Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.1
Permit Number - TD-DEV-0823-00343
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/13/2023 | Commercial Plumbing | APPROVED | |||
| 08/25/2023 | NPPO | APPROVED | |||
| 08/25/2023 | Site Landscape | APPROVED | |||
| 09/13/2023 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 08/14/2023 | Fire New Construction | REQUIRES RESUBMIT | -Include no parking/fire access tow away signs for turn around. john.vincent@tucsonaz.gov 5203495581 |
||
| 09/11/2023 | ROW Engineering Review | REQUIRES RESUBMIT | TD-DEV-0823-00343 (3711 E GLENN ST TUCSON, AZ 85716) Please resubmit revised drawings along with a detailed response letter which states how all comments were addressed. Comments: 1. AM 2-06.4.8.C – Dimension the width of curbs, curb cuts, and sidewalks in the ROW (existing and proposed) 2. P. A. G. SD 207, ICC 117.1 Sec 405.7 - Where adjoining sidewalk from the property ties to sidewalk along the ROW frontage, a 60” X 60” ADA landing is required with a maximum 2% cross slope. Please identify this landing with dimensions and specifications with a callout. Faffs Riederer Faffs.Riederer@tucsonaz.gov Abbreviations: City of Tucson Code (COTC), Unified Development Code (UDC) Administrative Manual (AM), Technical Standards Manual (TSM), Street Design Guide (SDG), Pima Association of Governments Standard Details (P. A. G. SD), Access Management Guidelines (AMG), Major Streets and Routes Plan (MS&R). |
||
| 08/24/2023 | Site Engineering | REQUIRES RESUBMIT | Tucson codes and ordinances can be found online at https://codelibrary.amlegal.com/codes/tucson/latest/overview The Design Standards for Stormwater Detention and Retention manual can be found online at https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf TD-DEV-0823-00343 1. A lot combination will be required. 2. Provide a detail showing the profile of the geocell and gravel system. 3. Provide waste stream calculations compliant with TSM 8-01.8. 4. From recent clarification from Environmental Services per TSM section 8, although recycling service isn’t required the site needs to provide at minimum the enclosure space for both solid waste and recycling. A single enclosure won’t be sufficient and a double enclosure or additional single enclosures will be needed to meet this requirement. It is also important to point out per TSM section 8-01.4.I - required parking may be reduced for existing development when solid waste and recycling enclosures are provided. Lianne Evans lianne.evans@tucsonaz.gov |
||
| 08/31/2023 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Nathan Herrera Planner PROJECT: Development Package (1st Review) TD-DEV-0823-00343 TRANSMITTAL DATE: August 31, 2023 DUE DATE: September 09, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is August 02, 2024. 2-06.3.0 Format Requirements: 1. 2-06.3.4 - A title block shall be provided in the lower right quadrant of each sheet. COMMENT: Show correct DP # (TD-DEV-0823-00343) in the bottom right corner on all sheets. 2-06.4.0 Content Requirements: 2. 2-06.4.7.A.2 - List the gross area of the site/subdivision by square footage and acreage. COMMENT: On Sheet 1, under Development Package Calculations, the square footage of the property does not match with the square footage under Zoning and Land Use Notes. Clarify the correct square footage and update Lot Coverage Calculation. 3. 2-06.4.7.A.8.c - For development package documents provide the percentage of building, lot area, or vehicular use area expansion. COMMENT: Per UDC Article 11.4.13, Lot Coverage calculation should include, “The area of a lot covered by buildings, storage areas, and vehicular use areas.” Update the Lot Coverage calculation to include all items required per the above standard. 2-06.4.8 - Existing Site Conditions 4. 2-06.4.8.A - Provide site boundary perimeter information, including bearing in degrees, minutes, and seconds, with basis for bearing noted, together with distances in feet, to hundredths of a foot, or other functional reference system. COMMENT: Add the above information to Sheet 2. 5. 2-06.4.8.B - All easements shall be drawn on the plan. The recordation information, location, width, and purpose of all easements on site will be stated. Blanket easements should be listed in the notes, together with recordation data and their proposed status. Should an easement not be in use and be proposed for vacation or have been abandoned, so indicate. However, should the easement be in conflict with any proposed building location, vacation of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided. COMMENT: Aerial imagery shows an electric power pole located on site. Identify the pole on the Sheet 2 and clarify if there is an existing easement. If there is an existing easement provide the above information. 6. 2-06.4.8.C - The following information regarding existing private or public right-of-way adjacent to or within the site shall be provided: the name, right-of-way width, recordation data, type and dimensioned width of paving, curbs, curb cuts, and sidewalks. COMMENT: Add the above information for Glenn Street to Sheet 2. 