Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: TP-PRE-0126-00004
Parcel: 13318007M

Review Status: Approved

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - TP-PRE-0126-00004
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Fire New Construction * REVIEW COMPLETED TP-PRE-0126-00004 • Pre-Application Conference Review v1 • 7000 E SPEEDWAY BL TUCSON, AZ 85710:
Based on the information provided, TFD has no comments at this time.
Questions: patricia.shelton@tucsonaz.gov / 520.837.7082
ROW Engineering Review * REVIEW COMPLETED DTM Review Comments for this property: 1) Driveway access from Green Hill Ave will require to be built out to meet PAG 206 Standards and be of full concrete construction to the back of sidewalk. 2) 20' easement to be built out and full pavement for extend of project width as will be used as dedicated Exit access point for project 3) North shared driveway access off Speedway Blvd will require a Shared Access agreement with Circle K 4) As noted by Zoning a Pedestrian circulation path connection property to Right of way along Speedway and Green Hill will be required. 5) Any damaged or Missing Sidewalk & Driveway panels along Green Hill and Speedway Blvd abutting property will require replacement. 6) Pedestrian access ramp at the corner of Green Hills Ave and Speedway Blvd with required placement of ADA compliant yellow detectable warning pad 7) Note any work performed within the City right of way will require a separate and individual ROW permit per scope of work 8) Traffic Impact study may be request at time of Development Package submission.

Zane.swenson@tucsonaz.gov
Site Engineering * REVIEW COMPLETED Permit Activity Number: TP-PRE-0126-00004
Project: New Valvoline Instant Oil Change Building
Location: 7000 E SPEEDWAY BL
Review Date: 2/19/2026
Reviewer: Dylan Molina - Engineering Associate - Site Engineering
Related Cases: TP-PRE-0725-00146

*This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-6 and Technical Standards Manual (TSM) Section for waste management, Pedestrian Access, Hydrology -Retention/Detention Requirements, and all site standard code.*
City of Tucson Code: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes
Drainage Manual Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/cot-drainage-manual-searchable.pdf
Design standards for Stormwater Detention and Retention Link:
https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf

Site Engineering Review Comments:
1. Prepare a development package (DP) submission with an updated site plan showing all existing site conditions and associated dimensions. AM 2-06.2
a. Show downspouts and scuppers on site plan. Must match DP and building permit. TSM 7-01.4.1.E
b. Pedestrian circulation is required to connect all buildings, dumpster areas, common areas, and the sidewalk on all the street frontages. Demonstrate how this is achieved for connecting to the trash enclosure as well as any other areas as determined by Site Zoning. TSM 7-01.3.3
c. Provide the Waste Stream Calculations for the site according to TSM 8-01.8.0.
d. Provide trash enclosure details. TSM 8-01.5.0 & TSM 8-01.9.0
e. Grading Plan to include cut and fill quantities and total area of disturbance. TSM 2-01.0.0
2. A drainage report with full compliance of first flush retention/balanced basin detention requirements. Refer to the DSSDR chapters 2, 3, & 4. Content and format requirements for the drainage report can be found in chapter 10 of the DSSDR.
3. Access requirements as they pertain to ES. One-Way 12’-4” drive may be too small and require a TSMR, “A minimum safe access and operational area of 14 feet by 40 feet” TSM 8-01.5.3.B Please contact Andy Vera, Andy.Vera@tucsonaz.gov, regarding technical standards modification request and submit his approval with DP application for TSMR.

This review is for Pre-Application purposes. Please be aware that additional comments may be forthcoming during submission process.

If you have any questions or concerns, please contact Dylan Molina, Dylan.Molina@tucsonaz.gov
Site Landscape * REVIEW COMPLETED PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: NEW VALVOLINE INSTANT OIL CHANGE BUILDING
ACTIVITY NO: TP-PRE-0126-00004
ADDRESS: 7000 E SPEEDWAY BL
ZONING: COMMERCIAL ZONE (C-2)
LAND USE: COMMERCIAL AUTO
02.17.2026

THE COMMENTS PROVIDED ARE PRELIMINARY AND ARE NOT TO BE ASSUMED AS A COMPLETE REVIEW OF THE PROPOSAL. DURING THE DEVELOPMENT PACKAGE REVIEW PROCESS, A FULL REVIEW WILL BE MADE BY THE SITE LANDSCAPE/NPPO REVIEW SECTION TO ENSURE COMPLIANCE WITH THE APPLICABLE CITY OF TUCSON UNIFIED DEVELOPMENT CODE, TECHNICAL STANDARDS MANUAL AND ADMINISTRATIVE MANUAL REQUIREMENTS FOR SITE LANDSCAPE, NATIVE PLANTS AND RAINWATER HARVESTING.

