Permit Number: TD-DEV-0325-00070
Parcel: 116206340

Address:
115 S LINDA AV

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW REVISION v.2

Permit Number - TD-DEV-0325-00070
Review Name: DEVELOPMENT PACKAGE NEW REVISION v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/29/2026 Design Review Standard APPROVED PDF file of Design Professional's Review available in the TDC account and PRO.
06/26/2026 Site Landscape Standard APPROVED
06/11/2026 Site Engineering Standard REQUIRES RESUBMIT Permit Activity Number: TD-DEV-0325-00070 (1st Review)
Project: Rev 1 - update to parking, grading, slope, irrigation, utilities, started 05.08.2026 ** New 3-story multi-family residential building
Location: 115 S LINDA AV
Review Date: 6/11/2026
Reviewer: Marco Contreras – Engineering Associate
Reviewer Contact Information: marco.contreras@tucsonaz.gov
Related cases:

Plan review for the above-referenced development package has been completed. This review was conducted for compliance with applicable development criteria including the City of Tucson Unified Development Code (UDC), Administrative Manual (AM) Section 2-6, and Technical Standards Manual (TSM) sections governing waste management, pedestrian access, hydrology – retention/detention requirements, and all applicable site standards.
The following comments must be addressed prior to approval. To help facilitate a timely resubmittal, please provide updated plans and calculations along with a written response to each comment, indicating what action was taken and where the change can be found on the plans. Do not use revision clouds on resubmittal drawings — clouds are reserved for post-permit revisions only. Submit your response letter and updated plan set & reports as separate files.

Applicable Code Links for quick/direct reference:
City of Tucson Code: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes
Floodplain Code: https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az/0-0-0-19333
Drainage Manual Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/cot-drainage-manual-searchable.pdf
Design standards for Stormwater Detention and Retention Link:
https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf
City of Tucson Chapter 25: https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az/0-0-0-18593

Site Engineering Review Comments:
1. Provide a geotechnical statement from the geotechnical engineer certifying that the proposed Swale to the West of the structure would be advisable & compliant with overall geotechnical analysis. The report describes that positive drainage should be maintained at least 10-ft beyond the perimeter of the building. Per the Drainage Manual 7.6.5 – buildings are to be setback 10-feet from drainage swales. It may be determined that the swale may need to be grouted to prevent Signiant infiltration near the building foundation.
07/06/2026 Site Zoning Standard REQUIRES RESUBMIT CDRC TRANSMITTAL

FROM:
Bobby Parsons
PDSD Zoning Review Section

PROJECT:
Linda Avenue Apartments
Development Package (1st Revision Review)
TD-DEV-0325-00070

TRANSMITTAL DATE: 7/6/2026
DUE DATE: 7/3/2026

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is May 12, 2027.

SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

Zoning and Land Use Notes

2-06.4.8.B - All easements shall be drawn on the plan. The recordation information, location, width, and purpose of all easements on site will be stated. Blanket easements should be listed in the notes, together with recordation data and their proposed status. Should an easement not be in use and be proposed for vacation or have been abandoned, so indicate. However, should the easement be in conflict with any proposed building location, vacation of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided.

1. COMMENT: 2-06.4.8.B – As a new TEP easement is being proposed on Sheet 5, please include the recordation information as noted by the standard above.

***For additional information on the any standard presented in this memo, please refer to the City of Tucson “Unified Development Code” – Administrative Manual Section 2-06 or Technical Standards noted in the comments. https://www.tucsonaz.gov/pdsd/all-codes-plans-determinations

If you have any questions about this transmittal, Contact Bobby Parsons at Robert.Parsons@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package and comment response letter. To resubmit visit Tucson Development Center at https://tdc-online.tucsonaz.gov/#/home.
Instructions for resubmittal - https://www.tucsonaz.gov/files/pdsd/website/Resubmittals.pdf.
07/02/2026 Commercial Plumbing Standard REVIEW COMPLETED
06/16/2026 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED 4350 E. Irvington Road
Post Office Box 711, Tucson, AZ 85702
June 16, 2026
WO#T145555
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: Linda Avenue Apartments
TD-DEV-0325-00070
Tucson Electric Power Company (TEP) has reviewed and approved the development
plan submitted 6/11/2026. There are existing facilities within the development which are
depicted upon the plan. COMMENTS ONLY PLEASE INDICATE APPROVAL WITH
THE BELOW CHECK BOX PLEASE DO NOT ADJUST IF THERE ARE NO
COMMENTS Further: Approved with requirement that primary duct will be installed a
minimum of 3 feet below the rainwater harvesting basin floor.
Enclosed is a copy of a TEP facilities map showing the approximate location of the
existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-
8300. Please submit a final set of plans including approved site, electric load, paving
off-site improvements and irrigation plans. If available, include a PDF version of the
plans.
Questions regarding Land, ROW, Easement, etc., please contact the TEP Land
Department
Liz Boehler
Right of Way Agent
Consultant
520-686-1341
Landreviews@tep.com
Should you have any technical questions, please contact the area designer,
Fred Quintero
(520) 235-6329
fquintero@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
07/13/2026 ROW Engineering Review Standard REVIEW COMPLETED