Permit Review Detail
Review Status: Approved
Review Details: DEVELOPMENT PACKAGE NEW v.2
Permit Number - TD-DEV-1223-00488
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/31/2024 | Commercial Plumbing | APPROVED | |||
| 01/25/2024 | NPPO | APPROVED | |||
| 01/31/2024 | Site Engineering | APPROVED | |||
| 01/25/2024 | Site Landscape | APPROVED | |||
| 01/22/2024 | Site Zoning | APPROVED | |||
| 01/22/2024 | Fire New Construction | NOT REQUIRED | |||
| 01/19/2024 | OK to Submit - Zoning Fast | NOT REQUIRED | |||
| 01/19/2024 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 02/07/2024 | CDRC Post Review Express | REVIEW COMPLETED | |||
| 01/19/2024 | CDRC Review Coordinator Express | REVIEW COMPLETED | Per SOP, TEP review required. Review request email sent to TEP. CDRC sent FYI email to PAG, USPS, SWG. | ||
| 01/19/2024 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 01/19/2024 | External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 02/05/2024 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | February 5, 2024 WO#T103527 City of Tucson Planning and Development Services Attn: CDRC Adming Team Dear CDRC Adming Team Subject: TUCSON WATER PROJECT EQUIP WELL C-117B TD-DEV-1223-00488 Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted 1/19/2024. There are existing faciliites within the development which are depicted upon the plan; however, there are no apparent conflicts at this time. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918-8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Should you have any easement questions, please contact our land Resources Department at TEPDEVREV@tep.com. Should you have any technical questions, please contact the area designer, CASSIE PETTITT at (520) 330-2430. Sincerely, Design Admins Design Admins Tucson Electric Power | ||
| 01/19/2024 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 01/25/2024 | ROW Engineering Review | REVIEW COMPLETED | No Comments Not City ROW David Stiffey David.Stiffey@tucsonaz.gov |