Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Requires Resubmit
Review Details: LAND DIVISION/LOT SPLIT v.1
Plan Number - TD-DIV-1025-00095
Review Name: LAND DIVISION/LOT SPLIT v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| Record Documents Express | PENDING ASSIGNMENT | ||||
| Commercial Plumbing Fast | REQUIRES RESUBMIT | 1. For the purposes of having a water meter, a parcel is required to have a minimum width of 15-feet of frontage on a water main. An easement is not considered to be frontage. Reference: Tucson Water Remote Meter Policy, Number IV-B.08, dated 07/14/2009. 2. Each occupiable building that abuts a public street that includes a public sewer shall have an independent connection to the public sewer. Show how access to the public sewer will be provided for parcel A. Reference: Section 701.3, IPC 2018. |
|||
| Residential Engineering Fast | REQUIRES RESUBMIT | Permit: TD-DIV-1025-00095 Location: 2226 S SAN JOSE DR Review Date: 11/3/2025 Site Engineering Comments: 1. The proposed land split exceeds the number of allowed splits for a property whose boundaries are fixed by a recorded plat which is divided into two or more parts, see UDC Article 11.4.20 definition of a Subdivision. The streets the boundary of the subdivision are also not fully developed/improved (UDC 8.4.3.B.4) as well as the subdivision being designated and subject to Hillside Development standards (UDC 8.4.3.B.8) Therefore this is not able to be processed as a minor subdivision. 2. This will be required to follow the tentative and final plat process UDC 8.4.4 & 8.4.5 Due to the referenced criteria above. If you have any questions or concerns, please contact Marco Contreras Marco.contreras@tucsonaz.gov |
|||
| Residential Zoning Fast | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TD-DIV-1025-00095 2226 S SAN JOSE DR. – R-1 Land Split (1st Review) TRANSMITTAL DATE: November 3, 2025 DUE DATE: October 31, 2025 SECTION 2-08.0.0: LAND SPLIT 2-08.2.0 CONTENT REQUIREMENTS 1. COMMENT: 2-08.2.0 – Based on the existing legal description of this parcel “HIRAM BANKS ACRES S75' E150.7' LOT 14 & S150' W200' LOT 14” the original parcel was created via a platting process. The proposed land split exceeds the number of allowed splits for a property whose boundaries are fixed by a recorded plat which is divided into two or more parts, see UDC Article 11.4.20 definition of a Subdivision, C. A minor subdivision meeting AM 2-07 is required to be submitted and approved. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
|||
| TW New Development Review Fast | REQUIRES RESUBMIT | Per Tucson Water Remote Meter Policy No. IV-B.08 (07/14/2009), each parcel must have ≥15 ft of frontage on a public water main to qualify for a water meter; easements do not constitute frontage. Under the proposed lot split, Parcel A has sufficient frontage and can be served from the existing 8" CA water main, PN-045-1963. The other three parcels lack the required 15 ft frontage on a main; therefore water service/meters cannot be approved as configured. | |||
| CDRC Application Completeness Express | REVIEW COMPLETED | ||||
| Commercial Building Fast | REVIEW COMPLETED | ||||
| Residential Building Fast | REVIEW COMPLETED |