Permit Number: TD-DEV-0325-00070
Parcel: 116206340

Address:
115 S LINDA AV

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.2

Permit Number - TD-DEV-0325-00070
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/18/2025 Commercial Plumbing Standard APPROVED
07/01/2025 External Reviewers - COT Environmental Services Standard APPROVED
06/09/2025 ROW Engineering Review Standard APPROVED
07/01/2025 CDRC Post Review Express PENDING ASSIGNMENT
06/17/2025 Design Review Standard REQUIRES RESUBMIT review.
06/24/2025 Fire New Construction Standard REQUIRES RESUBMIT IFC 507.5.1.1 (2024). Fire hydrant is required within 100' of fire dept connections when buildings is equipped with a standpipe system. Show location of fire dept connections and measurement to hydrant.
john.vincent@tucsonaz.gov
5203495581
06/24/2025 Site Engineering Standard REQUIRES RESUBMIT 1. See that zoning comments are addressed.
2. Per previous comment 2 - show the easement on the plans along with the recordation information.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
06/26/2025 Site Landscape Standard REQUIRES RESUBMIT CDRC TRANSMITTAL
PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, RLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: NEW 3-STORY MULTIFAMILY RESIDENTIAL BUILDING
ACTIVITY NO: TD-DEV-0325-00070
ADDRESS: 115 S LINDA AV
ZONING: C-3 COMMERCIAL ZONE
LAND USE: MULTIFAMILY

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants, and water harvesting.

Please resubmit revised drawings along with a detailed response letter, which states how all of the Site Landscape/NPPO Section review comments have been addressed.

SITE LANDSCAPE/NPPO SECTION COMMENTS:

1. Once the Special District review (SD-0525-00076) comments are addressed and all revisions have been reflected on the Development Package, then Site Landscape will approve the plan set.

Thank you.
Chad Keller, RLA
Landscape Architect
chad.keller@tucsonaz.gov
520.837.4923
06/24/2025 Site Zoning Standard REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT: Linda Avenue Apartments
Development Package (2nd Review)
TD-DEV-0325-00070

TRANSMITTAL DATE: June 24, 2025

DUE DATE: June 23, 2025

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC) Administrative Manual (AM) Section 2-06. Also, compliance with applicable development criteria for the proposed use as listed in the City of Tucson Uniform Development Code (UDC) and the UDC Technical Standards Manual (TSM).

Section 3.3.3.G.5.c UDC, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One-year Expiration date is March 19, 2026.

2-06.4.7 - General Notes
The following general notes are required. Additional notes specific to each plan are required where applicable.

2-06.4.7.A - Zoning and Land Use Notes

1. Until approved by all review agencies Zoning cannot approve this DP. COMMENT: 2-06.4.7.A.6 - As you are proposing to use the Infill Incentive District (IID) and Individual Parking Plan (IPP) processes, these processes must be approved prior to approval of the DP.

2. Until approved by all review agencies Zoning cannot approve this DP. COMMENT: 2-06.4.7.A.6 – As this site is located within the Rio Nuevo Area (RNA) RNA review is required and must be approved prior to approval of the DP.

2-06.4.9 - Information on Proposed Development
The following information on the proposed project shall be shown on the drawing or added as notes.

3. This comment was not addressed. Provide a dimension from the enclosure to the PAAL. COMMENT: 2-06.4.9.H.5 – Demonstrate that the requirements of UDC Article 7.4.6.F.2.b are met from the PAAL east to the trash enclosure.

4. Until approved by all review agencies Zoning cannot approve this DP. COMMENT: 2-06.4.9.H.5.a – The required number of vehicle parking spaces is 96, proposed is 29. The IPP will need to be approved prior to approval of this DP.

5. This comment was not addressed. No dedication was found on sheet 1 and no easement details were provided on sheet 2, as stated in your response to comments. COMMENT: 2-06.4.9.L – As access is proposed across the parcel to the south some type of recorded easement/agreement is required. Provide a copy of the recorded document with the next submittal. If this is done via an easement show the easement on the plan along with the recordation information.

6. Until approved by all review agencies Zoning cannot approve this DP. COMMENT: 2-06.4.9.O – The required west street perimeter yard setback is 20’ and the proposed is 1.1’. The IID will need to be approved prior to approval of this DP.

Additional Comments

7. Until approved by all review agencies Zoning cannot approve this DP. COMMENT: - As you are proposing to exceed the allowed density in the C-3 Zone, allowed dwelling units is 44, proposed 49. The IID must be approved prior to approval of the DP.

8. Per a discussion with the Zoning Administrator provide the following general note on the plan, “Any construction happening on adjacent private property (whether within easement area or not) will need written permission from the property owner”.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf.
06/09/2025 Transportation Landscape Review Standard REVIEW COMPLETED Comments on plans, these will be available after all reviewers are complete