7. 2-06.4.9.A - Draw in all proposed lot lines with approximate distances and measurements. COMMENT: Sheet 1, Note 6 under Zoning and Land Use Note states a Covenant Regarding Development and Use of Real Property to be recorded; Note 30 on Sheet 2 states “refer to Lot Combination”. Clarify if the two parcels that makeup the property are going to be combined or if the Covenant will be recorded. Zoning cannot approve until either the Covenant or a Lot Combination are recorded. Provided the recorded document with the next submittal. 2-06.4.9.H Proposed Traffic Circulation 8. 2-06.4.9.H.5.a -Design criteria for parking spaces and access are located in Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC. COMMENT: Per UDC Article 7.4.6.G, “Parking spaces must be marked with a four-inch wide, white stripe along all sides, except at the entrance to the stall or where the limits of the space are defined by other means, such as curbing.” Demonstrate on the Parking Space Plan on Sheet 1 how the above standard is being met. COMMENT: Per UDC Article 7.4.6.I, Vehicular Use Areas must be surfaced with the following; pervious or impervious asphaltic or cement concrete, penetration treatment of bituminous material and seal coat of bituminous binder and mineral aggregate, or Alternative surfacing as determined appropriate by the City Engineer. The proposed paving for the property is described as “compacted pea gravel” and does not appear to meet the above required standard. Approval for the proposed alternate surfacing must be determined by the City Engineer. If the City Engineer does not approve a Board of Adjustment Variance approval will be required. COMMENT: Per UDC Article 7.4.6.E.2, “The minimum height clearance along access lanes and PAALs is 15 feet.” Aerial imagery shows power lines on the site that appear to be over the proposed PAAL. Provide the clearance of the powerlines to ensure the above standards is met, or, state the power lines are to be removed. COMMENT: Per UDC Article 7.4.9.B.2.h, “An access aisle at least five feet wide must be provided between two rows of bicycle parking.” It appears that the clearance between the long-term and short-term bicycle parking spaces do not meet the above standard. If the short-term parking is oriented east-to-west that should allow for the above standard to be met. 9. 2-06.4.9.O - All applicable building setback lines, such as zoning will be shown. COMMENT: Per UDC Article 6.3-2.A, in the R-2 Zone, a Nonresidential Use adjacent to a Residential Zone requires a perimeter yard setback the greater of 10’ or ¾ the height of the building wall. Change the Perimeter Yard notes on Sheet 1, under Development Package Calculations to show the required setbacks. Sheet 2 shows the side and rear property setbacks as 8’. The minimum required is 10’. Adjust the setbacks, and Keynote 8, as shown on Sheet 2 to show the correct required setbacks. COMMENT: The property is located on a Major Street and Route. Per UDC Article 6.4.5.C.2.a, “multifamily development abutting an Arterial or Collector Street the minimum required street perimeter yard is ten feet, as measured from the existing or future property line.” Change the Perimeter Yard notes on Sheet 1, under Development Package Calculations to show the required setbacks. Keynote on Sheet 2 shows the required street setback as 21’. Adjust the setbacks, and Keynote 9, as shown on Sheet 2 to show the correct required setbacks. 10. 2-06.4.9.R - Show on-site pedestrian circulation and refuge utilizing location and the design criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards Manual. COMMENT: Per TSM Section 7-01.4.3.B, All sidewalks must have a minimum unobstructed vertical clearance of 84 inches. The proposed height of the handicap sign on Sheet 1 does not meet this standard. The sign must be heightened to be compliant with the above standard. 11. 2-06.4.9.V - For gang mailboxes indicate location to assure there are no conflicts with other requirements, such as pedestrian accessibility, utilities, and landscaping. COMMENT: It appears that the mailboxes for the property are located in the ROW. Show the mailboxes on Sheet 2. If you have any questions about this transmittal, please contact me at Nathan.Herrera@tucsonaz.gov or at 520-837-4894. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: revised Development Package along with a detailed response letter, which states how all Zoning Review Section comments were addressed. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home. Instructions for resubmittal - https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf. |
||
| 08/03/2023 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 08/07/2023 | CDRC Review Coordinator Express | REVIEW COMPLETED | No external reviewers nor added. | ||
| 08/03/2023 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 08/03/2023 | OK to Submit - Landscape Fast | REVIEW COMPLETED | |||
| 08/04/2023 | OK to Submit - Zoning Fast | REVIEW COMPLETED |