SITE LANDSCAPE/NPPO COMMENTS:

*PER PREVIOUS DISCUSSIONS, THESE COMMENTS PERTAIN ONLY TO THE VALVOLINE OIL SERVICE DEVELOPMENT ON ITS DESIGNATED PARCEL.

1. A Native Plant Preservation Plan (NPPP) or a NPPO waiver is required per UDC 7.7. See UDC 7.7.3. Applicability; UDC 7.7.4 NPPO General Provisions and Standards; UDC 7.7.4.c. Plan Approval Prior to Permitting; UDC 7.7.4.d. Professional Expertise 7.7.5.c.5; also see AM 2-11.3.0 Permitted Exceptions. If applicable, the Planning and Development Services Department will provide the applicant with the NPPO waiver form upon request.

COPY THE FOLLOWING LINK INTO YOUR INTERNET BROWSER FOR ACCESS TO THE NPPO WAIVER:

https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/applicationsforms/nppoapp-2025-v.2-fillable-1.pdf

2. See UDC 7.7.4.D. Professional Expertise: Preparation of all elements of the Native Plant Preservation Plan and on-site monitoring as required under Section 7.7.5.C.5, On- Site Monitoring, must be performed by a plant professional, such as: 1. An arborist certified by the International Society of Arboriculture; 2. A landscape architect; or, 3. A horticulturist, biologist, or botanist with a minimum B.A. or B.S. in an appropriate arid environment natural resource field.

3. UDC 7.6.2. APPLICABILITY
The provisions of this section apply to the following:
A. All new developments require a landscape plan set. Preparation of the landscape plans shall adhere to UDC 7.6 and Administrative Manual 2-10.

4. Parking lot canopy trees are required at 1 tree for every 4 parking spaces provided, see UDC 7.6.4.B. Structurally covered parking spaces do not count toward the ratio, see UDC 7.6.4.B.1.c.(8). Trees are to be distributed evenly throughout the parking area, see UDC 7.6.4.1.a.(1). See Technical Standards Manual 5-01.3.0 for additional landscaping in vehicular use area requirements.

5. A street landscape border is required along N Green Hills Av and along E Speedway Av, per UDC 7.6.4.C-2 and Table 7.6.4-1. See UDC 7.6.4.C. Commercial land use along MS&R and non-MS&R requires a 10’ street landscape border.

6. DTM review is required for all planting and irrigation in the ROW prior to the approval of the development package. Reach out to David Marhefka (david.marhefka@tucsonaz.gov) for review and approval if applicable for this project.

7. All landscape plans shall incorporate water conserving design as defined in UDC Section 7.6.6, Use of Water, and as described in the Technical Standards Manual 5.01-5.11.

8. A Commercial Rainwater Harvesting plan is required: See Technical Standards Manual 4-01.3.0 RAINWATER HARVESTING PLAN. A Rainwater Harvesting Plan shall be submitted with all applications for commercial developments at which landscaping is required. The Rainwater Harvesting Plan shall consist of two elements: a Site Water Budget and a Water Harvesting Implementation Plan. Preparation of the Rainwater Harvesting Plan elements requires coordination between project managers, site engineers and landscape architects from the inception of the project. The two elements of the Rainwater Harvesting Plan shall illustrate water harvesting how will meet 50% of annual landscape water demand, as required by the ordinance.

9. Coordinate the Landscape Plan, Commercial Rainwater Harvesting Plan and the Civil Grading Plans to have identical basin size, grades/percent slopes, spot elevations and curb cut inlet and outlet locations.

10. Maximize rainwater harvesting across the site into all landscape areas, including the street landscape borders and planting islands for the required trees in the parking area.

