Review Status: Approved

Review Details: PRE-APPLICATION CONFERENCE REVIEW v.1

Plan Number - TP-PRE-0125-00001
Review Name: PRE-APPLICATION CONFERENCE REVIEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
Fire New Construction REVIEW COMPLETED TP-PRE-0125-00001 • Pre-Application Conference Review v1 • 3135 W NEW STAR PL TUCSON, AZ 85745:
Based on the information provided, TFD has no comments at this time.
Questions: patricia.shelton@tucsonaz.gov / 520.837.7082
ROW Engineering Review REVIEW COMPLETED TP-PRE-0125-00001 • 3135 W NEW STAR PL

1. The proposed curb, sidewalk and sidewalk scuppers along Anklam Rd will have to be constructed under a Private Improvement Agreement (PIA). For additional information on PIAs please visit https://www.tucsonaz.gov/tdot/private-improvement-agreement or contact Jesus Villezcas (jesus.Villezacas@Tucsonaz.gov) or at 520-791-5100.

If you have any questions, please contact Richard Leigh at richard.leigh@tucsonaz.gov.
Site Engineering REVIEW COMPLETED TP-PRE-0125-00001
3135 W NEW STAR PL

1. Please submit a tentative plat for the entire subdivision. A separate DP will be required for each phase of the project.
2. Permission from the HOA is required to use Daystar Mtn Dr. for access.


Chris Arrington
chris.arrington@tucsonaz.gov
Site Landscape REVIEW COMPLETED CDRC TRANSMITTAL
PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: PRE-APPLICATION CONFERENCE TO DISCUSS THE RE-SUBMITTAL OF ANKLAM PEAKS SUBDIVISION, INCLUDING THE POTENTIAL OF PHASING THE PROJECT
ACTIVITY NO: TP-PRE-0125-00001
ADDRESS: 3135 W NEW STAR PL
ZONING: RX-2 RESIDENCE ZONE

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.

The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the Development Package review process, a full review will be made by Landscape/NPPO to ensure compliance with the applicable UDC development criteria and Technical Standards.

SITE LANDSCAPE/NPPO COMMENTS:

1. All applicable Site Landscape, NPPO, HDZ, SCZ requirements were previously submitted and approved as part of the S06-253 Development Package. If it is established that new Development Packages are required for the separate phases and overall tentative plat moving forward, them a re-package of the drawings will need to be submitted.

If you have any questions about these comments, I can be reached at chad.keller@tucsonaz.gov
Site Zoning REVIEW COMPLETED CDRC Thursday Pre-Submittal Transmittal
PDSD Zoning Review
FROM: Georgia Pennington, Lead Planner
Parcel(s): 116-09-4410
Current Zoning: RX-2
Existing Use: Vacant
Proposed Use: Flexible Lot Development- Detached residential

COMMENTS:
1. Development must comply with the Administrative Manual Section 2-06 – Development Package. The Development Package is a separate submittal from the building permits, and the building permits cannot be approved until the Development Package is approved.
2. The existing zone is RX-2. A Flexible Lot Development is a permitted use in the RX-2 zone, subject to use-specific standard 8.7.3.(4.8.-4)
3. Maximum Height: 25 Feet (Table 8.7.3-1)
4. Maximum Density: 2.25 Dwelling Units/Acre (Table 8.7.3-1)
5. Site Coverage: 33% (Table 8.7.3-1)
6. Minimum lot size: 12,000 SQFT
7. Setbacks:
a. Interior Front/Side Street within proposed development: 5’ (6.4.5.C.1.d)
b. Side/Rear along interior lot lines: The perimeter yard requirements of Section 6.3.4, Dimensional Standards and Exceptions Tables, may be reduced for setbacks along interior lot lines to the extent permitted by the City’s adopted Building Codes. (Table 6.3-4.A)
8. A buffer area 30 feet wide, to the MS&R , is required and shall be preserved and maintained in its natural state.
9. Motor Vehicle Space requirements: 2 spaces per dwelling plus visitor parking required at a ratio of 0.25 space per unit. (7.4.4)

10.A neighborhood meeting is required per 8.7.3.P.1.b.

11. The comments provided are preliminary and are not to be assumed as a complete review of the proposal. During the review process, a full review will be made by Zoning to assure compliance with the applicable UDC development criteria and Technical Standards.

If you have any questions, please contact me at Georgia.Pennington@tucsonaz.gov
TW New Area Development REVIEW COMPLETED TP-PRE-0125-00001 - Pre-Application Conference Review v1 – 3135 W NEW STAR PL

Tucson Water has following comments regarding this proposed development and offers the following comments for your convenience:

1. The previously water master plan (DP1514) and water design (construction) plan (TW PN 067-2017) that were approved in 2017 for the Anklam Peaks, Lots 1-28 subdivision have expired. The owner/developer of this project will need the water master plan and the water design (construction) plan for this subdivision re-accepted by Tucson Water’s New Area Development Division. Please note that new standards for acceptance have been implemented since 2017, and these plans may require substantial changes.

2. If the construction of the water mains to serve this project is going to be phased, an Overall (Phased) Master Water Plan must first be submitted to Tucson Water for review and acceptance.

3. After the Overall (Phased)) Master Water Plan has been accepted by Tucson Water, a single-phase master water plan and a water construction (design) plan for the 1st construction phase will need be submitted to Tucson Water for review and acceptance. As each construction phase will be small, the single-phase master water plan and water construction (design) plan may be submitted together for a concurrent review in a Water At-Risk Plan Review.

4. After the single-phase master water plan for the 1st construction phase has been accepted by Tucson Water, the single-phase master water plan and a water construction (design) plan for the next construction phase may then be submitted as a Water At-Risk Plan Review.

5. This process repeated until such time that a single-phase master water plan and a water construction (design) plan have been accepted by Tucson Water.

6. The construction of the new water mains in the 1st construction phase may not begin until after all of the following have occurred:
a) Tucson Water’s acceptance of the Overall Master Water Plan.
b) Tucson Water’s acceptance of the single-phase master water plan and the water construction (design) plan for the new water mains in the 1st construction phase.
c) The owner/developer has entered into a Construction Agreement with Tucson for the new water mains in the 1st construction phase.
d) An ADEQ Construction Authorization (aka Approval To Construct) has been obtained from Pima County Development Services for the new water mains in the 1st construction phase.
e) A Pre-Construction Meeting has been held with Tucson Water’s Construction Section, and
f) Tucson Water’s Construction Section has issued a Notice to Proceed for for the new water mains in the 1st construction phase.
The above comments are based on the limited preliminary information provided by the applicant and should not be construed as a complete review of the proposal. Any questions, comments or concerns about these comments may be directed to:


Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
201 N. Stone Avenue, #2-220
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106