Permit Number: TD-DEV-0324-00092
Parcel: 14117008A

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE NEW v.1

Permit Number - TD-DEV-0324-00092
Review Name: DEVELOPMENT PACKAGE NEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
09/11/2026 External Reviewers - COT Parks & Recreation Standard APPROVED CDRC

Approved

Regarding TD-DEV-0324-00092, the City of Tucson Parks and Recreation Department has no additional requirements for the Project and no further reviews by TPRD are required.

Parcel: 14117008A

Regards,
Joe Barr
Project Manager
Tucson Parks and Recreation
520-307-2811
09/11/2026 NPPO Standard APPROVED
08/25/2026 TSMR/PDMR - Engineering APPROVED
09/17/2026 CDRC Post Review Express PENDING ASSIGNMENT
09/09/2026 Commercial Plumbing Standard REQUIRES RESUBMIT The use of saddle-type fittings is prohibited by the IPC, use directional wye fittings to connect the building sewers to the private sewer main. Reference: Section 707.1 (6), IPC 2024 and Pima County Standard Detail RWRD 401, 2021.

If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov.
08/26/2026 Site Engineering Standard REQUIRES RESUBMIT Permit Activity Number: TD-DEV-0324-00092 (1st Review)
Project: Houghton-Willow Center, lots 1-7 and CA "A"
Location: 7655 S HOUGHTON RD
Review Date: 8/26/2026
Reviewer: Marco Contreras – Engineering Associate & Joe Macaulay – Civil Engineer
Reviewer Contact Information: marco.contreras@tucsonaz.gov
Related cases:

Plan review for the above-referenced development package has been completed. This review was conducted for compliance with applicable development criteria including the City of Tucson Unified Development Code (UDC), Administrative Manual (AM) Section 2-6, and Technical Standards Manual (TSM) sections governing waste management, pedestrian access, hydrology – retention/detention requirements, and all applicable site standards.
The following comments must be addressed prior to approval. To help facilitate a timely resubmittal, please provide updated plans and calculations along with a written response to each comment, indicating what action was taken and where the change can be found on the plans. Do not use revision clouds on resubmittal drawings — clouds are reserved for post-permit revisions only. Submit your response letter and updated plan set & reports as separate files.

Applicable Code Links for quick/direct reference:
City of Tucson Code: https://www.tucsonaz.gov/Departments/Planning-Development-Services/Codes
Floodplain Code: https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az/0-0-0-19333
Drainage Manual Link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/cot-drainage-manual-searchable.pdf
Design standards for Stormwater Detention and Retention Link:
https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/engineering-code/updated-retention-detention-manual.pdf
City of Tucson Chapter 25: https://codelibrary.amlegal.com/codes/tucson/latest/tucson_az/0-0-0-18593

