Review Status: Approved
Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1
Plan Number - TP-PRE-0425-00081
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| Fire New Construction | REVIEW COMPLETED | TP-PRE-0425-00081 • Pre-Application Conference Review v1 • 310 N COMMERCE PARK LP TUCSON, AZ 85745: Based on the information provided, TFD has no comments at this time. Questions: patricia.shelton@tucsonaz.gov / 520.837.7082 |
|||
| ROW Engineering Review | REVIEW COMPLETED | ||||
| Site Engineering | REVIEW COMPLETED | TP-PRE-0425-00081 310 N COMMERCE PARK LP Site engineering comments are as follows: 1. Maintain a 14ft wide by 40ft deep x 25ft vertical clearance in front of each dumpster. TSM 8-01.5.3.B Ryan Insalaco – ryan.insalaco@tucsonaz.gov |
|||
| Site Landscape | REVIEW COMPLETED | CDRC TRANSMITTAL PLANNING AND DEVELOPMENT SERVICES DEPARTMENT REVIEWER: CHAD KELLER, RLA SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION PROJECT: INSTALLATION OF PV SOLAR SHADE STRUCTURES TO PARKING LOT AT SANTA RITA SENTINEL ACTIVITY NO: TP-PRE-0425-00081 ADDRESS: 310 N COMMERCE PARK LP ZONING: PAD 4 (RIO NUEVO PAD) This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by the Site Landscape and NPPO section to ensure compliance with the applicable UDC development criteria and Technical Standards. SITE LANDSCAPE/NPPO COMMENTS: 1. Provide a NPPO or a NPPO waiver for the trees that will be removed due to the installation of the solar canopies. See UDC 7.7. SEE UDC 7.7.3. APPLICABILITY; UDC 7.7.4 NPPO GENERAL PROVISIONS AND STANDARDS; UDC 7.7.4.C. PLAN APPROVAL PRIOR TO PERMITTING; UDC 7.7.4.D. PROFESSIONAL EXPERTISE 7.7.5.C.5; ALSO SEE AM 2-11.3.0 PERMITTED EXCEPTIONS. PDSD will provide the applicant with the NPPO Waiver form upon request. 2. For all of the removed trees that are not protected natives shall be mitigated at a 1:1 ratio elsewhere on site for shade/heat island effect and the overall aesthetic of the site. 3. At the formal development package submittal provide a planting and irrigation plan that shows the new location of the mitigation trees from the NPPO, and other possible non-protected native trees replaced at the stated 1:1 ratio above. Include supplemental irrigation and applicable detailing. 4. RIO NUEVO PAD 4 - Appendix B - Recommended Landscape Plant Materials THIS PLANT LIST WAS ADOPTED AS A PART OF THE RIO NUEVO REDEVELOPMENT PLAN/ PLANNED AREA DEVELOPMENT. SINCE ADOPTION, A LOW-WATER USE/DROUGHT TOLERANT PLANT LIST MEETING THE SOUTHERN ARIZONA WATER RESOURCES ASSOCIATION AND THE ARIZONA DEPARTMENT OF WATER RESOURCES STANDARDS HAS BEEN APPROVED BY THE CITY OF TUCSON AND PIMA COUNTY. IT IS RECOMMENDED THAT THE LOW WATER USE/DROUGHT TOLERANT PLANT LIST BE REFERENCED FOR USE IN NEW DEVELOPMENT AND REVEGETATING EXISTING DEVELOPMENT PROJECTS. Thank you. Chad Keller, RLA Landscape Architect chad.keller@tucsonaz.gov 520.837.4923 |
|||
| Site Zoning | REVIEW COMPLETED | CDRC Thursday Pre-Submittal Transmittal FROM: Bobby Parsons, Planner PDSD Zoning Review PROJECT: Pre-submittal meeting TP-PRE-0425-00081 Address: 310 N Commerce Park Loop Tucson, AZ 85745 Zoning: PAD4 – Rio Nuevo PAD Existing Use: Parking Lot Proposed Use: Parking Lot Solar Array TRANSMITTAL DATE: May 8, 2025 COMMENTS: 1. Development must comply with the Administrative Manual Section 2-06, Development Package. 2. Per UDC 7.4.6.E.2, the minimum height clearance along access lanes and parking area access lanes (PAAL’s) is 15’. 3. Per UDC 7.4.6.F.2, setbacks from access lanes and PAAL’s must be at least 1’ from: 1. An open structure, such as a carport or covered pedestrian access path as measured from the closest part of the structure or roof overhang. 4. Ensure compliance with Table 7.4.4-1: Minimum Number of Motor Vehicle Spaces Required if any parking spaces are reduced with this project. 5. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. If you have any questions, please contact me at Robert.Parsons@tucsonaz.gov. |
|||
| TW New Area Development | REVIEW COMPLETED | TP-PRE-0425-00081 - Pre-Application Conference Review v1 – 310 N COMMERCE PARK LP Tucson Water has no objections to the proposed photovoltaic project. The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to: Tim Rowe, P.E., Civil Engineer Tucson Water, New Development Section 201 N. Stone Avenue, #2-220 P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 tim.rowe@tucsonaz.gov |