Permit Number: TD-DEV-0823-00361
Parcel: 133231650

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-0823-00361
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/21/2023 OK to Submit - Zoning Fast APPLICATION INCOMPLETE PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Tucson Specialty Hospital – Building & Canopy Addition
7220 E. Rosewood St. – PAD-3
TD-DEV-0823-00361
Development Package OK to Submit (1st Review)

TRANSMITTAL DATE: August 21, 2023

The development package has been reviewed by the Zoning Review Section for minimal compliance with the requirements of the Administrative Manual (AM) 2-06. It has been determined that the submitted plans do not provide sufficient information to complete a plan review. The following items need to be addressed prior to re-submittal.

1. The plans submitted are the building plan set and do not meet the requirements of Administrative Manual (AM) 2-06.

2. There are now two (2) Development Packages (DPs) submitted for the proposed additions on this site, TD-DEV-0223-00136, and this plan TD-DEV-0823-00361, withdraw DP TD-DEV-0823-00361.

This review is a cursory review for compliance with the Checklist for Minor Changes to Commercial/Industrial Sites and does not constitute a complete review. Addition comments maybe forth coming once the plan is accepted for review.

If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov.
08/21/2023 CDRC Post Review Express PENDING ASSIGNMENT
08/21/2023 CDRC Review Coordinator Express PENDING ASSIGNMENT
08/21/2023 Commercial Plumbing PENDING ASSIGNMENT
08/21/2023 Fire New Construction PENDING ASSIGNMENT
08/21/2023 NPPO PENDING ASSIGNMENT
08/21/2023 ROW Engineering Review PENDING ASSIGNMENT
08/21/2023 Site Engineering PENDING ASSIGNMENT
08/21/2023 Site Landscape PENDING ASSIGNMENT
08/21/2023 Site Zoning PENDING ASSIGNMENT
08/18/2023 OK to Submit - Engineering Fast REQUIRES RESUBMIT 1. Please remove the construction plans from the plan set and only provide a site plan and relevant details. The construction plans will be reviewed with the associated building permit.

Lianne Evans
lianne.evans@tucsonaz.gov
08/18/2023 CDRC Application Completeness Express REVIEW COMPLETED
08/18/2023 OK to Submit - Landscape Fast REVIEW COMPLETED