Site Engineering Review Comments:
1. This site is bounded by Houghton RD. This road can be found on the Major Streets & Routes plan and identified as a Scenic Corridor. As such, this site is covered by the Scenic Corridor Zone (SCZ). It is acknowledged that the General note required by this is provided:
a. Per UDC 5.3.4.A.1 and 3., “A buffer area 30 feet wide, adjacent to the MS&R future right-of-way line, is required and shall be preserved and maintained in its natural state…” and “The buffer area shall be restored as closely to its natural state as possible In areas where public safety or the delivery of public services precludes preservation of existing vegetation…” Draw, dimension, and label the 30-foot SCZ setback area on the site/grading plan.
b. UDC 5.3.4.C, describes permitted improvements within the SCZ setback area, Driveways or access lanes, if their area does not exceed 20% of the Scenic Routes Buffer Area (Buffer Area). In this instance, the width of the Buffer Area is 30 feet in accordance with Section 5.3.4.A.1. For the purposes here, the Buffer Area is calculated as follows: Multiply the distance of the property’s along the measured at the by 30 feet. If, due to topographical or engineering constraints, the or exceeds 20% of the Buffer Area, the width of the Buffer Area shall be increased to accommodate the square footage resulting from the following calculation: (Distance of the along the measured at the - total width of or ) x 24 feet = Required Buffer Area in square feet.
c. Ensure to update/revise all applicable details that show encroachment into the Scenic Buffer area.
2. ADA Grading note – Revise the keynote provided, the City of Tucson adopted The IBC 2024 with ICC A117.1 2017 edition at the beginning of 2026. This will need to be addressed across the plan set where IBC 2018 w/
3. Site plan and grading plan sheets – revise the plans to show and dimension the setback distance of the existing electric infrastructure from the proposed basin at the Northeast portion of the proposed development. This setback will have to be compliant to ensure no adverse impacts from the proposed infiltration area in regard to affecting the established towers and structures.
4. Regarding the CMU wall proposed directly north of water harvesting basin and west of the Lot 1 - When a wall is proposed within 5 feet of the horizontal location of the 100-year water depth, a report from an engineer registered in the State of Arizona shall be provided prior to approval of the construction permit that contains at least the following: a. The appropriate minimum setback from the top of slope; and b. Specific structural design requirements with details.
5. Revise/Update keynote 19 on sheet 8 – the clearance space for a double enclosure is required to be a minimum of 28ft X 40ft.
6. Pedestrian circulation is required to connect all buildings, dumpster areas, common areas, and the sidewalk on all the street frontages [TSM 7-01.3.3]. Demonstrate how this requirement is addressed for connecting the site to the proposed trash enclosure at the NE corner of the proposed site for lot 1.
7. Sidewalks shall be flood free for all storm discharges of up to and including a ten-year frequency flood event. Drainage flowing across all pedestrian circulation paths shall be conveyed under the path for up and including the ten-year frequency flood events, except at street intersections, pedestrian crossings, and PAAL pedestrian crossings [TSM 7-01.4.1.E]. This will need to be addressed regarding the SW side of proposed building on Lot #1 – a downspout (Keynote #34) is shown to be directly discharging on the concrete sidewalk at this section. Revise accordingly.
8. Provide a complete trash enclosure construction details in compliance with TSM 8-01.5.0. Details must address wall materials, wall height, gate type and swing, foundation, and enclosure dimensions. It is strongly encouraged that the figures presented in TSM 8-01.9.0 be used as the minimum basis for the enclosure and dumpster layout details shown on the plans.
a. If it is desired to proceed with the “Modified Dumpster Enclosure” as shown - Environmental services approval will be required in regard to accepting that they will have no issues with the proposed modified requirements. The current proposal shows the enclosure with finalized dimensions that differ from the standard double enclosure detail. The contact to reach out to at ES will be Andy Vera at Andy.vera@tucsonaz.gov. Please submit the approval provided for the resubmission of this development package.
b. If approval is provided, it will be necessary that a Technical Standards Modification Request (TSMR) be included in resubmission.
09/11/2026 Site Landscape Standard REQUIRES RESUBMIT PLANNING AND DEVELOPMENT SERVICES DEPARTMENT
REVIEWER: CHAD KELLER, PLA
SITE LANDSCAPE/NATIVE PLANT PRESERVATION SECTION

PROJECT: HOUGHTON-WILLOW CENTER, LOTS 1-7 AND CA "A"
ACTIVITY NO: TD-DEV-0324-00092
ADDRESS: 7661 S HOUGHTON RD
ZONING: HEAVY INDUSTRIAL ZONE (I-2)
LAND USE: COMMERCIAL AUTOMOTIVE SERVICE AND REPAIR CENTER
9.11.2026

THE PROPOSED PLANS HAVE BEEN REVIEWED FOR COMPLIANCE WITH APPLICABLE DEVELOPMENT STANDARDS FOR SITE LANDSCAPE, NATIVE PLANTS, AND RAINWATER HARVESTING, PER-THE-CITY OF TUCSON UNIFIED DEVELOPMENT CODE (UDC), TECHNICAL STANDARDS MANUAL (TSM), AND ADMINISTRATIVE MANUAL (AM).

RESUBMIT REVISED DRAWINGS ALONG WITH A DETAILED RESPONSE LETTER, STATING HOW ALL SITE LANDSCAPE AND NPPO SECTION REVIEW COMMENTS HAVE BEEN ADDRESSED.

