Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Approved
Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1
Plan Number - TP-PRE-0423-00167
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
Fire New Construction | REVIEW COMPLETED | Questions: patricia.shelton@tucsonaz.gov / 520.837.7082 | |||
Site Engineering | REVIEW COMPLETED | Project: TP-PRE-0423-00167 Address: 9550 E Golf Links Rd Comments: 1. Ensure ES maneuverability and design per TSM 8-01 2. From recent clarification from Environmental Services, per TSM section 8, although recycling service isn’t required the site needs to provide at minimum the enclosure space for both solid waste and recycling. So a single enclosure won’t be sufficient and a double enclosure or an additional single enclosure will be needed to meet this requirement. It is also important to point out per TSM section 8-01.4.I - required parking may be reduced for existing development when solid waste and recycle enclosures are provided. 3. Maximize Water Harvesting into any landscaping through the use of flush curbs, curb cuts, or scuppers Scott Haseman scott.haseman@tucsonaz.gov |
|||
Site Landscape | REVIEW COMPLETED | CDRC TRANSMITTAL PROJECT: Salad & Go ACTIVITY NO. TP-PRE -0423-00167 ADDRESS/PARCEL: 9550 E GOLF LINKS RD/ 136-12-833C ZONING: C-1 This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants and water harvesting. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Landscape/NPPO to assure compliance with the applicable UDC development criteria and Technical Standards. COMMENTS: 1. There must be a NPPO waiver. An NPPO is required per UDC 7.7.3-B. A Native Plant Preservation Plan, Section 7.7.4, is required to be submitted or approved or a request for an exception from the Native Plant Preservation requirements approved in accordance with Sections 7.7.3.D.3 & .4 of the UDC and Admin. Manual Section 2-11.0.0 prior to Grading Plan approval. 2. A landscape plan is required per 7.6.2.B.1-b. The Unified Development Code (UDC) requires all new development or an expansion of greater than 25% of an existing development to submit a landscape plan, UDC 7.6.2. Preparation of the landscape plan shall adhere to UDC 7.6.4 and Administrative Manual 2-10. 3. Ensure the required number of trees is in all vehicular parking areas (1 tree: 4 parking spaces) per UDC 7.6.4.B.1. Trees are to be distributed evenly throughout the parking area, UDC 7.6.4.1.B.1, UDC Technical Standards Manual 5-01-.3.2 and UDC 7.6.4.B.1.a. 4. There may need to be an updated street landscape border on E Golf Links Rd per UDC 7.6.4.C-2 and Table 7.6.4-1. See UDC 7.6.4.C for landscape border requirements. 5. See Engineering notes for Retention/Detention. 6. All landscape plans shall incorporate water conserving design as defined in UDC Section 7.6.6, Use of Water, and as described in the Technical Standards Manual 5.01-5.11. 7. The Landscape Plan should match the Commercial Rainwater Harvesting Plan as well as the Grading Plan. 8. Maximize the rainwater harvesting across the site into the landscape areas, including but not limited to the street landscape borders as well as the tree wells for the required trees for the parking lot. 9. There may need to be a Commercial Rainwater Harvesting plan is required per UDC Technical Standards Manual – Section 4-01.3.0. and Section 5-01.0.0 Landscaping and Screening. Adherence to the Low Impact Development Standards outlined in Section 5 of the PCRFCD Design Standards for Stormwater Detention and Retention is required and shall work in conjunction with the Commercial Rainwater Harvesting design. Using Low Impact Development design and water harvesting provides critical basin detention and first flush retention for all new development and impervious area. The newly adopted Detention/Retention Manual can be found: https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Flood%20Control/Rules%20and%20Procedures/Stormwater%20Detention-Retention/dssdr-final-201406-manual.pdf With CoT edits to the manual are found at: https://www.tucsonaz.gov/files/pdsd/codes/Detention_Retention_Manual_Tech_Standards_Amemdments.pdf If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988 |
|||
Site Zoning | REVIEW COMPLETED | CDRC Thursday Pre-Submittal Transmittal PDSD Zoning Review FROM: Georgia Pennington, Planner PROJECT: TP-PRE-0423-00167 Parcel(s): 136-12-833C Current Zoning: C-1 portion of property Existing Use: Parking Proposed Use: Salad and Go COMMENTS: 1. Development must comply with the Administrative Manual Section 2-06 – Development Package. The Development Package is a separate submittal from the building permits, and the building permits cannot be approved until the Development Package is approved. https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az_udc/0-0-0-8354 2. Include the entire parcel in your site plan when submitting your application. 3. The existing zone is C-1. Food Service is a permitted land use in the C-2 zone, subject to use-specific standards 4.9.4.M.1 and 4.9.13.P. 4. Maximum Height: 40 Feet 5. Setbacks: a. Front Street: 21’ or the height of the proposed exterior building wall as measured from the back of the existing curb or future curb location b. Side/Rear: 0’ 6. Parking for the existing development must maintain minimum requirements despite proposed development using a portion of the existing parking supply. 7. Motor Vehicle Space requirements: a. 1 space per 300 sq. ft. GFA (if no on-site dining) 8. Bicycle Parking Requirements: a. Short term: 1 space 2,000 SF GFA (min 2) b. Long term: 1 space per 12,000 SF GFA (min 2) 9. Electric Vehicle Charging Requirements: a. EV Installed (A designated parking space within 6 feet of an installed networked or non-networked charging station.): 5% EV Capable (A parking space within 6 feet of the termination (in a listed cabinet, box, or other enclosure) of a listed electrical conduit to accommodate a future individual branch circuit originating at the main service or subpanel. The service panel or subpanel circuit directory shall provide capacity to accommodate a 40-ampere minimum 208-volt or 240-volt dedicated branch circuit. The ampere and volt minimums described above can be modified with administrative approval to allow for advances in industry standards. The conduit shall be installed so that minimal removal of materials is necessary to complete a future installation.): 10% 10. Parking Area Access Lanes (PAAL) shall be 24 feet wide for 2-way traffic and fire access. 11. Comply with Section 7-01 Pedestrian Access in the Technical Standards Manual for new construction. 12. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards. If you have any questions, please contact me at Georgia.Pennington@tucsonaz.gov. |
|||
Traffic Engineering Review | REVIEW COMPLETED | TP-PRE-0423-00001 9550 E. Golf Links Rd. No Comments David Stiffey David.Stiffey@tucsonaz.gov |
|||
TW New Area Development | REVIEW COMPLETED | TP-PRE-0423-00167 - Pre-Application Conference Review v1 - 9550 E GOLF LINKS RD 1. Tucson Water has no objections to, or comments on, the proposed development. 2. The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to: Tim Rowe, P.E., Civil Engineer Tucson Water, New Development Section 201 N. Stone Avenue, #2-220 P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 tim.rowe@tucsonaz.gov |