Permit Number: TD-DEV-0523-00257
Parcel: 117130410

Address:
20 E OCHOA ST

Review Status: Approved

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-0523-00257
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Approved
Review Date Reviewer's Name Type of Review Description Status Comments
04/03/2024 Commercial Plumbing APPROVED
04/04/2024 Design Review APPROVED Design Professional Review
Development No. TD-DEV-0523-00257
Westpoint Apartments II, Revision #1
Date: 4 April 2024
From: R. Fe Tom, AIA

Project: Revision to Development Plans Package
Project Name: West Point Apartments II
Address: 20 E. Ochoa St
tac #: 22039
Re: Design Professional Review Comments

I have reviewed a letter outlining revisions from Grenier Engineering,Inc dated 20 Feb 2024 and Development Package for above project with revisions noted as delta 1. All changes are site related and are not critical to the esthetics of the previously approved project. I therefore approve the requested modification.
Sincerely,
Richard Fe Tom, AIA
COT Design Professional Reviewer
04/05/2024 External Reviewers - Tucson Electric Power (TEP) APPROVED April 5, 2024
WO#T107083
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: New 7-story Apartment Building
TD-DEV-0523-00257
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 3/1/2024. There are existing facilities within the development which are
depicted upon the plan; there are conflicts including existing TEP poles and overhead
lines. Plans indicate that there will be coordination with TEP to have them transitioned
to underground lines where applicable.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our land Resources Department,
TEPDEVREV@tep.com.
Should you have any technical questions, please contact the area designer,
Fred Quintero
(520) 235-6329
fquintero@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
04/01/2024 Site Engineering APPROVED
04/16/2024 Site Landscape APPROVED
04/03/2024 Site Zoning APPROVED
04/16/2024 NPPO NOT REQUIRED
02/23/2024 CDRC Application Completeness REVIEW COMPLETED
04/17/2024 CDRC Post Review REVIEW COMPLETED
03/01/2024 CDRC Review Coordinator REVIEW COMPLETED Review request email sent per TEP. CDRC sent FYI email to PAG, USPS, SWG.
03/01/2024 External Reviewers - Pima Association of Governments REVIEW COMPLETED CDRC sent FYI email to PAG, USPS, SWG. No further action is required from the customer at this time.
03/01/2024 External Reviewers - Southwest Gas REVIEW COMPLETED CDRC sent FYI email to PAG, USPS, SWG. No further action is required from the customer at this time.
03/01/2024 External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED CDRC sent FYI email to PAG, USPS, SWG. No further action is required from the customer at this time.
03/28/2024 Fire New Construction REVIEW COMPLETED
04/02/2024 Historic REVIEW COMPLETED
02/28/2024 OK to Submit - Engineering REVIEW COMPLETED
02/26/2024 OK to Submit - Landscape REVIEW COMPLETED
02/29/2024 OK to Submit - Zoning REVIEW COMPLETED
04/02/2024 ROW Engineering Review REVIEW COMPLETED No Comments

David Stiffey