Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: TP-PRE-0625-00108
Parcel: 12901014C

Review Status: Approved

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - TP-PRE-0625-00108
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Fire New Construction REVIEW COMPLETED
ROW Engineering Review REVIEW COMPLETED DTM has no comments at this time.

If you have any questions, please contact Richard Leigh at 520-403-0970 or email richard.leigh@tucsonaz.gov.
Site Engineering REVIEW COMPLETED TP-PRE-0625-00108
2310 E BROADWAY BL

Site engineering comments are as follows:
1. Show on-site trash truck maneuverability compliant with TSM Sec 8. The maximum trach truck back up distance is 80 ft. The truck may not back into Broadway Blvd.
2. Show on-site Fire Apparatus maneuverability which complies with IFC Appendix D. The maximum depth / length of a dead end is 150 ft.
https://codes.iccsafe.org/content/IFC2021P1/appendix-d-fire-apparatus-access-roads
3. Provide a vertical barrier such as a curb preventing a vehicle from hitting the southern wall when backing into the back up spur. UDC Article 7.4.6.4
https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az_udc/0-0-0-5587
4. First flush retention and balanced basin detention compliant with sections 2 and 3 of the Design Standards for Stormwater Detention and Retention (DSSDR) manual are required for the proposed project. Provide a drainage report which states how these requirements will be met.
Ryan Insalaco – ryan.insalaco@tucsonaz.gov
Site Landscape REVIEW COMPLETED CDRC TRANSMITTAL
PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: THE PROJECT CONSISTS OF SITE IMPROVEMENTS TO ACCOMMODATE FOR NEW PARKING
ACTIVITY NO: TP-PRE-0625-00108
ADDRESS: 2310 E BROADWAY BL
ZONING: C-1 COMMERCIAL ZONE; UOD-3 SUNSHINE MILE (MID-CENTURY SUBDISTRICT)

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.

The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by the Site Landscape and NPPO section to ensure compliance with the applicable UDC development criteria and Technical Standards.

SUNSHINE MILE DISTRICT; MID-CENTURY SUBDISTRICT SITE LANDSCAPE COMMENTS:

1. Except as required by Subsection III.F, Development Transition Standards, a complete or partial exception to Section 7.6 of the UDC, Landscaping and Screening Standards, may be granted in order to encourage infill and redevelopment on constrained sites. If shade is provided for pedestrians and customers, such as along sidewalks, pedestrian circulation paths and outdoor patios (in accordance with Subsection III.J.1), and there are no adverse impacts on adjoining properties, an exception may be granted by the PDSD Director from the landscaping and screening requirements.

2. Upon submittal of the landscape plan development package, provide documentation and calculations explaining how all of the Sunshine Mile District requirements are being met. Examples: 40% open space and minimum landscape area; environmentally conscious design practices; 70% of the parking areas will be shaded; 50% shade requirement for all sidewalks and pedestrian paths. See the following link for the Sunshine Mile guidelines and requirments: https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/smd_document_final_9-14-21.pdf

ADDITIONAL SUNSHINE MILE COMMENTS:

3. Section J (page III-23) Open Space No. 7, Parking areas may not be counted as Open Space.

4. Sunshine Mile Overlay District states that Open Space for Non-Residential use is a minimum of 10% of the lot area. Of that Open Space, 60% of that area must be landscaped. (See page IV-19 of the Sunshine Mile Final Document).

5. Section E of the Sunshine Mile Overlay District, shade shall be provided for at least fifty (50) percent of all sidewalks and pedestrian paths as measured at 2:00 pm on June 21 when the sun is 82 degrees above the horizon. Shade may be provided by trees, arcades, canopies, or shade structures provided their location and design characteristics are compatible with the historic and design context of the street and the architectural integrity of the building. The use of plantings and shade structures in the City Right-Of-Way is permitted to meet this standard with the approval of DTM. See (page III-10).

SITE LANDSCAPE/NPPO COMMENTS:

1. A NPPO or a NPPO Waiver is required per UDC 7.7. SEE UDC 7.7.3. APPLICABILITY; UDC 7.7.4 NPPO GENERAL PROVISIONS AND STANDARDS; UDC 7.7.4.C. PLAN APPROVAL PRIOR TO PERMITTING; UDC 7.7.4.D. PROFESSIONAL EXPERTISE 7.7.5.C.5; ALSO SEE AM 2-11.3.0 PERMITTED EXCEPTIONS. PDSD will provide the applicant with the NPPO Waiver form upon request.

