Permit Number: TD-DEV-1123-00448
Parcel: 131092290

Review Status: Approved

Review Details: DEVELOPMENT PACKAGE NEW REVISION v.1

Permit Number - TD-DEV-1123-00448
Review Name: DEVELOPMENT PACKAGE NEW REVISION v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
06/10/2025 Commercial Plumbing Standard APPROVED
06/17/2025 Site Engineering Standard APPROVED
06/13/2025 Site Landscape Standard APPROVED
06/16/2025 Site Zoning Standard APPROVED
05/13/2025 CDRC Application Completeness Express REVIEW COMPLETED
05/20/2025 CDRC Review Coordinator Express REVIEW COMPLETED CDRC added TEP to workflow and sent out review email.
07/10/2025 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED July 8, 2025
WO#T151570
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Enterprise - Craycroft
TD-DEV-1123-00448
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 5/20/2025. There are existing facilities within the development which are
depicted upon the plan. No apparent conlicts.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
Martin Salazar
(520) 305-6713
msalazar@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
05/19/2025 OK to Submit - Engineering Fast REVIEW COMPLETED
05/15/2025 OK to Submit - Zoning Fast REVIEW COMPLETED