Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Plan Number: TP-PRE-0523-00205
Parcel: 141020040

Address:
5001 S KOLB RD

Review Status: Approved

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - TP-PRE-0523-00205
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Entitlements REVIEW COMPLETED DATE: 5/30/2022
REVIEWED BY: Gabriel Sleighter, Planner
CASE NUMBER: TP-PRE-0523-00205, Tucson Water SCADA upgrades
PROJECT ADDRESSES: 5001 S Kolb Road
PARCEL NUMBERS: 141-02-0040
EXISTING ZONING: SR
EXISTING USE: Utilities Distribution
PROPOSED ZONING: SR
PROPOSED USE: SCADA Upgrades to Well Site

PROJECT DESCRIPTION & LOCATION:
The applicant has resubmitted a presubmittal request for special exception procedure supporting an equipment upgrade project at a City of Tucson Water wellsite. The development site is located within the larger parcel addressed 5001 S Kolb Rd, approximately 1650 feet east of Kolb Road, and 130 feet south of Irvington Road, currently used by DMAFB for airplane storage, an industrial land use per the UDC.

APPLICANT NAME: GARRETT ALDRETE, THE PLANNING CENTER
E-MAIL: galdrete@azplanningcenter.com

PLAN DIRECTION

ADOPTED PLAN (S): PLAN TUCSON, SOUTH PANTANO AREA PLAN

PLAN AMENDMENT REQUIRED BASED ON CONCEPT PRESENTED (SEE NOTES BELOW)

0 YES 1 NO 0 TO BE CONFIRMED LATER
NOTE: THE NORTHSIDE PLAN DOES NOT SUPPORT THE 3 STORIES ON THE NORTHERN PARCELS

PLAN SUPPORT BASED ON CONCEPT PRESENTED (SEE NOTES BELOW):

1 YES 0 NO 0 WILL DEPEND ON DESIGN







Applicable Plan Policies: Plan Tucson
Policy direction in Plan Tucson encourages the improvement of the appearance of above-ground utilities and structures and require development to support infill and redevelopment projects that reflect sensitivity to site and neighborhood conditions and adhere to relevant site and architectural design guidelines. Policies also call to prioritize, invest in, and maintain public infrastructure, including expanding the use of state-of-art, cost-effective technologies, and services for public infrastructure and facilities.

South Pantano Area Plan
The goals of the South Pantano Area Plan are to provide guidelines for proposed development, to protect existing development, and to create a sense of community within established neighborhoods. The South Pantano Area Plan contains no specific policies guiding utilities, however the Plan provides guidance for DMAFB.

Policies:
1. Ensure compatibility of new development with existing and future operations of Davis-Monthan Air Force Base.

Implementation Techniques

A. Rezoning requests should be reviewed on a case-by-case basis with regard to current and future base operations.
B. Request Davis-Monthan Air Force Base Community Planning staff to review proposed development plans for the South Pantano area.
C. Request a “fair disclosure statement” be part of any development plans, informational brochures, and sales/rental agreements, indicating that certain types of military air and ground training activities occur at Davis-Monthan.
D. When a study is prepared which demonstrated extensive noise level problems related to Davis-Monthan activities, policies similar to those adopted in the Tucson International Airport Environs Plan should be applied to the appropriate Davis-Monthan Air Force Base high-noise areas.
E. When Appropriate require developers to screen, buffer or orient developments, from Davis-Monthan Air Force Base properties.

2. Ensure compatibility of base operations with existing and potential adjacent development.

Implementation Techniques

A. Request Davis-Monthan Air Force Base Community Planning to review plans entailing future development, expansion or changes for compatibility with off-base development.

Surrounding Zoning and Land Uses: The subject parcel is zoned SR (Suburban Ranch), and the predominant land use is aircraft storage associated with the DMAFB Boneyard facility. The project site itself represents only a small portion east of Kolb Road and south of Irvington Road. The land use to the south is The Boneyard. Irvington Road runs west-to-east immediately north of the project site. Across Irvington Road to the north the zoning is R-2 (Residential) and the land use is single family homes. Both Irvington Road and Kolb Road are designated arterials by the City of Tucson Major Streets and Routes Plan. The development site is not within an Airport Environs Zone.

Analysis:
Per recent code updates effectuated by Mayor and Council in April 2023, a zoning special exception procedure is not a requirement for this project.

Per UDC 4.9.11.A:

12. The following requires approval in accordance with Section 3.3.4, 100’ Notice Procedure. The PDSD Director may forward the request to the Design Review Board (DRB) for design review and recommendation.

a. Water pumping and storage facility upgrades or expansions, provided:

(1) Existing setbacks are not altered.
(2) Use Specific Standards 4.9.11.A.5, .9, .11, are met.

Applicant should proceed with the 100’ Notice Procedure, staff is in support of this proposal.

Due to proximity to the DMAFB Boneyard, external review by Davis-Monthan Air Force Base Community Planning staff will be required as an external review for your building permit.

A plan amendment is not required.
Fire New Construction REVIEW COMPLETED No comments
john.vincent@tucsonaz.gov
5203495581
Site Engineering REVIEW COMPLETED Site Engineering has no comments on the preliminary plan.

Lianne Evans
lianne.evans@tucsonaz.gov
Site Landscape REVIEW COMPLETED PROJECT: SCADA UPGRADES WELL E-008A
ACTIVITY NO. TP-PRE-0523-00205
ADDRESS/PARCEL: 5001 S KOLB RD
ZONING: S-R

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants and water harvesting.
The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Landscape/NPPO to assure compliance with the applicable UDC development criteria and Technical Standards.

COMMENTS:
1. Landscape/NPPO has no concerns about this project in its current form.


If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988
Site Zoning REVIEW COMPLETED Special Exception Transmittal

FROM: Nicholas Martell
PDSD Zoning Review

PROJECT: Rezoning Pre-submittal meeting TP-PRE-0523-00205
Address: 5001 S KOLB RD TUCSON
Parcel(s): 141020040
Existing Zoning: SR
Existing Use: Utilities-Distribution System

TRANSMITTAL DATE: May 30, 2023

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 - Development Package.
2. Utilities-Distribution System is permitted through the zoning examiner special exception procedure.
a. The project may be eligible for an Administrative Special Exception Process per newly adopted code measures.
3. The following use-specific standards apply: 4.9.11.A. 1, .2, .5, .8, .9, .11
4. Parking requirements: See UDC Article 7.4.4 https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az_udc/0-0-0-5445
5. Bike parking is not required.
6. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions, please contact me at nicholas.martell@tucsonaz.gov.
Traffic Engineering Review REVIEW COMPLETED No Comments

David Stiffey

David.Stiffey@tucsonaz.gov