Permit Review Detail
Review Status: Approved
Review Details: DEVELOPMENT PACKAGE NEW v.2
Permit Number - TD-DEV-1023-00427
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Approved
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/11/2023 | Commercial Plumbing | APPROVED | |||
| 12/06/2023 | External Reviewers - COT Parks & Recreation | APPROVED | TD-DEV-1023-00427 – Approved TPRD Salvation Army Amphi Corps Playground and Building remodel, 218 E. Prince, Parcel 10604071B. Regarding TD-DEV-1023-00427, City of Tucson Parks and Recreation has no additional requirements for the Development Plan. Regards, Joe Barr Project Manager Parks and Recreation | City of Tucson Joe.Barr@tucsonaz.gov main 520.837.2263 |
||
| 12/06/2023 | External Reviewers - Tucson Electric Power (TEP) | APPROVED | December 6, 2023 WO#T98007 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: NEW PLAYGROUND, SPLASH PAD AND BUILDING REMODEL TD-DEV-1023-00427 Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted 11/27/2023. There are no existing facilities within the development plan and thus do not appear to be any apparent conflicts at this time. To apply for electric service, please call the New Construction department at (520) 918- 8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Your final plans should be sent to: Gabriela Bielecka Tucson Electric Power Company New Business Residential Project Manager P. O. Box 711 (OH 204) Tucson, AZ 85703 (520) 651-3833 Should you have any technical questions, please contact the area designer, Ryan Romero at (520) 240-4575. Sincerely, Design Admins Design Admins Tucson Electric Power |
||
| 12/15/2023 | NPPO | APPROVED | |||
| 12/08/2023 | ROW Engineering Review | APPROVED | |||
| 12/18/2023 | Site Engineering | APPROVED | |||
| 12/15/2023 | Site Landscape | APPROVED | |||
| 12/04/2023 | Site Zoning | APPROVED | |||
| 11/27/2023 | Fire New Construction | NOT REQUIRED | |||
| 11/17/2023 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 12/19/2023 | CDRC Post Review Express | REVIEW COMPLETED | |||
| 11/24/2023 | CDRC Review Coordinator Express | REVIEW COMPLETED | Parks&Rec review required per SOP. Review request email sent per ADOT, TEP. CDRC sent FYI email to PAG, USPS, SWG. | ||
| 12/14/2023 | External Reviewers - Arizona Department of Transportation (ADOT) | REVIEW COMPLETED | Good Afternoon, ADOT has no comments on this DEV. Thank you for the opportunity to review. |
||
| 11/24/2023 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 11/24/2023 | External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 11/24/2023 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS and SWG. No further action is required from customer at this time. | ||
| 11/24/2023 | OK to Submit - Zoning Fast | REVIEW COMPLETED |