Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.1
Permit Number - TD-DEV-0823-00351
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/19/2023 | Site Engineering | APPLICATION INCOMPLETE | 1. Per UDC article 7.4.6.K.2 the alley must be a minimum 20 feet wide to be used as a primary access. After talking with Faffs Riederer from DTM he agrees that the better solution would be to extend the existing curb cut from the driveway to the west of this site and share a driveway entrance onto 22nd St. This work would be done in a ROW permit and this DP would not be needed. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
||
| 09/15/2023 | Site Zoning | APPLICATION INCOMPLETE | See Engineering comments. A development package is not necessary for this proposal. | ||
| 09/15/2023 | External Reviewers - Tucson Airport Authority | APPROVED | September 15, 2023 Planning and Development Services City of Tucson 201 North Stone Avenue Tucson, AZ. 85701 RE: TD-DEV-0823-00351, TSMR / 328 E 22nd St, Tucson, AZ 85713, Received August 29, 2023 To whom this may concern, Thank you for the opportunity to comment on TD-DEV-0823-00351, a request to modify a standard to allow for main access to the property to be from the existing alley at 328 E 22nd Street. This development is located in the N.E. quarter of the N.E. quarter of Section 24, Township 14S, Range 13E, of the Gila and Salt River Meridian. The development site occupies parcel number 118-12-0360, covers approximately 0.17 ± acres, and is zoned as Residence Zone 2 (R-2). The nearest major roadway intersection is East 22nd Street and South 3 rd Avenue, approximately 200 feet to the northeast of the subject development. This site does lie within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace. The Tucson Airport Authority approves the proposed project and is not requiring a resubmit of this project. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520- 573-4811. Respectfully, Scott Robidoux, C.M. Manager of Planning |
||
| 08/30/2023 | NPPO | NOT REQUIRED | |||
| 09/18/2023 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 09/18/2023 | Commercial Plumbing | REQUIRES RESUBMIT | 1. Show the building drain connecting to the public sewer and the section of the public sewer between manholes 9891-04A and 9891-03A. Reference: Section 107.2.1, IBC 2018. 2. Verify the building FFE and the rim elevation of the next upstream manhole. The elevations noted on the drawing do not comport with the topographic maps of the area. Reference: Section 107.2.1, IBC 2018. 3. Determine the need for a backwater valve for the building per Section 714.1, IPC 2018, as amended by the City of Tucson. |
||
| 09/15/2023 | ROW Engineering Review | REQUIRES RESUBMIT | See Engineering Comments. Please submit for a ROW General permit to make an expanded shared driveway apron, expanding the existing apron to the west. Email or call to discuss -Faffs faffs.riederer@tucsonaz.gov 520-837-6647 | ||
| 08/11/2023 | CDRC Application Completeness Express | REVIEW COMPLETED | Customer was advised regarding full submittal review needed prior to TSMR review. | ||
| 08/28/2023 | CDRC Review Coordinator Express | REVIEW COMPLETED | Added external reviewers, sent emails and sent FYI emails per SOP. | ||
| 09/15/2023 | External Reviewers - Arizona Department of Transportation (ADOT) | REVIEW COMPLETED | [EXTERNAL] Re: DUE SEPTEMBER 17, 2023 / TSMR / TD-DEV-0823-00351 Jay Gomes CDRC Good Morning, ADOT has no comments on this DEV. Thank you for the opportunity to review. |
||
| 08/28/2023 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | Sent FYI emails per SOP. | ||
| 08/28/2023 | External Reviewers - Southwest Gas | REVIEW COMPLETED | Sent FYI emails per SOP. | ||
| 08/28/2023 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | Sent FYI emails per SOP. | ||
| 08/28/2023 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | Sent FYI emails per SOP. | ||
| 08/30/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 08/18/2023 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 08/14/2023 | OK to Submit - Landscape Fast | REVIEW COMPLETED | |||
| 08/21/2023 | OK to Submit - Zoning Fast | REVIEW COMPLETED | |||
| 08/30/2023 | Site Landscape | REVIEW COMPLETED |