Permit Review Detail
Review Status: Approved
Review Details: DEVELOPMENT PACKAGE NEW v.3
Permit Number - TD-DEV-1223-00491
Review Name: DEVELOPMENT PACKAGE NEW v.3
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/11/2024 | Commercial Plumbing | APPROVED | |||
| 01/16/2024 | External Reviewers - Tucson Electric Power (TEP) | APPROVED | January 16, 2024 WO#T101046 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: CITY PROJECT, WATER SITE, GRADING ONLY TD-DEV-1223-00491 Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted 1/4/2024. There are facilities within the development which are depicted upon the plan; there is a potential conflict with existing TEP facilities near the northwest corner of the property as depicted upon the attached faciliites map. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918-8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Your final plans should be sent to: GABRIELA BIELECKA Tucson Electric Power Company New Business Residential Project Manager P. O. Box 711 (OH 204) Tucson, AZ 85703 (520) 651-3833 Should you have any technical questions, please contact the area designer, CRUZ VEGA at (520) 349-9850. Sincerely, Design Admins Design Admins Tucson Electric Power | ||
| 01/05/2024 | NPPO | APPROVED | |||
| 01/09/2024 | ROW Engineering Review | APPROVED | |||
| 01/11/2024 | Site Engineering | APPROVED | |||
| 01/04/2024 | Site Zoning | APPROVED | |||
| 01/02/2024 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 01/17/2024 | CDRC Post Review Express | REVIEW COMPLETED | |||
| 01/03/2024 | CDRC Review Coordinator Express | REVIEW COMPLETED | Review request email sent per TEP, FYI email sent to PAG, USPS, SWG. | ||
| 01/03/2024 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 01/03/2024 | External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 01/03/2024 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 01/04/2024 | Fire New Construction | REVIEW COMPLETED | |||
| 01/03/2024 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 01/03/2024 | OK to Submit - Zoning Fast | REVIEW COMPLETED |