Permit Review Detail
Review Status: Requires Resubmit
Review Details: DEVELOPMENT PACKAGE REVIEW v.3
Permit Number - TD-DEV-0223-00141
Review Name: DEVELOPMENT PACKAGE REVIEW v.3
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/02/2023 | Site Engineering | APPROVED | |||
08/29/2023 | TSMR/PDMR - Engineering | APPROVED | |||
08/24/2023 | TSMR/PDMR - Traffic Engineering | APPROVED | No Comments (TRMR is Approved) David Stiffey David.Stiffey@tucsonaz.gov |
||
08/29/2023 | TSMR/PDMR - Zoning | APPROVED | |||
09/07/2023 | CDRC Post Review | PENDING ASSIGNMENT | |||
09/05/2023 | Commercial Plumbing | REQUIRES RESUBMIT | Comment not resolved. If the distance from the rim of the cleanout to the pipe invert is 5-feet, the maximum horizontal distance to the next cleanout opening would be 95-feet. You show four sections of the building sewer that are too long. [Initial comment: The maximum distance between cleanouts shall be 100-feet, measured along the developed pipe length from the upstream entrance of the cleanout. Reference: Section 708.1.1, IPC 2018.] | ||
08/04/2023 | Fire New Construction | REQUIRES RESUBMIT | -Per IFC table B105.1(2) fire flow for IIB/14380 square feet, unsprinklered, is 2500 for 2hrs. You have 1500 on the coversheet. -You have three hydrants which is correct. Just need the fire flow data on the coversheet corrected. thanks john.vincent@tucsonaz.gov 5203495581 |
||
09/07/2023 | NPPO | REQUIRES RESUBMIT | Please revise the NPPO Plan to closer match the sample plan sent over via email. If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988 |
||
09/07/2023 | Site Landscape | REQUIRES RESUBMIT | Please revise the Commercial Rainwater Harvesting Plan to closer match the sample plan sent over. If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988 |
||
08/31/2023 | Site Zoning | REQUIRES RESUBMIT | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Wyatt Berger Lead Planner PROJECT: TWC Tucson Development Package (2nd Review) TD-DEV-0223-00141 TRANSMITTAL DATE: August 31, 2023 DUE DATE: August 31, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This plan has been reviewed for compliance with the Unified Development Code (UDC), Administrative Manual (AM) Section 2-06, and the Technical Standards Manual (TSM). Per UDC Section 3.3.3.G.5.c, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year expiration date is August 31, 2024. 1. COMMENT: 2-06.4.8.B – Provide the abandonment information for the easements proposed to be vacated. A hold will be placed on the Certificate of Occupancy of the proposed building until the abandonment information is provided. 2. COMMENT: 2-06.4.9.H.5.a – This comment was not entirely addressed. The proposed handicapped accessible parking signs conflict with the use of wheel stop curbing. An unobstructed clearance of two and one-half feet is required from the front of the wheel stop to the sidewalk curb. A minimum unobstructed clearance of four feet is still required for the pedestrian circulation path. 3. COMMENT: 2-06.4.9.R – This comment was not entirely addressed. The required pedestrian path along the south wall of the proposed building is required to be a minimum of four feet wide (TSM 7-01.4.3.A). If you have any questions about this transmittal, please contact me at Wyatt.Berger@tucsonaz.gov or at (520) 837-4951. RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/pdsd/website/Resubmittals.pdf. |
||
08/01/2023 | CDRC Application Completeness | REVIEW COMPLETED | |||
08/24/2023 | Traffic Engineering Review | REVIEW COMPLETED | No Comments David Stiffey David.Stiffey@tucsonaz.gov |