Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.1
Permit Number - TD-DEV-1122-00057
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/21/2023 | Site Landscape | APPROVED | |||
07/24/2023 | CDRC Post Review | PENDING ASSIGNMENT | |||
07/24/2023 | Commercial Plumbing | REQUIRES RESUBMIT | Comment not resolved. The current submittal of the utility plan (25 of 48), shows two 6” sections of the building sewer with 100 LF and 119 LF between cleanouts. [Initial comment: The maximum distance between cleanouts shall be 100-feet, measured along the developed pipe length from the upstream entrance of the cleanout. For example, a section of the building sewer downstream of a cleanout with a rim elevation of 3004.27’ and a 2999.84’ invert can have a maximum horizontal length of 95.57’. Reference: Section 708.1.1, IPC 2018.] | ||
07/21/2023 | Site Engineering | REQUIRES RESUBMIT | TD-DIV-1122-00011 will need to be reviewed and approved before this development package can be approved. Lianne Evans lianne.evans@tucsonaz.gov |
||
06/26/2023 | Site Zoning | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: Home Depot @ Houghton Town Center Development Package (2nd Review) TD-DEV-1122-00057 TRANSMITTAL DATE: June 26, 2023 DUE DATE: July 15, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is February 13, 2024. 2-06.4.7 - General Notes The following general notes are required. Additional notes specific to each plan are required where applicable. 2-06.4.7.A - Zoning and Land Use Notes 1. This comment was not addressed. COMMENT: 2-06.4.7.A.7 – As it appears that some type of final plat will be needed this plat must be approved prior to approval of this DP. 2-06.4.7.A.8 - For development package documents provide: 2. Zoning was not able to find the table on the “notes sheet”. Zoning acknowledges that the PAD reference was not correct and should be PAD-36 Section 3.C.1. COMMENT: 2-06.4.7.A.8.d – Provide the required Zoning Documentation Table on the plan, see PAD-36 Section C.1. 2-06.4.9 - Information on Proposed Development The following information on the proposed project shall be shown on the drawing or added as notes. 3. This comment was not fully addressed and there are still easements that do not show the recordation information. COMMENT: 2-06.4.9.B – Provide the recordation information for all proposed easements on the plan. 4. Zoning acknowledges your response to this comment. Provide a copy of the CC&Rs with the next submittal. COMMENT: 2-06.4.9.B – As access is proposed across the property to the east provide a copy of the required access agreement/easement with the next submittal. 5. Per UDC Article 1.7.4.A.1 Any complete application that has been submitted for approval, but upon which no final action has been taken by the appropriate decision-making body prior to the effective date of this UDC, shall be reviewed in accordance with an ordinance in effect on the date the application was deemed complete. That said, this application was deemed complete on 12/23/2022 and the Electric Vehicle (EV) requirements became effective 12/01/2022 therefore this comment applies. COMMENT: 2-06.4.9.H.5.a – The vehicle parking calculation on sheet 3 does not match what is shown on sheet 1, clarify which is correct and either correct so that they match or remove one of the calculations. 6. COMMENT: 2-06.4.9.H.5.a – Demonstrate on the plan how the requirements of UDC Article 7.4.11 & 7.4.12 are met. 7. COMMENT: 2-06.4.9.H.5.d – For the new short-term bicycle location shown near the southwest corner of the building demonstrate how the requirements of UDC Article 7.4.9.B.1.g are met. 8. This comment was not fully addressed. A sidewalk is required and shall meet the requirements of 7-01.4.3. COMMENT: 2-06.4.9.R – Demonstrate that the requirements of TSM Section 7-01.4.1.C along the east and west side of the proposed building. If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
||
06/08/2023 | CDRC Application Completeness | REVIEW COMPLETED |