2. UDC 7.6.2. APPLICABILITY
The provisions of this section apply to the following:
A. All new development; and,
B. Expansion of existing development, as provided below:
**2. Buildings 10,000 Square Feet or Less
On sites where the gross floor area of the existing building (s) is 10,000 square feet or less, expansions in square footage of land area, floor area, lot coverage , or vehicular use area as follows.
a. If the expansion is less than 50%, the standards of this section apply only to the proposed expansion. Existing development on the site is subject to the zoning standards in effect at the time the existing development received zoning approval.
** b. If the expansion is 50% or greater or if expansions as of February 15, 1991, cumulatively result in a 50% or greater expansion in land area, floor area, lot coverage, or **vehicular use area, the standards of this section apply to the entire site. Preparation of the landscape plan shall adhere to UDC 7.6.4 and Administrative Manual 2-10.

3. A landscape plan is required per UDC 7.6.2.B.1-b. The Unified Development Code requires all new development, or an expansion of greater than 25% of an existing development to submit a landscape plan, UDC 7.6.2. Preparation of the landscape plan shall adhere to UDC 7.6.4 and Administrative Manual 2-10.

4. Provide the required number of trees in all vehicular parking areas (1 tree to 4 parking spaces) per UDC 7.6.4.B.1. Trees are to be distributed evenly throughout the parking area, UDC 7.6.4.1.B.1, UDC Technical Standards Manual 5-01-.3.2 and UDC 7.6.4.B.1.a.

5. A street landscape border is required along E Broadway Bl per UDC 7.6.4.C-2 and Table 7.6.4-1. See UDC 7.6.4.C for landscape border requirements. Commercial land use along MS&R and non-MS&R requires a 10’ street landscape border. If it is determined that this standard cannot be met due to the nature of the development, then a variance to the UDC site landscape requirements is a viable alternative. Please reach out to Mark Castro with PDSD for more information on the variance process. Mark.Castro@tucsonaz.gov

6. A drip irrigation plan and details are required for all proposed landscape planting areas.

7. DTM review is required for all planting and irrigation in the ROW prior to the approval of the development package. Reach out to David Marhefka (david.marhefka@tucsonaz.gov) if necessary for this project.

8. All landscape plans shall incorporate water conserving design as defined in UDC Section 7.6.6, Use of Water, and as described in the Technical Standards Manual 5.01-5.11.

9. A Commercial Rainwater Harvesting plan is required: See Technical Standards Manual 4-01.3.0 RAINWATER HARVESTING PLAN. A Rainwater Harvesting Plan shall be submitted with all applications for commercial developments at which landscaping is required.

10. Coordinate the Landscape Plan, Commercial Rainwater Harvesting Plan and the Civil Grading Plans to have identical basin size, grades, spot elevations and curb cut locations.

11. Maximize rainwater harvesting across the site into all landscape areas, including the street landscape borders and planting islands for the required trees in the parking area.

12. A separate irrigation water meter is required. Please label irrigation meter as “irrigation only”. See TSM 4-01.6.0

Thank you.
Chad Keller, RLA
Landscape Architect
chad.keller@tucsonaz.gov
520.837.4923
Site Zoning REVIEW COMPLETED CDRC TRANSMITTAL

TO:
Planning & Development Services Department

FROM: Fernando L. García
PDSD Zoning Review Section

PROJECT:
2310 E Broadway Bl, Tucson, AZ 85719
Parcel(s): 129-01-015A, 129-01-014C
Zoning: C-1; I-1
Pre-Submittal Conference (1st Review)
TP-PRE-0625-00108

TRANSMITTAL DATE: June 24, 2025

1. The proposed development must comply with the City of Tucson Unified Development Code (UDC) Administrative Manual Chapter 2-06 – Development Package. Building permits can be submitted and reviewed concurrently with the development package but the building plans cannot be approved until the development package is approved and the building plans are reviewed for consistency.

2. A lot combination of these two parcels will be required since they both serve as part of a single site.

3. If the parking spaces on the adjacent parcel to the west, 129-01-021B, could be accessed through the new parking area access lane (PAAL) on your site. If this is the case, then that parcel (regardless of ownership) would be considered one site with your own given the shared access to parking area/spaces. If so, the development package for this project will need to include that site.

In this case, since the parking lot expansion would constitute a greater-than-25% expansion on the combined site, the neighboring site would also need to come into compliance with current commercial development standards. To avoid this determination, demonstrate how the subject site is separate from the neighboring site. This can be accomplished by vertically curbing the PAAL, and/or placing a landscape screen, fence, or wall.

4. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, the Zoning Review Section will conduct a full review to assure compliance with applicable UDC development criteria and technical standards.

5. If you have any questions, please contact me at fernando.garcia2@tucsonaz.gov.
TW New Area Development REVIEW COMPLETED TP-PRE-0625-00108 - Pre-Application Conference Review v1 – 2310 E BROADWAY BL

Tucson Water has no objections to, or comments about the proposed development

The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to:


Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
201 N. Stone Avenue, #2-220
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov