| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/16/2023 | Commercial Plumbing | APPROVED | |||
| 10/13/2023 | External Reviewers - Tucson Airport Authority | APPROVED | October 11, 2023 Planning and Development Services City of Tucson 201 North Stone Avenue Tucson, AZ. 85701 RE: TD-DEV-0823-00375, Adding Truck wells and restriping back parking / 6221 S Palo Verde Rd, Tucson, AZ 85706, Received September 26, 2023 To whom this may concern, Thank you for the opportunity to comment on TD-DEV-0823-00375, the development plan for adding truck wells and restriping back parking at 6221 S Palo Verde Rd. This development is located in the S.W. quarter of the S.W. quarter of Section 9, Township 15S, Range 14E, of the Gila and Salt River Meridian. The development site occupies parcel number 140-29-1990, covers approximately 3.97 ± acres, and is zoned as Light Industrial Zone 1 (I-1). The nearest major roadway intersection is East Hemisphere Loop and South Palo Verde Road, approximately 200 feet to the southwest of the subject development. This site does lie within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace. The Tucson Airport Authority approves the proposed project and is not requiring a resubmit of this project. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520- 573-4811. Respectfully, Scott Robidoux, C.M. Manager of Planning |
||
| 10/06/2023 | ROW Engineering Review | APPROVED | |||
| 10/16/2023 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 10/12/2023 | Site Engineering | REQUIRES RESUBMIT | Tucson codes and ordinances can be found online at https://codelibrary.amlegal.com/codes/tucson/latest/overview The Design Standards for Stormwater Detention and Retention manual can be found online at https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf 1. Show that each relocated dumpster enclosure has a clear space of 14 feet by 40 feet in front of it, compliant with TSM 8-01.5.3 B. 2. Ensure dumpster enclosures meet all other maneuvering standards outlined in TSM 8-01.5 Lianne Evans lianne.evans@tucsonaz.gov |
||
| 10/16/2023 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Paul Camarena PDSD Zoning Review Section PROJECT: 6221 S PALO VERDE RD Development Package (1st Review) TD-DEV-0823-00375 TRANSMITTAL DATE: October 16, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is August 30,2024 . SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS) CONTENT REQUIREMENTS 2-06.4.1 - The name, mailing and email addresses, and phone number of the primary property owner of the site, the developer of the project, registrant(s), and other person(s), firm(s), or organization(s) that prepared the development package documents shall be provided on the right half of the cover sheet. The applicable registration or license number shall be provided if prepared by or with the assistance of a registered professional, such as a surveyor, architect, landscape architect, or engineer. All sealing shall be consistent with Arizona Board of Technical Registration guidelines. 1. COMMENT: 2-06.4.1 - Provide the information noted by the standard above. 2-06.4.2 - The title block shall include the following information and be provided on each sheet: 2-06.4.2.B - A brief legal description and a statement as to whether the project is a re-subdivision are to be provided. On re-subdivisions, provide the recording information of the existing subdivision plat; 2. COMMENT: 2-06.4.2.B - Provide the brief legal description on the title block. 2-06.4.3 - The administrative street address and relevant case numbers (development package document, subdivision, rezoning, board of adjustment, DDO, MDR, DSMR, overlay, etc.) shall be provided adjacent to the title block on each sheet. 3. COMMENT: 2-06.4.3 - Provide the development package case number, TD-DEV-0823-00375, adjacent to the title block on each sheet. 2-06.4.7.A.4 - Identify the existing and proposed use of the property as classified per the UDC. List all UDC sections applicable to the proposed uses. 4. COMMENT: 2-06.4.7.A.4 - Revise the use, It appears that the use being proposed is Commercial storage use. 2-06.4.9.H.5 - If utilizing parking area access lanes (PAALs), they shall be designed in accordance with Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC. 5. COMMENT: 2-06.4.9.H.5 - As you are relocating the dumpster enclosure provide PAAL dimension. 2-06.4.9.H.5.a - Show all motor vehicle off-street parking spaces provided, fully dimensioned. As a note, provide calculations on the number of spaces required (include the ratio used) and the number provided, including the number of spaces required and provided for the physically disabled. The drawing should indicate parking space locations for the physically disabled. A typical parking space detail shall be provided for both standard parking spaces and those for the physically disabled. For information on parking requirements for the physically disabled, refer to adopted building and accessibility codes of the City of Tucson. Design criteria for parking spaces and access are located in Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC. 6. COMMENT: 2-06.4.9.H.5.a - Revise the parking calculation, for commercial storage the parking calculation is “1 space per 5,000 sq. ft. GFA, plus 1 space per 5,000 sq. ft. of outdoor storage area for the first 20,000 sq. ft. of outdoor storage area, plus 1 space per 10,000 sq. ft. of outdoor storage area over 20,000 sq. ft. of outdoor storage area” 2-06.4.9.H.5.c - Show all loading zones, vehicle maneuverability fully dimensioned, and access route. Provide as a note the number of loading spaces required, the number provided, whether the loading space is a Type A or B as provided in UDC Section 7.5.4. 7. COMMENT: 2-06.4.9.H.5.c - Provide the information noted by the standard above. 2-06.4.9.R - Show on-site pedestrian circulation and refuge utilizing location and the design criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards Manual. 8. COMMENT: 2-06.4.9.R - Show pedestrian circulation to both dumpsters. ***For additional information on the any standard presented in this memo, please refer to the City of Tucson “Unified Development Code” – Administrative Manual Section 2-06 or Technical Standards noted in the comments. https://www.tucsonaz.gov/pdsd/all-codes-plans-determinations If you have any questions about this transmittal, Contact Paul Camarena at (520)837-4986 or by email Paul.Camarena@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
||
| 09/13/2023 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 09/26/2023 | CDRC Review Coordinator Express | REVIEW COMPLETED | Review request email sent per TAA. FYI email sent to PAG, USPS, SWG & TEP. | ||
| 09/26/2023 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/26/2023 | External Reviewers - Southwest Gas | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/26/2023 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/26/2023 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | FYI email sent per PAG, USPS, SWG & TEP | ||
| 09/28/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 09/27/2023 | NPPO | REVIEW COMPLETED | |||
| 09/13/2023 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 09/21/2023 | OK to Submit - Zoning Fast | REVIEW COMPLETED | |||
| 09/27/2023 | Site Landscape | REVIEW COMPLETED |