Permit Number: TD-DEV-0325-00078
Parcel: 121116630

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-0325-00078
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
04/21/2025 NPPO Standard NOT REQUIRED
04/21/2025 Site Landscape Standard NOT REQUIRED
04/16/2025 Commercial Plumbing Standard REQUIRES RESUBMIT Provide independent sewer connections for the buildings located on the two parcels. Each occupiable building that abuts a street in which there is a public sewer shall have an independent connection to the public sewer. Show how access to the public sewer will be provided for parcel A. Reference: Section 701.3, IPC 2018.
04/01/2025 ROW Engineering Review Standard REQUIRES RESUBMIT TD-DEV-0325-00078 • 4705 E FAIRMOUNT ST

1.In accordance with Section 10-01.3.3 of the Technical Standards Manual, a pedestrian circulation path, as outlined in Section 10-01.4.0, must be established along the full street frontage of the development. This includes bringing the curb access ramp at the NE corner of Swan Rd and Fairmont Av into compliance with current standards and specifications.

2. Show and label the existing roadway infrastructure along Swan Rd.

3. Per Sec. 25-43 of the Tucson City code, the existing curb openings not utilized with this development will have to be closed.

4. Per Sec 25-38 of Tucson City code, a minimum 5' separation from the catch basin and driveway must be provided.

If you have any questions, please contact Richard Leigh at Richard Leigh at richard.leigh@tucsonaz.gov
04/28/2025 Site Engineering Standard REQUIRES RESUBMIT 1. See that all zoning comments are addressed.
2. Per UDC 7.4.6.I – the proposed gravel driveway surface does not meet surfacing requirements. Show how the gravel will be stabilized (using a geogrid product) and how it will be contained. Provide more detail for callout 13 – edge of gravel driveway surface.
3. Keynote 5 indicates that there is existing sidewalk along the property frontage to E Fairmount St, however, Map Tucson is not showing any sidewalk existing. Revise as needed.
4. The plans have the two streets fronting the project as Swan Rd and Fairmount Av, but they should be labeled as N Swan Rd and E Fairmount St. Revise as needed.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
04/18/2025 Site Zoning Standard REQUIRES RESUBMIT CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Nick Ross
Section Manager

PROJECT:
Development Package (1st Review)
TD-DEV-0325-00078
TRANSMITTAL DATE: 4/18/25

DUE DATE: April 14, 2025

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is 3/21/26.


1. 2-06.3.4 - A title block shall be provided in the lower right quadrant of each sheet.
COMMENT: Please add TD-DEV-0325-00078 to all sheets of the planset.

2. 2-06.4.7.A.8.a - Floor area for each building;
COMMENT: Provide GFA for each proposed building on site


3. 2-06.4.9.A - Draw in all proposed lot lines with approximate distances and measurements.
COMMENT: A lot combination will be required

4. 2-06.4.9.H.2 - Show future and existing sight visibility triangles. On a designated MS&R street, the sight visibility triangles are based on the MS&R cross-section.
COMMENT: There are no SVT shown on the site plan.

5. 2-06.4.9.H.4 - Indicate if existing streets are public or private; provide street names, widths, curbs, sidewalks, and utility locations, all fully dimensioned.

COMMENT: Please provide this additional ROW information on your next submittal.

6. 2-06.4.9.H.5 - If utilizing parking area access lanes (PAALs), they shall be designed in accordance with Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC.
COMMENT: The use of gravel surfacing must be approved by Engineering staff. Additionally, it is unclear how UDC 7.4.6.H is being met. Additional comments may be forthcoming.

7. 2-06.4.9.H.5.a - Show all motor vehicle off-street parking spaces provided, fully dimensioned. As a note, provide calculations on the number of spaces required (include the ratio used) and the number provided, including the number of spaces required and provided for the physically disabled. The drawing should indicate parking space locations for the physically disabled. A typical parking space detail shall be provided for both standard parking spaces and those for the physically disabled. For information on parking requirements for the physically disabled, refer to adopted building and accessibility codes of the City of Tucson. Design criteria for parking spaces and access are located in Section 7.4.6, Motor Vehicle Use Area Design Criteria, of the UDC.

COMENT: Per Table 7.4.4-1, the parking requirement provided is not correct. For multifamily between 2-5 units, one space per unit is required. Additionally, please provide EV (Section 7.4.11) and ADA parking calcs and a clear depiction of their location on the site plan. Dimensions of all proposed parking spaces on site is required.

