Permit Number: TD-DEV-1022-00008
Parcel: 10702001D

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE REVIEW v.1

Permit Number - TD-DEV-1022-00008
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/15/2022 Commercial Plumbing APPROVED
12/28/2022 Site Zoning APPROVED
12/08/2022 OK to Submit - External Reviewer PC Addressing NOT REQUIRED
01/30/2023 Transportation Application Review NOT REQUIRED
02/01/2023 CDRC Post Review PENDING ASSIGNMENT
12/27/2022 External Reviewers - PC RFCD REQUIRES RESUBMIT The Regional Flood Control District (District) has reviewed the Development Package and Drainage Report 1st submittal and has the following comments:



1. Add to Grading and General Construction Note 8 “, including required Facility Impact Permits from the Regional Flood Control District.”

2. Add more grading detail to clearly show how flows will reach culvert inlets.

3. On Sheet 4, show District parcel 107 02 003D.

4. Show sewer easements for private sewer connections on District property. Provide legal descriptions to Pima County Real Property and apply for the easements.

5. South of Parcel 5, the distance from the edge of soil cement is less than 50 feet. Prepare a legal description for an additional dedication to the District and submit it to Real Property.

6. Review whether there are more opportunities for distributed retention, such as a the NW corner of the project at the access road intersection.

7. Reconfigure Pad 4 so that the entire pad grade is 1 foot above the Existing Conditions Model water surface elevation.

8. Retention immediately adjacent to soil cement and levees is not allowed. Standard separation is 100 feet. Review and address.

9. Add to the drainage report information documenting compliance with District Standard DS-304 B.

10. Add information to the drainage report about requirements for levee recertification following installation of the new culvert. A performance bond will be held until the District and FEMA accept the recertification report.



The District requests that CDRC place a condition on the permit that a Facility Impact Permit is required prior to start of grading on District property.



Thank you,

Ann
12/22/2022 NPPO REQUIRES RESUBMIT CDRC TRANSMITTAL
TO: Planning and Development Services Department, Plans Coordination
FROM: Anne Warner, RLA
PDSD Landscape/Native Plant Preservation Section

PROJECT: Prince/I-10 South Grading Plan
Zoning - PAD 43
ACTIVITY NO: TD-DEV-1022-00008

TRANSMITTAL DATE: December 22, 2022
DUE DATE: December 1, 2022
COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Landscape Review Section comments were addressed.
This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.
General Note - UDC 2-10.4.1 Identification and Descriptive Data - All improvements and site information, such as adjacent rights-of-way and property lines, shown on the landscape plan will be identical in size and location to those shown on the base plan (site plan or tentative plat). Should amendments be required to the base plan through the review process, the same amendments will be made to the landscape plan which will then be resubmitted along with the base plan.
1. Olneya tesota has a requirement of 50% PIP/TOS, please correct calculations. Table UBC 7.7.5-1.
2. Show the location of the proposed salvage yard, and how it will be protected and irrigated long term. UDC Admin Manual 2-11.4.4.A.5.
3. Please describe the temporary irrigation system for the salvage yard as well as landscape. How are the plants in the salvage yard going to survive for a potential of 2 years? UDC Admin Manual – 2-11.4.4.B.4. Truck watering is not an acceptable method of irrigation.
4. A Commercial Rainwater Harvesting plan is required for each pad as development occurs. UDC Technical Standards Manual – Section 4-01.0.0. and Section 5-01.0.0 Landscaping and Screening.
5. Please identify on the plans, name, address, and contact number of the project monitor prior to any grading activities, UDC 7.7.5.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package

YOUR NEXT STEPS: Submit documents to the Tucson Development Center
https://tdc-online.tucsonaz.gov/#/home
1) Comment Response Letter (your response to
the reviewer's Requires changes comments)
2) Plan Set (or individual sheets)
3) Any other items requested by review staff

