with the development package but the building plans cannot be approved until the development package is approved and the building plans are reviewed for consistency. 2. The history of the creation of this parcel cannot be clearly determined. Please provide proof indicating that the parcel was legally created through an application for land division through the City of Tucson. 3. The site is zoned R-1. The proposed use is Middle Housing, which is permitted, subject to UDC use specific standards 4.9.7.B.4-.6, .8, & .9. 4. Silverlake Rd is a Major Street and Route. All proposed development must meet the requirements in UDC 5.4. 5. Lots 3 and 4 are currently operating as one site due to shared access and parking. Eight units on one site is considered commercial multifamily. To maintain two residential lots, add a fence or vertical separation between the two parcels. 6. Dimensional Standards per UDC Table 6.3-2.A: a. Minimum density: 4 units per 6,000 sq ft b. Minimum lot size: 6,000 sq ft c. Maximum lot coverage: 70% d. Maximum height: 25 ft e. Front street setback (Santa Cruz Ln): 20 ft f. Side street setback (Silverlake Rd): 10 ft (UDC 6.4.5.C.1.b) g. Interior lot line setbacks: 5 ft 7. Ensure landscaping requirements are met in UDC 7.6.8. a. Min of 4 canopy trees required per lot (1 tree per 1,000 sq ft of Gross Floor Area) b. Vegetative groundcover is required within the front yard setback: (X Linear ft of Street Frontage) – (Y Curb cut width) x (5 ft Depth) = Z Sq ft of vegetative groundcover 8. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. For Site Zoning questions, please contact me at krista.hansen@tucsonaz.gov. |
|||
| TW New Area Development * | REVIEW COMPLETED | Based on the information provided, Tucson Water has no objections to the proposed development. The existing building currently has one existing domestic water meter size (5/8-inch). This service is connected to the 8-inch cement asbestos water main (A Zone) located within the east side of the parcel within the right-of-way of S Santa Cruz Ln. Please note that creating a separate lot will require a new water meter service. The new service can tie into the existing 8-inch cement asbestos water main (A Zone) located within the east side of the parcel within the right-of-way of S Santa Cruz Ln. Water pressure in this area is 50-57 PSI at an elevation of 2377ft. Water pressure can vary by an additional 5 psi +/-. If any new domestic water, irrigation water, or fire water services are needed to serve this proposed development, please contact Tucson Water’s New Services Section by calling 520-791-5164 or by sending an email to TW_Common@tucsonaz.gov. Please coordinate with the City of Tucson Department of Transportation and Mobility (DTM) to confirm the paving schedule and whether the proposed work will be subject to the City’s 5-year pavement cut moratorium. The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to Abdullah Salman (Project Manager) at Abdullah.Salman@tucsonaz.gov |