Permit Number: TD-DEV-1025-00258
Parcel: 114512110

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.3

Permit Number - TD-DEV-1025-00258
Review Name: DEVELOPMENT PACKAGE NEW v.3
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
01/09/2026 Traffic Engineering Review Standard APPROVED Traffic Engineering has no additional comments on this project.
01/20/2026 Site Engineering Standard REQUIRES RESUBMIT Permit: TD-DEV-1025-00258
Location: 9015 E TANQUE VERDE RD
Review Date: 1/20/2026

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-6 and Technical Manual (TM) Section for waste management, Pedestrian Access, Hydrology -Retention/Detention Requirements, and all site standard code.

Site Engineering Comments:
1. As the TSMR request for relief from connecting to Catalina HWY frontage sidewalk has been denied. It will remain required that a pedestrian pathway connection be provided to connect the entire site to Catalina HWY sidewalk per TSM 7-01.3.3.

If you have any questions or concerns, please contact
Marco Contreras
Marco.contreras@tucsonaz.gov
02/02/2026 Site Landscape Standard REQUIRES RESUBMIT PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: EXISTING BANK BUILDING / REBUILD TO A CIRCLE K C-STORE, FUELING CANOPY, PARKING, GRADING, AND UTILITY IMPROVEMENTS
ACTIVITY NO: TD-DEV-1025-00258
ADDRESS: 9015 E TANQUE VERDE RD
ZONING: C-1 COMMERCIAL ZONE
LAND USE: COMMERCIAL CONVENIENCE STORE
REVIEW #2
02.02.2026

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.

Please resubmit revised drawings along with a detailed response letter, which states how all of the Site Landscape and NPPO Section review comments have been addressed.

SITE LANDSCAPE/NPPO SECTION COMMENTS:

1. Site Engineering has denied the TSMR. Ensure that all design linework required by this denial is included on all sheets in the development package set with the resubmittal.

Thank you.
Chad Keller, RLA
Landscape Architect
chad.keller@tucsonaz.gov
520.837.4923
02/04/2026 Site Zoning Standard REQUIRES RESUBMIT CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Loran Shamis
PDSD Zoning Review Section

PROJECT: New Circle K
Development Package (2nd Review)
TD-DEV-1025-00258 - 9015 E TANQUE VERDE RD

TRANSMITTAL DATE: February 4, 2026
DUE DATE: January 29, 2026

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is October 21, 2025.

SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)

1. COMMENT: 2-06.4.9.R – As the TSMR to waive this requirement was denied, this comment has not been fully addressed. Provide a pedestrian circulation path to the fueling stations and to E Catalina Hwy that meets the requirements of TSM 7-01.

***For additional information on the any standard presented in this memo, please refer to the City of Tucson “Unified Development Code” – Administrative Manual Section 2-06 or Technical Standards noted in the comments. https://www.tucsonaz.gov/pdsd/all-codes-plans-determinations


If you have any questions about this transmittal, Contact Loran Shamis by email Loran.Shamis@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package and comment response letter. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home.
Instructions for resubmittal - https://www.tucsonaz.gov/files/pdsd/website/Resubmittals.pdf
01/15/2026 TSMR/PDMR - Engineering REQUIRES RESUBMIT 1. TSMR is not approved, sidewalk along Catalina Hwy is being required by right-of-way and pedestrians will cross the site regardless of having a circulation path across the site, but it will be safer with a path for them.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
01/16/2026 TSMR/PDMR - Zoning REQUIRES RESUBMIT See Engineering comments
01/29/2026 Commercial Plumbing Standard REVIEW COMPLETED
02/17/2026 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED 4350 E. Irvington Road
Post Office Box 711, Tucson, AZ 85702
February 17, 2026
WO#T167976
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Circle K - Tanque Verde and Catalina Hwy
TD-DEV-1025-00258
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 2/6/2026. There are existing facilities within the development which are
depicted upon the plan. TEP lines are not shown on profile view but do not appear to be
in conflict. New transformer location will be determined by TEP.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
Martin Rodriguez
(520) 991-5495
mrodriguez@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
01/29/2026 Fire New Construction Standard REVIEW COMPLETED
01/26/2026 ROW Engineering Review Standard REVIEW COMPLETED Review will continue on related PIA.