Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE NEW v.1
Permit Number - TD-DEV-0325-00081
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/02/2025 | External Reviewers - Tucson Electric Power (TEP) Standard | REQUIRES RESUBMIT | April 2, 2025 WO#T146558 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: Water Recharge Basin TD-DEV-0325-00081 Tucson Electric Power Company (TEP) has reviewed and cannot approve the development plan submitted 3/26/2025. There are existing facilities within the development which are not depicted upon the plans. Further, Docket 11649 Page 1654 and Docket 6746 Page 552 have been included within the attachments pertaining to existing facilities. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918- 8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. If easements are required, they will be secured by separate instrument. Should you have any easement questions, please contact our Land Resources Department, LandReviews@tep.com. Should you have any technical questions, please contact the area designer, Martin Rodriguez (520) 991-5495 mrodriguez@tep.com Sincerely, Design Admins Design Admins Tucson Electric Power |
||
| 05/29/2025 | Floodplain Administration Review Standard | REQUIRES RESUBMIT | 1. The proposed development is within both ERZ (Environmental Resource Zone) and Floodway (Tanque Verde Wash Floodway and Agua Caliente Floodway). A drainage report, encroachment analysis, and ERR (Environmental Resource Report) will be required to demonstrate no adverse impact to both the floodway and ERZ. 2. The ERR will be required to demonstrate no critical riparian habitat is being disturbed or removed and a mitigation plan may be required to enhance and revegetate the disturbed area, if the critical riparian habit is being disturbed. 3. Reduce the footprint of the disturbed area for the excavation or demonstrate how all 14 standards are being met from COT code sec 26-5.1 Floodway development. Especially numbers 4, 5, 6, 10, and 13. Floodway has a no rise requirement which triggers encroachment analysis and pre- and post flood conditions assessment for depth, velocity, and floodplain limits. If the floodplain limits increase - especially in a way that increases floodplain on a property, then the LOMR is also needed to be submitted to City and FEMA. Please note, COT will need additional approvals from other agencies including Army Corps of Engineers for excavating in the FEMA high-risk floodway. 4. An Memo Of Understanding will be required to set up maintenance responsibility for the basin Austin Wesnitzer 520-305-2376 Austin.Wesnitzer@tucsonaz.gov |
||
| 05/23/2025 | NPPO Standard | REQUIRES RESUBMIT | This project cannot be reviewed until the associated site development package is submitted for review. | ||
| 05/29/2025 | Site Engineering Standard | REQUIRES RESUBMIT | 1. The proposed development is within both ERZ (Environmental Resource Zone) and Floodway (Tanque Verde Wash Floodway and Agua Caliente Floodway). A drainage report, encroachment analysis, and ERR (Environmental Resource Report) will be required to demonstrate no adverse impact to both the floodway and ERZ. 2. The ERR will be required to demonstrate no critical riparian habitat is being disturbed or removed and a mitigation plan may be required to enhance and revegetate the disturbed area, if the critical riparian habit is being disturbed. 3. Reduce the footprint of the disturbed area for the excavation or demonstrate how all 14 standards are being met from COT code sec 26-5.1 Floodway development. Especially numbers 4, 5, 6, 10, and 13. Floodway has a no rise requirement which triggers encroachment analysis and pre- and post flood conditions assessment for depth, velocity, and floodplain limits. If the floodplain limits increase - especially in a way that increases floodplain on a property, then the LOMR is also needed to be submitted to City and FEMA. Please note, COT will need additional approvals from other agencies including Army Corps of Engineers for excavating in the FEMA high-risk floodway. 4. An MOU will be required to set up maintenance responsibility for the basin. Stephen Blood (520) 837-4958 Stephen.blood@tucsonaz.gov |
||
| 05/23/2025 | Site Landscape Standard | REQUIRES RESUBMIT | This project cannot be reviewed until the associated site development package is submitted for review. | ||
| 05/30/2025 | Site Zoning Standard | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TD-DEV-0325-00081 – Development Package (1st Review) 1501 N Houghton Rd, Tucson, AZ 85749 TRANSMITTAL DATE: May 30, 2025 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM). Per UDC Section 3.3.3.G.5.c, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is March 15, 2026. 1. COMMENT: Full review and approval for this permit cannot be granted until approved grading development package for fill site locations (parcels 133033960, 133033970, 133033980, 133033990, 133034000, 133034010, and 13303304C per General Note 2) is approved. 2. COMMENT: Provide a general note that the fill from this site is to be used only on site (La Mariposa). Transportation of, or usage, of fill material off-site may reclassify this borrow pit as a type of industrial extraction that is not permitted in SR zoning. 3. COMMENT: The submitted plan(s) should also include details regarding destination of fill, phasing/timeline, transportation and access routes, staging areas, and parking areas. If you have any questions about this transmittal, please contact fernando.garcia2@tucsonaz.gov. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A corrected development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf. |
||
| 03/14/2025 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
| 03/26/2025 | CDRC Review Coordinator Express | REVIEW COMPLETED | CDRC added TEP to the workflow. Review request email sent to TEP. | ||
| 04/17/2025 | Commercial Plumbing Standard | REVIEW COMPLETED | |||
| 03/27/2025 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 03/25/2025 | OK to Submit - Engineering Fast | REVIEW COMPLETED | |||
| 03/26/2025 | OK to Submit - Zoning Fast | REVIEW COMPLETED | |||
| 04/07/2025 | ROW Engineering Review Standard | REVIEW COMPLETED | |||
| 03/26/2025 | ROW Review | REVIEW COMPLETED |