Permit Review Detail
Review Status: Approved
Review Details: DEVELOPMENT PACKAGE NEW v.2
Permit Number - TD-DEV-0224-00052
Review Name: DEVELOPMENT PACKAGE NEW v.2
Review Status: Approved
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/11/2024 | External Reviewers - COT Parks & Recreation | APPROVED | Approved TD-DEV-0224-00052 Address: (744 E 39TH ST TUCSON, AZ 85713) City of Tucson Parks and Recreation has no additional requirements for the Development Plan. Regards, Joe Barr Project Manager Tucson Parks and Recreation | ||
03/21/2024 | External Reviewers - Tucson Airport Authority | APPROVED | March 21, 2024 Planning and Development Services City of Tucson 201 North Stone Avenue Tucson, AZ. 85701 RE: TD-DEV-0224-00052, Application is for a new shade structure at each of the enclosed parks / 744 E 39th St, Tucson, AZ. 85713, Received March 7, 2024 To whom this may concern, Thank you for the opportunity to comment on TD-DEV-0224-00052, a development plan for constructing a new shade structure at an existing park at 744 East 39th Street. This development is located in the N.W. quarter of the N.W. quarter of Section 30, Township 14S, Range 14E, of the Gila and Salt River Meridian. The development site occupies parcel number 129-14-164A, covers approximately 0.806 ± acres, and is zoned as Residence 3 Zoning (R-3). The nearest major roadway intersection is East 39th Street and South Euclid Road, approximately 50 feet to the northeast of the subject development. This site does lie within the Tucson International Airport avigation easement requirements and public disclosure area, FAA traffic pattern airspace, and FAA Part 77 airspace. The Tucson Airport Authority approves the proposed project and is not requiring a resubmittal. Please do not hesitate to contact me if you have any questions or concerns regarding this comment letter. I can be reached by email at srobidoux@flytucson.com or by telephone at 520-573-4811. Respectfully, Scott Robidoux, C.M. Manager of Planning | ||
03/21/2024 | ROW Engineering Review | APPROVED | No Comments David Stiffey David.Stiffey@tucsonaz.gov |
||
03/21/2024 | Site Engineering | APPROVED | |||
03/21/2024 | Site Landscape | APPROVED | |||
03/21/2024 | Site Zoning | APPROVED | |||
03/22/2024 | Commercial Plumbing | NOT REQUIRED | |||
03/18/2024 | Fire New Construction | NOT REQUIRED | |||
03/21/2024 | NPPO | NOT REQUIRED | |||
03/05/2024 | CDRC Application Completeness Express | REVIEW COMPLETED | |||
03/22/2024 | CDRC Post Review Express | REVIEW COMPLETED | |||
03/07/2024 | CDRC Review Coordinator Express | REVIEW COMPLETED | Review request email sent per ADOT, TAA and Parks&Rec. CDRC sent FYI email to PAG, USPS, SWG, and TEP. | ||
03/21/2024 | External Reviewers - Arizona Department of Transportation (ADOT) | REVIEW COMPLETED | Good Morning, ADOT has no comments on this DEV. Thank you for the opportunity to review. |
||
03/07/2024 | External Reviewers - Pima Association of Governments | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
03/07/2024 | External Reviewers - Southwest Gas | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
03/07/2024 | External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
03/07/2024 | External Reviewers - United States Postal Service (USPS) | REVIEW COMPLETED | CDRC sent FYI email to PAG, USPS, SWG and TEP. No further action is required from the customer at this time. | ||
03/07/2024 | OK to Submit - Zoning Fast | REVIEW COMPLETED |