SITE LANDSCAPE/NPPO SECTION COMMENTS:

1. COMMENT: UDC 5.3.4 SCENIC BUFFER AREA: The 30-foot scenic buffer area is supposed to be revegetated with only native vegetation and laid out in a way that looks like the natural desert. With that being said per a conversation with site zoning, and similar projects along the same scenic buffer corridor, the scenic buffer can’t be used for drainage basins. An option would be to move the basin to the east 30 feet and leave the scenic buffer relatively flat with the naturalized plantings and hydroseeding. As always, I’m open to having a conversation about this issue. Please don’t hesitate to reach out to myself and/or the site zoning reviewer if you would like to discuss the Scenic Corridor Zone further.

2. On the rainwater harvesting plan, include a few of the spot elevations and drainage flowlines within the hardscape areas as shown on the grading plan for quick schematic reference.

3. Include a note on the rainwater harvesting plan to see the civil grading plan for drainage scheme and drainage structure implementation, e.g. curb cut detail.

4. Include a quick schematic detail or cross-section of one of the WHIA for general information. Mimic detail 1/grade transition and include plant placement, maximum slope, screened rock depth, depth of WHIA from hardscape flowline to top of screened rock, and anything else that you see fit for clarity for contractor and inspector quick reference during construction.

5. The irrigation pipe sleeves and the asphalt hatch are the same gray color, making the sleeves hard to see. Please update the line type or change the color of the asphalt hatch for clarity.

6. Prior to site landscape approval, ensure that Site Zoning and Site Engineering comments are fully addressed.

7. Include the Activity Number TD-DEV-0324-00092 on all sheets in the plan set.

Thank you.

CHAD KELLER - PLA
LANDSCAPE ARCHITECT

CITY OF TUCSON - PDSD
CHAD.KELLER@TUCSONAZ.GOV
520.837.4923
09/17/2026 Site Zoning Standard REQUIRES RESUBMIT CDRC TRANSMITTAL

REVIEWED BY:
Fernando Garcia
PDSD Site Zoning Review Section

PROJECT:
Commercial Development
Development Package (1st Review)
TD-DEV-0324-00092 (7661 S Houghton Rd, Tucson, AZ 85747)

TRANSMITTAL DATE: September 17, 2026

Per UDC Section 3.3.3.G.5.c, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year expiration date is August 13, 2027.

SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)


4.1.B.4 Note the number of proposed lots and common areas. If the subdivision is a FLD, a condominium, or a similar type of residential subdivision utilizing special provisions of the UDC, it shall be noted;

1. COMMENT: 2-06.4.1.B.4 – Provide requested information regarding number of lots and common areas in general notes.


2. COMMENT: 2-06.4.2.D – Correct the use-specific standards that apply to the proposed Trade Service & Repair, Major use. It should site that the use is “subject to use-specific standards 4.9.4.X.1 and 4.9.13.Q per UDC Table 4.8-5.”

Also indicate that “Commercial Storage” is “subject to use-specific standards 4.9.10.A and 4.9.13.Q per UDC Table 4.8-5”.


4.2.I. Percentage of building, lot area, or vehicular use area expansion, including previous expansions. When the proposed site is part of a larger site, the calculations encompass the entire site, whether existing or proposed.

3. COMMENT: 2-06.4.2.I – Provide requested information regarding percentage of expansions as compared to existing improvements on the site (on Lot 2).


4.7.B Identify all lots within the project/subdivision with the parcel identification number (if recorded), block or lot number within the subdivision boundary, total square footage, and lot line boundaries with approximate distances and measurements.

4. COMMENT: 2-06.4.7.B – Close the western property line for Common Area A on the reference site plan on Sheet 1.


5. COMMENT: 2-06.4.7.G – Per UDC 5.3.4.A.2., “No development or improvements shall occur in a Scenic Route buffer area except as provided in Section 5.3.4.C, Permitted Improvements; (See Figure 5.3-B.)” Drainage and flood control facilities are NOT a permitted improvement within the 30’ SCZ buffer area. The site must be redesigned to move the totality of the proposed basin outside of the buffer area.

Per UDC 5.3.4.A.3, the buffer area shall be restored as closely to its natural state as possible in areas where public safety or the delivery of public services precludes preservation of existing vegetation. Although the basin must be moved from this area, it must still be restored per the revegetation guidelines provided in 5.3.4.D.

Per UDC 5.3.9.C., “When an existing devel is expanded by 50% or more in floor area or land area, new and existing utilities to all portions of the development shall be located underground unless relief is otherwise granted pursuant to UDC sections 5.3.14, Variances and/or through a Zoning Examiner special exception process…” Expansion is cumulative.