If you have any questions, please contact me at anne.warner@tucsonaz.gov
12/29/2022 Site Engineering REQUIRES RESUBMIT 1. A floodplain use permit will be required for the proposed grading in the floodplain.
2. Since the scope of work includes only the grading and the not the full development of the pads include a note on the grading sheets that calls out the temporary or permanent stabilization method for the graded soil to be used for this project.
3. Delineate the Erosion Hazard Setback required at Krueger Wash
4. Include spot grades in planned drainage swales/depressions to confirm drainage arrows
5. By PAD 43, existing bank protections and levee may not be modified or penetrated by any new drainage connections. Please remove the proposed "Southern Culvert" from plans and drainage report. Show how retention/detention will be provided to maintain adequate flow through the existing culverts. Please refer to the updated retention/detention manual at: https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Flood%20Control/Rules%20and%20Procedures/Stormwater%20Detention-Retention/dssdr-final-201406-manual.pdf With amendments listed at: https://www.tucsonaz.gov/files/pdsd/codes/Detention_Retention_Manual_Tech_Standards_Amemdments.pdf
6. By PAD 43, any proposed connections to existing outlets on PRFCD property requires a Facility Impact Permit (See comment from RFCD)
7. Provide an encroachment analysis in the drainage report to ensure the fill within the floodplain will not raise the BFE of adjacent properties by over 0.1 ft
8. Provide detail on side slopes of water harvesting basin. Sidewalls in the basins must be protected from erosion with measures compliant with TSM 2-01.11.1.
9. Provide a mitigation plan for the known and potential landfill areas.
10. Sheet 9
a. Per TSM 2-01.8.2 Fill slopes steeper than 20% and fill is greater than 5', benching into sound bedrock is required. This appears to be possible on the west side of Pad 3, especially with 18" over excavation. Please identify areas and provide benching information on plan sheet.
11. Sheet 10
a. Verify elevations – S.E. corner pad elevation 94.1 existing contours show 95+
b. Per the Geo report, Fill slopes greater than 20% shall be benched between Native material and structural fill. Please provide a typical detail of benching and identify required locations on grading plans.
12. Sheet 11
a. Keynotes 1, 3, & 5 are not called out on this plan sheet, identify them or remove notes.
b. Provide grading area dimensions around new 8" PVC line.
13. Sheet 12
1. Keynote 2, 3, & 5 are not called out on this plan sheet, identify them or remove notes.
2. Provide access agreement/easement for dirt access rd. to encroach onto ADOT property as shown.
3. This Dirt access is not identified on the SWPPP. Please provide a construction entrance/exit and provide a revised complete SWPPP including all grading areas.
14. Per Geo report, fill on one side of a building pad should be no more than 2 times as deep as fill on the other side of the pad to minimize differential settlement, indicate areas where this may be an issue on grading plans and direct appropriate over excavation to mitigate issue.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
12/22/2022 Site Landscape REQUIRES RESUBMIT See NPPO comments
11/01/2022 CDRC Application Completeness REVIEW COMPLETED Completed RS
12/13/2022 CDRC Review Coordinator REVIEW COMPLETED
02/01/2023 External Reviewers - Arizona Department of Transportation (ADOT) REVIEW COMPLETED
12/19/2022 Fire New Construction REVIEW COMPLETED
11/01/2022 OK to Submit - Engineering REVIEW COMPLETED
11/03/2022 OK to Submit - Zoning REVIEW COMPLETED
12/19/2022 Traffic Engineering Review REVIEW COMPLETED TP-DEV-1022-00008
Comments:

(No Address. Location: Ft. Lowell Rd., west of I-10 frontage.)

1. A PIA is going to be required for this project. https://www.tucsonaz.gov/tdot/private-improvement-agreement Contact TDOT Engineering for information. DOT-Engineering-Review-Section@tucsonaz.gov Or call. 520-791-5100 Jesus Villezcas


David Stiffey
DTM Project Coordinator
David.Stiffey@tucsonaz.gov