8. 2-06.4.9.H.5.d - Show bicycle parking facilities fully dimensioned. For specifics, refer to Section 7.4.9, Bicycle Parking Design Criteria, of the UDC. Provide, as a note, calculations for short and long term bicycle spaces required and provided.
COMMENT: Provide dimensions that show compliance with UDC Section 7.4.9.E.2

9. 2-06.4.9.I - Show all right-of-way dedications on or abutting the site and label. If the development package documents have been prepared in conjunction with a subdivision plat or is required as a condition of approval of a review process, such as a rezoning, street dedications in accordance with the Major Streets and Routes (MS&R) Plan may be required by these processes.
COMMENT: This project is located on a N Swan Rd which is a designated MS&R. Future dedication may be required. See Comment 10.

10. Projects bounded by streets having only a portion of the right-of-way width dedicated will be required to dedicate right-of-way, up to one-half, to complete the street width.
COMMENT: N Swan Rd has a future width of 120ft and appears to currently only be 90ft. Clearly indicate the future property line and identify any future dedication that may be required.

11. 2-06.4.9.O - All applicable building setback lines, such as erosion hazard, floodplain detention/retention basins, and zoning, including sight visibility triangles, will be shown.
COMMENT: The setback requirements provided in General Note 8 are incorrect.

12. 2-06.4.9.Q - Provide the square footage and the height of each commercial, industrial, or business structure and the specific use proposed within the footprint of the building(s).
COMMENT: Sqft must be shown within the footprint of each structure on the site plan.

13. 2-06.4.9.R - Show on-site pedestrian circulation and refuge utilizing location and the design criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards Manual.
COMMENT: There are numerous issues with the proposed pedestrian paths on site. A Pedestrian path cannot cross directly behind a designated parking space. Additionally, each unit must have pedestrian access and since this site is located at an intersection of two streets, a connection out to N Swan Rd will be required.

14. 2-06.4.9.S - Show existing or proposed pedestrian circulation along abutting rights-of-way. Such sidewalks must comply with accessibility requirements for the physically disabled and the design criteria in Section 10-01.0.0, Street Technical Standards, of the Technical Standards Manual.
COMMENT: Show existing sidewalk along N. Swan Rd.

If you have any questions about this transmittal, please contact me at Nicholas.Ross@tucsonaz.gov or (520) 837-4029.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
03/12/2025 CDRC Application Completeness Express REVIEW COMPLETED
03/21/2025 CDRC Review Coordinator Express REVIEW COMPLETED CDRC added Addressing, TEP, PAG, USPS, and SWG to the workflow. Review request email sent to Addressing, and TEP. FYI email sent to PAG, USPS, SWG.
03/26/2025 External Reviewers - Pima Association of Governments Standard REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
03/24/2025 External Reviewers - Pima County Addressing Standard REVIEW COMPLETED Good morning,



Pima County Addressing approves TD-DEV-0325-00078.



Units 1 and 2 at 4705/4711 E Fairmount ST are issued and in PimaMaps.



Nicholas Jordan

Site Review Project Manager II – Addressing Official

Pima County Development Services Department

201 N Stone AV – 1st Floor

Tucson, AZ 85701

(520) 724-9623
03/26/2025 External Reviewers - Southwest Gas Standard REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
05/09/2025 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED May 9, 2025
WO#T147119
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Savannah Court
TD-DEV-0325-00078
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 3/21/2025. There are no existing facilities within the development. There
are no apparent conflicts at this time.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
If easements are required, they will be secured by separate instrument. Should you
have any easement questions, please contact our Land Resources Department,
LandReviews@tep.com.
Should you have any technical questions, please contact the area designer,
Martin Salazar
(520) 305-6713
msalazar@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
03/26/2025 External Reviewers - United States Postal Service (USPS) Standard REVIEW COMPLETED CDRC sent FYI email sent to PAG, USPS, SWG. No further action is required.
04/14/2025 Fire New Construction Standard REVIEW COMPLETED
03/20/2025 OK to Submit - Engineering Fast REVIEW COMPLETED
03/14/2025 OK to Submit - Zoning Fast REVIEW COMPLETED
03/26/2025 ROW Review REVIEW COMPLETED