4.7.I All easements (utility, sewer, drainage, access, etc.) shall be drawn, dimensioned, and labeled on the plan. The recordation information, location, width, and purpose of all easements on site will be stated. Blanket easements should be listed in the notes, together with recordation data and their proposed status. Indicate if any existing easements are proposed to be abandoned or vacated. Should an existing easement be in conflict with any proposed building location, vacation of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided. The easements may have to be recorded and the recordation information added to the development package prior to approval. Obtain review for conflicts and written concurrence from existing easement holder(s). Said written concurrence must be present as a part of the final package for approval or evidence that the easement will be moved resulting in no additional conflicts.

6. COMMENT: 2-06.4.7.I – Cite recordation number for abandonment of 15’ water easement; prior to final inspection condition may be placed.


4.7.S Show on-site pedestrian circulation and refuge utilizing location and the design criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards Manual.

7. COMMENT: 2-06.4.7.S – Pedestrian circulation is required, per TSM 7-01.3.3, to connect all areas of a development, to enclosure dumpster enclosures. None is currently shown to the dumpster enclosures from the main building.


RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Please resubmit revised drawings and any corrected plans along with a detailed response letter, stating how all Site Zoning Review comments were addressed.

**Instructions for resubmittal - www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/tdc-faq/new-pdfs/revisions-and-resubmittals.pdf.

***For additional information on the standards presented in this memo, please refer to the City of Tucson Administrative Manual Section 2-06 or Technical Standards noted in the comments.

If you have any questions about this transmittal, please contact Lead Planner, Site Zoning, Fernando Garcia at fernando.garcia2@tucsonaz.gov
08/13/2026 CDRC Application Completeness Express REVIEW COMPLETED
08/18/2026 CDRC Review Coordinator Express REVIEW COMPLETED CDRC added Parks, Addressing, PAG, SWG, USPS, and TEP to the workflow. FYI notices sent out to , PAG, SWG, USPS, and TEP.
08/18/2026 External Reviewers - Pima Association of Governments Standard REVIEW COMPLETED CDRC sent FYI Notice email sent. No further action is required.
08/21/2026 External Reviewers - Pima County Addressing Standard REVIEW COMPLETED Good afternoon,

Pima County Addressing approves of TD-DEV-0324-00092. Please note that the new project address will be 7661 S Houghton Rd. The current project address will be retained for the existing building on site.

The 7661 S Houghton Rd address will be active once our invoice is paid P26AD00655.

Thank you,










David Wilging

Planner I - Addressing Division

Pima County Development Services

201 N. Stone Avenue 1st Floor

Tucson, Arizona 85701

520-724-6381

**Please update the address to reflect the correct address of 7661 S Houghton Rd. on all pages of the plan set and related documentation.
08/18/2026 External Reviewers - Southwest Gas Standard REVIEW COMPLETED CDRC sent FYI Notice email sent. No further action is required.
08/18/2026 External Reviewers - Tucson Electric Power (TEP) Standard REVIEW COMPLETED CDRC sent FYI Notice email sent. No further action is required.
08/18/2026 External Reviewers - United States Postal Service (USPS) Standard REVIEW COMPLETED CDRC sent FYI Notice email sent. No further action is required.
09/09/2026 Fire New Construction Standard REVIEW COMPLETED
08/14/2026 OK to Submit - Engineering Fast REVIEW COMPLETED
08/17/2026 OK to Submit - Zoning Fast REVIEW COMPLETED
09/09/2026 ROW Engineering Review Standard REVIEW COMPLETED
08/26/2026 TSMR/PDMR - Zoning REVIEW COMPLETED
08/20/2026 TW New Development Review REVIEW COMPLETED TUCSON WATER HAS NO OBJECTION TO THE PROPOSED LAND DIVISION. THE PROPOSED LOT CONFIGURATION IS CONSISTENT WITH THE ACCEPTED 2026 MASTER WATER PLAN FOR HOUGHTON-WILLOW CENTER, WHICH INCLUDES LOTS 1-2, C.A. “A” (JOINT ACCESS AND UTILITIES), AND C.A. “B” (DRAINAGE AND LANDSCAPE). PREVIOUS TUCSON WATER COMMENTS HAVE BEEN ADDRESSED.