11. A separate irrigation water meter is required. Please label irrigation meter as “irrigation only”. See TSM 4-01.6.0. Or see City of Tucson Ordinance 10597 -- Sec. 6-182. Rainwater Harvesting Plan: Number 3 (a) A separate water meter connected to the main water supply; or (b) An irrigation sub-meter.

12. **If it is determined that any of the above provided site landscape standards cannot be met due to the nature of the development, then a Design Development Option (DDO) may be an option to gain partial relief from some landscape requirements, see UDC 3.11.1.B.3 for landscape and screening modifications allowed. A Board of Adjustment Variance to the UDC site landscape requirements is also a viable alternative. Please reach out to Mark Castro or Georgia Pennington with PDSD for more information on the DDO and Variance process. Mark.Castro@tucsonaz.gov – Georgia.Pennington@tucsonaz.gov

Thank you.
Chad Keller, RLA
Landscape Architect
chad.keller@tucsonaz.gov
520.837.4923
Site Zoning * REVIEW COMPLETED CDRC TRANSMITTAL

TO:
Planning & Development Services Department

FROM: Fernando L. García
PDSD Zoning Review Section

PROJECT:
7000 E Speedway Bl, Tucson, AZ 85710
Parcel: 133-18-007M
Current Zoning: C-2
Pre-Submittal Conference (1st Review)
TP-PRE-0126-00004

TRANSMITTAL DATE: February 18, 2026

1. 1. The proposed development must comply with the City of Tucson Unified Development Code (UDC) Administrative Manual Chapter 2-06 – Development Package. Building permits can be submitted and reviewed concurrently with the development package but the building plans cannot be approved until the development package is approved and the building plans are reviewed for consistency.

2. Automotive, Minor Service and Repair, is a permitted use in the C-2 subject to use-specific standards 4.9.13.E.

3. Dimensional standards for C-2 are below:

a. The maximum lot coverage is 70% for residential and N/A for nonresidential
b. The maximum height is 40’
c. The perimeter yards are as follows:
i. To the north, adjacent to E Speedway Bl: 20’
ii. To the east and south, adjacent to C-2 zoning: 0’
iii. To the west, adjacent to N Green Hills Av, a local street: 20’

4. Commercial services require a parking ratio of one motor vehicle space for every 300 square feet of gross floor area (GFA). For a GFA of 3,334 sf, 11 motor vehicle parking spaces are required.
a. A reduction of one may be permitted for every non-required EVSE space provided. The submitted site plan indicates an intent to pursue such a reduction.
b. Even with the EVSE reduction, additional reductions would be required. To submit an Individual Parking Plan (IPP) contact Mark Castro at mark.castro@tucsonaz.gov.

5. Per UDC Technical Standards Manual (TSM) 7-01.3.3, pedestrian circulation is required to connect all public areas of a development as well as to that only an adjacent streets. No pedestrian circulation path is shown to N Green Hills Av. or E Speedway Bl. A Technical Standards Modification Request (TSMR) would be required to request relief from this standard. Contact Stephen Blood at stephen.blood@tucsonaz.gov for a copy of the TSMR to submit.

6. Wheel stops may be necessary to prevent vehicles from encroaching into landscaping along the western property line.

7. Provide a copy, or recordation number, for the described easement along the southern property line at time of submission of the DP.

8. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package/Tentative Plat review process, the Site Zoning Review Section will conduct a full review to assure compliance with applicable UDC development criteria and technical standards.

9. If you have any questions, please contact me at fernando.garcia2@tucsonaz.gov.
TW New Area Development * REVIEW COMPLETED Based on the information provided, Tucson Water has no objections to the proposed development.
The building currently has one existing irrigation meter. The service is connected to a 10-inch cement asbestos water main (C Zone) located north of the parcel (E Speedway Bl). Water pressure in this area is 64-71 PSI at an elevation of 2538 ft. Water pressure can vary by an additional 5 psi +/-.
If any new domestic water, irrigation water, or fire water services are needed to serve this proposed development, please contact Tucson Water’s New Services Section by calling 520-791-5164 or by sending an email to TW_Common@tucsonaz.gov.
The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to Kathryn Gerber (Engineering Manager) at Kathryn.Gerber@tucsonaz.gov.