Permit Number: TD-DEV-0623-00288
Parcel: 13312006M

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-0623-00288
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/03/2023 Commercial Plumbing APPROVED
07/18/2023 Site Engineering APPROVED
08/08/2023 Traffic Engineering Review APPROVED TD-DEV-0623-00288 (7822 E WRIGHTSTOWN RD TUCSON, AZ 85715)

Comments:

1. Work in the right-of-way requires a ROW Permit. Please apply for a separate ROW Permit on DTC Online.

Faffs Riederer
Faffs.Riederer@tucsonaz.gov
06/30/2023 NPPO NOT REQUIRED
08/08/2023 CDRC Post Review PENDING ASSIGNMENT
06/30/2023 Site Landscape REQUIRES RESUBMIT Grady Street requires a landscape border. It appears that 1 palm tree will be removed. Please add to plan, and show replanting another tree with irrigation.
07/11/2023 Site Zoning REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Catalina Village West Access
Development Package (1st Review)
TD-DEV-0623-00288

TRANSMITTAL DATE: July 11, 2023

DUE DATE: August 03, 2023

COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is June 26, 2024.

CONTENT REQUIREMENTS

1. COMMENT: 2-06.4.3 – Provide the development package case number, TD-DEV-0623-00288, adjacent to the title block on all sheets.

If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package & detailed response letter.
06/27/2023 CDRC Application Completeness REVIEW COMPLETED
06/28/2023 CDRC Review Coordinator REVIEW COMPLETED No external reviewers nor added.
07/16/2023 Fire New Construction REVIEW COMPLETED
06/27/2023 OK to Submit - Engineering REVIEW COMPLETED
06/27/2023 OK to Submit - Landscape REVIEW COMPLETED
06/27/2023 OK to Submit - Zoning REVIEW COMPLETED
08/01/2023 TW New Development Review REVIEW COMPLETED TD-DEV-0623-00288- Development Package Review v1 - 7822 E WRIGHTSTOWN RD

1. Tucson Water has no objections to the proposed development package.

2. Any questions, comments or concerns about these comments may be directed to:

Tim Rowe, P.E., Civil Engineer
Tucson Water, New Development Section
201 N. Stone Avenue, #2-220
P.O. Box 27210
Tucson, AZ 85726-7210
(520) 837-2106
tim.rowe@tucsonaz.gov