Permit Number - TD-DEV-0423-00225
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/02/2023 CDRC Post Review PENDING ASSIGNMENT
05/02/2023 CDRC Review Coordinator PENDING ASSIGNMENT
05/02/2023 Commercial Plumbing PENDING ASSIGNMENT
05/02/2023 Fire New Construction PENDING ASSIGNMENT
05/02/2023 NPPO PENDING ASSIGNMENT
05/02/2023 ROW Engineering Review PENDING ASSIGNMENT
05/02/2023 Site Engineering PENDING ASSIGNMENT
05/02/2023 Site Landscape PENDING ASSIGNMENT
05/02/2023 Site Zoning PENDING ASSIGNMENT
05/02/2023 OK to Submit - Zoning REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Fontana Group – Building Expansion
3509 N Campbell Av. – O-3
TD-DIV-0423-00225

TRANSMITTAL DATE: April 28, 2023

The development package has been reviewed by the Zoning Review Section for minimal compliance with Administrative Manual (AM) 2-06. It has been determined that the submitted plans do not provide sufficient information to complete a plan review. The following items need to be addressed prior to re-submittal.

1. Provide a Development Package (DP) that meets the requirements of the Administrative Manual (AM) 2-06. As this site is made up of 8 parcels which act as a single site the development package shall show all 8 parcels.

2. 2-06.4.7.A.8.d - When the proposed site is part of a larger site, the calculations encompass the entire site, whether existing or proposed. If the project is being phased, calculations must show that, at each phase, requirements are being met.

If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov.
05/01/2023 CDRC Application Completeness REVIEW COMPLETED
05/01/2023 OK to Submit - Engineering REVIEW COMPLETED
05/01/2023 OK to Submit - Landscape REVIEW COMPLETED