Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: TD-DEV-1122-00011
Parcel: 113100040

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE REVIEW v.2

Permit Number - TD-DEV-1122-00011
Review Name: DEVELOPMENT PACKAGE REVIEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
02/08/2023 Commercial Plumbing APPROVED
01/23/2023 NPPO NOT REQUIRED
02/13/2023 CDRC Post Review Express PENDING ASSIGNMENT
01/27/2023 Site Engineering REQUIRES RESUBMIT Tucson codes and ordinances can be found online at https://codelibrary.amlegal.com/codes/tucson/latest/overview

1. Dumpster enclosure should comply with standards outlined in TSM 8-01.5.2. Please include this standard in your dumpster enclosure callout or provide a detail showing that the enclosure meets this standard.
2. A sidewalk is required along N. Campbell Ave.
3. Underground Retention: As per the updated Detention/Retention manual, underground retention requires city engineer approval based on the following comments:
a. As per the updated Detention/Retention manual 4.13.1.4, show how 150% of the required 100-yr detention volume is provided in the site drainage improvements
b. Show how necessary first flush volume is retained and infiltrated into the surrounding soils and that the soil beneath the chamber will infiltrate in a reasonable amount of time through a geotechnical report (now), or an infiltration test completed (prior to final inspection)
c. Ensure landscaping comments regarding rainwater harvesting are addressed. Water harvesting must be maximized. Onsite flow should be primarily directed towards landscaping through the use of grading and curb cuts/scuppers
d. Include a note in the plan set requiring a maintenance schedule and process that follows the manufacturer's process in the drainage report. Ensure this includes a plan for cleaning the outlet into the drainage channel
e. As per the Detention/Retention Manual 4.13.1.5, include an inspection and maintenance port into each chamber
f. As per the detention/retention manual 4.13.1.7, process a covenant agreement for this project, a sample can be found at:
https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Flood%20Control/Rules%20and%20Procedures/Stormwater%20Detention-Retention/dssdr-final-201406-appendix-g.pdf
g. Apply for city engineering approval by emailing Stephen Blood stephen.blood@tucsonaz.gov and Loren Makus loren.makus@tucsonaz.gov. Please provide proof of addressing the comments 6a-6f in that email

Lianne Evans
lianne.evans@tucsonaz.gov
01/23/2023 Site Landscape REQUIRES RESUBMIT CDRC TRANSMITTAL
TO: Planning and Development Services Department, Plans Coordination
FROM: Anne Warner, RLA
PDSD Landscape/Native Plant Preservation Section

PROJECT: Chop Shop
ACTIVITY NO: TD-DEV-1122-00011 v2
Address: 2749 N CAMPBELL AV
Zoning: C-1
Existing Use: Retail
Proposed Use: Food Service

TRANSMITTAL DATE: January 23, 2023
DUE DATE: February 17, 2023
COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Landscape Review Section comments were addressed.
This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants and water harvesting.
General Note - UDC 2-10.4.1 Identification and Descriptive Data - All improvements and site information, such as adjacent rights-of-way and property lines, shown on the landscape plan will be identical in size and location to those shown on the base plan (site plan or tentative plat). Should amendments be required to the base plan through the review process, the same amendments will be made to the landscape plan which will then be resubmitted along with the base plan.
1. This comment was not adequately addressed - Engineer Comment - A Commercial Rainwater Harvesting plan is required that directs first flush to landscape area. An underground storage system for stormwater is not allowed until water harvesting is maximized and approved by City Engineers. UDC Technical Standards Manual – Section 4-01.0.0. and Section 5-01.0.0 Landscaping and Screening. Demonstrate how water harvesting is being maximized.
RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
YOUR NEXT STEPS: Submit documents to the Filedrop
https://docs.tucsonaz.gov/Forms/tucsonpermitapp
Select "Existing Application"
1) Comment Response Letter (your response to
the reviewer's Requires changes comments)
2) Plan Set (or individual sheets)
3) Any other items requested by review staff

If you have any questions, please contact me at anne.warner@tucsonaz.gov
02/13/2023 Site Zoning REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Orginal Chopshop
Development Package (1st Review)
TD-DEV-1122-00011

TRANSMITTAL DATE: February 13, 2023

DUE DATE: February 17, 2023

COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is November 10, 2024.

CONTENT REQUIREMENTS

1. COMMENT: 2-06.4.3 – Provide the development package case number, TD-DEV-1122-00011, adjacent to the title block on all sheets. The case number was not provided on sheets 9-15.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

2. COMMENT: 2-06.4.7.A.6.a - As Campbell Ave. is designated as an Arterial Gateway on the COT MS&R Map provide a general note on the cover sheet stating “THIS PROJECT IS DESIGNED TO MEET THE OVERLAY ZONE(S) CRITERIA, UDC ARTICLE 5.4 MAJOR STREETS AND ROUTES SETBACK ZONE (MS&R) & UDC ARTICLE 5.5 GATEWAY CORRIFOR ZONE (GCR)”

2-06.4.7.A.8 - For development package documents provide:

3. COMMENT: 2-06.4.7.A.8.a – There appears to be a discrepancy in the floor area provided under General Note 4, under the vehicle parking space calculation and what is shown within the footprint of the building. Clarify what the correct square footage is.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

4. COMMENT: 2-06.4.9.H.2 – As Campbell Ave. is designated as an Arterial Gateway on the COT MS&R Map with a 120’ future right-of-way and currently is not a full width show the future right-of-way, future curb & sidewalk and future SVT’s on the plan.

5. COMMENT: 2-06.4.9.H.5 – Show the required 1’-0” setback from the drive-thru access lane to the building, see UDC Article 7.4.6.F.2.a.(2).

6. COMMENT: 2-06.4.9.H.5.a – The wheel stop location dimension shown on detail A sheet 5 is not correct. Review UDC Article 7.4.6.H.3 and show the correct dimension.

7. COMMENT: 2-06.4.9.H.5.a – It appears that the proposed location of the accessible sign encroaches on the 2’-6” vehicle overhang, clearly demonstrate that the sign does not reduce the 2’-6” overhang.

8. COMMENT: 2-06.4.9.H.5.d – The bicycle parking space calculation is not correct. Per UDC Table 7.4.8-1: Minimum Required Bicycle Parking Spaces, COMMERCIAL USE GROUP, Food Service, the required short-term is 1 space per 2,000 sq. ft., minimum requirement is 2 spaces, and long-term is 1 space per 12,000 sq. ft., minimum requirement is 2 spaces.

9. COMMENT: 2-06.4.9.H.5.d – Show the required long-term bicycle parking on the plan and provide a detail.

10. COMMENT: 2-06.4.9.H.5.d – Demonstrate on the plan or details how the requirement of :UDC Article 7.4.9.B.1.e is met for both the short- & long-term bicycle parking.

11. COMMENT: 2-06.4.9.W - Indicate the locations and types of proposed signs (wall, free-standing, pedestal) to assure there are no conflicts with other requirements and that minimal locational requirements can be met. Also provide a note on the plan stating that all signs require separate permits.

If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
01/18/2023 CDRC Application Completeness Express REVIEW COMPLETED
01/20/2023 Fire New Construction REVIEW COMPLETED
01/19/2023 OK to Submit - Engineering Fast REVIEW COMPLETED